2007 Supreme(Del) 1319

High Court Of Delhi
A. K. SIKRI
G. S. LUTHRA - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondents
CS (OS) 2227 Of 1993
Decided On : 07/06/2007

Advocates Appeared:
ANUSUYA SALWAN, MONICA SHARMA, RAMAN KAPUR

The main legal point established is that delays and breaches attributable to one party in a construction contract entitle the other party to compensation under the Indian Contract Act.

Headnote:

Arbitration - Construction Contract - Arbitration Act,1940 - Section 14, 17, 30, 33 - Clause 25 of the General Conditions of contract - Sections 73 and 74 under the Indian Contract Act, 1872

Fact of the Case:

The plaintiff participated in a construction contract with the Delhi Development Authority (DDA) in 1981. The work got prolonged beyond the stipulated period, and the DDA cancelled the work in 1987. The plaintiff filed for arbitration, and the Arbitrator rendered an Award in 1993. The DDA filed objections under the Arbitration Act, which were contested by both parties.

Finding of the Court:

The court found in favor of the plaintiff, upholding the Arbitrator's award. The court analyzed each claim and rejected the objections raised by the DDA, emphasizing that the delays and breaches were attributable to the DDA, entitling the plaintiff to compensation under the Indian Contract Act.

Issues: Delay in construction, Breach of contract, Arbitration proceedings, Objections under the Arbitration Act

Ratio Decidendi: The court held that the delays and breaches were caused by the DDA, justifying the compensation awarded to the plaintiff under the Indian Contract Act. The court also emphasized that the Arbitrator's award was reasonable and well-justified.

Final Decision: The court upheld the Arbitrator's award and modified the rate of interest, making it a Rule of the Court.

A. K. SIKRI, J.

( 1 ) THE Delhi Development Authority (Objector) herein floated tenders for the construction of a Player's Building Phase-1 in 1981. The plaintiff also participated and was successful as its tender was accepted by the DDA vide letter dated June 18,1981. Formal agreement was also signed between the parties. The construction work under this contract was to be completed within eleven (11) months. However, as it has become a common feature, this contract also got prolonged much beyond the stipulated period. The work continued till 1984 and was not completed even by that time. According to the plaintiff, between 1984 and 1987 the DDA did not give any instruction regarding the work and it remained in suspended animation. In 1987, the plaintiff received letter dated May 12,1987 from the DDA cancelling the work.

( 2 ) AS per the plaintiff its dues were not settled and had many claims against the dda for the alleged breaches committed by the DDA because of which the work got delayed and ultimately not rescinded without even allowing the plaintiff to complete the work. In view of the Clause 25 of the General Conditions of contract which is an arbitration clause, the plaintiff requested for appointment of Arbitrator. As the needful was not done, Suit No. 934a/1988 was filed in this court in which orders dated September 13, 1988 were passed directing the Member engineer to appoint an Arbitrator in terms of Clause 25 of the Contract. Arbitrator was appointed pursuant to these directions. The Arbitrator, however, resigned and thereafter in his place another Arbitrator was appointed who also without completing the arbitration proceedings resigned. Ultimately Shri r. J. Bakhru was appointed as the Sole Arbitrator who has rendered the Award dated september 15,1993.

( 3 ) AFTER receiving the notice from the Arbitrator of making and publishing the award, the plaintiff filed Suit No. 2227a/93 which is an application under section 14 and 17 of the Arbitration Act,1940. Directions were given in this case to the Arbitrator to file the Award. After the Arbitrator filed his Award, notice of filing the award was issued to the parties. The plaintiff has accepted the Award as it chose not to file any objections. However, DDA has preferred to file objections under Sections 30 and 33 of the Arbitration Act which are registered as IA. 1117/94. Both the counsel made their submissions qua these objections.

( 4 ) FIRST objection is to the award of amount against Claim No. 1. Under this claim, a sum of Rs. 860665/- was demanded as loss of profit due to curtailment of scope of work. A sum of Rs. 394922/- is awarded by the learned Arbitrator. It was the submission of the learned counsel for the DDA that no work was done after August,1984 as accepted in the Award itself and, therefore, it amounted to abandoning the work by the plaintiff. Under these circumstances, if work was formally rescinded on 12. 5. 1987 it was not open to the plaintiff to claim 'loss of profit'.

( 5 ) THERE is no dispute that execution of work was delayed. There is also no dispute that between 1984 and 1987 no work was carried. The plaintiff blamed the DDA for this state of affairs alleging that it happened due to hindrances, lapses, default and failures on the part of DDA to perform their obligation. It would be of importance to note that this contention of the plaintiff found favour with the learned Arbitrator. He has, inter alia, arrived at a finding to the effect that there was a delay in handing over complete and clear site due to delay in completion of work of pile foundation executed by other agency; the site was handed over in parts from time to time with the result the work in entire area could not be taken up immediately; there were delays in giving drawings and designs, revised drawings, detailed specifications, clarifications which were given in piecemeal; there was delay in making payment of escalation in price of material and labour under Clause 10 (c) and












Click Here to Read the rest of this document