SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2007 Supreme(Del) 1565

144 (2007) DELHI LAW TIMES 686
DELHI HIGH COURT
Dr. S. Muralidhar, J.
HARINDER ANAND – Petitioner
versus
DELHI DEVELOPMENT AUTHORITY & ORS. – Respondents
W.P. (C) No. 5073 of 2003 and W.P. (C) No. 11878 of 2006
Decided on : 2.8.2007

Advocates appeared:
For the Petitioner:Mr. Sandeep Sharma, Advocate.
For the Respondent:Mr. Bhupesh Nantla, Advocate.

The main legal point established in the judgment is that the proper remedy for challenging demands raised by the DDA under the PLRA is to file suits in the Civil Court and raise all possible grounds available in law.

Headnote:

DDA - Recovery of Arrears of Land Revenue - Punjab Land Revenue Act, 1887 (PLRA) - Section 68

Fact of the Case:

The Delhi Development Authority (DDA) raised demands against the petitioners for recovery of sums of money as arrears of land revenue under Section 68 of the Punjab Land Revenue Act, 1887 (PLRA). The petitioners challenged the demands, arguing that the DDA could not invoke the provisions of PLRA to recover the amounts.

Finding of the Court:

The court found that the writ petitions under Article 226 were not maintainable as the demands were covered by the judgment of the Division Bench of the court in a similar case. The court held that the proper remedy available to the petitioners was to file suits in the Civil Court and challenge the demands on all possible grounds available to them in law.

Issues: The main issue was whether the DDA could invoke the provisions of PLRA to recover the amounts from the petitioners.

Ratio Decidendi: The court relied on the judgment of the Division Bench of the court in a similar case, which indicated that the DDA could recover the amount in any manner open to it, and the contractor could file a suit and raise all such contentions as deemed fit. The court also noted that the challenge to the impugned demands as being violative of the principles of natural justice could be raised before the Civil Court.

Final Decision: The writ petitions were dismissed as not maintainable, and the petitioners were advised to file suits in the Civil Court to challenge the demands.

JUDGMENT

Dr. S. Muralidhar, J. (Open Court)-The challenge in these writ petitions are to demands raised by the Delhi Development Authority (DDA) against the petitioners for a recovery of certain sums of money as arrears of land revenue under Section 68 of the Punjab Land Revenue Act, 1887 (PLRA). The principal ground of such challenge is that since the work contracts entered into by the DDA with the petitioners, out of which these demands arise, does not contain any clause that permits the DDA to recover such amounts. It is contended that in any event the DDA cannot invoke the provisions of PLRA to recover such amounts.

2. The facts in both writ petitions are more or less similar. For convenience, the facts of the first petition, Writ Petition (C) No. 5073 of 2003 are discussed in some detail. By a contract dated 28.2.1989 entered into with the DDA, the petitioner was awarded the work of "Development of Local Shopping Centre at Madangir." The work commenced on 10.3.1989 and was to be completed within four months. For various reasons, which need not be gone into in these proceedings, the work could not be completed within the stipulated period. It was rescinded on 9.3.1990. The disputes between the parties was, in terms of the contract, referred to arbitration. Before the Arbitrator, the DDA filed, inter alia, counter claims against the petitioner. These included a claim in the sum of Rs. 1,34,130/- "on account of compensation levied under Clause 2 of the contract." The Arbitrator, by an award dated 6.8.1993, held that the action of the DDA in levying compensation under Clause 2 of the contract was unwarranted and accordingly disallowed the counter claim. When, by a petition filed by the petitioner in this Court, the award was sought to be made a rule of Court, the DDA questioned this portion of the award on the ground that the Arbitrator could not have adjudicated upon the claim for compensation under Clause 2 of the Contract as it was an excepted matter. This Court upheld the objection of the DDA by its decision dated 15.11.1999; Harinder Anand v. Delhi Development Authority, 83 (2000) DLT 391=2001 (1) Arb.LR 319 (Delhi). This Court followed the judgment of the Division Bench of this Court in Delhi Development Authority v. M/s. Sudhir Brothers, 57 (1995) DLT 474 (DB)=1995 (2) Arb.LR 306 (DB). Accordingly, the portion of the award dealing with DDAs claim for compensation under Clause 2 of the contract was set aside.

3. all. 27.3.2003 the DDA issued to the petitioner the impugned demand notice invoking Section 68 of the PLRA. The petitioner wrote to the Assistant Collector, Grade-I, DDA on 2.6.2003 protesting against the impugned demand on the ground that the delay, if any, in completion of the contract is attributable to the DDA and that the DDA could not invoke the provisions of the PLRA for recovering the amount. In response to the petitioners letter dated 2.6.2003, the DDA on 18.7.2003 filed a rejoinder before the Assistant Collector contending that the amount was recoverable under the PLRA. Further, it was claimed that after the order of this Court dated 15.11.1999 became final the validity of such demand could not be reexamined.

4. Thereafter the petitioner filed the present writ petition on 1.8.2003. While directing notice to issue on 11.8.2003, this Court stayed the impugned demand.

5. The facts in the accompanying petition [Writ Petition (C) 11878 of 2006] are more or less similar except for a difference in the dates of the award and the impugned demand notice.

6. Mr. Sandeep Sharma, learned Counsel appearing for the petitioners submits that in terms of Clause 2 of the Contract, the DDA could only determine the amount of compensation which according to it was payable.

The said clause does not permit the DDA to recover the amount of compensation so determined. DDA will have to fie a separate suit for recovering the amount. In support of his submission Mr. Sharma relied upon the judgment of this Court in V.K. Mittal v. Assista

















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top