SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2009 Supreme(Del) 843

164 (2009) DELHI LAW TIMES 388
DELHI HIGH COURT
Rajiv Sahai Endlaw, J.
VEDA RESEARCH LABORATORIES LTD. – Petitioner
versus
SURVI PROJECTS – Respondent
OMP No. 10 of 2007
Decided on : 6.8.2009

Advocates appeared:
For the Petitioner:Mr. Rajesh Banati and Mr. Hari Mohan, Advocates.
For the Respondent:Mr. Pradeep Jain, Director of tile petitioner company with Mr. R. Rajappan and Ms. Reyasine, Advocates.

The main legal point established in the judgment is the criteria for granting interim measures under Section 9 of the Arbitration Act, including the need to establish a prima facie case, potential irreparable injury, and the balance of convenience.

Headnote:

Arbitration Act - Interim Measures - Section 9, Section 34 - [Section 9, Section 34] - The court discussed the provisions of Section 9 and Section 34 of the Arbitration Act, 1996 and emphasized the criteria for granting interim measures, including prima facie case, irreparable injury, and balance of convenience. The court also referred to legal precedents to support its decision.

Fact of the Case:

The respondent filed an application seeking interim measures under Section 9 of the Arbitration Act, 1996, claiming that the petitioner was siphoning off business to another company to defeat the arbitral award. The petitioner denied the allegations and argued that the application should not be entertained at this stage.

Finding of the Court:

The court found that the respondent had made a case for interim measures based on the substantial fall in the petitioner's business and the potential irreparable injury. The court also considered the balance of convenience and granted the application, restraining the petitioner from alienating its factory premises.

Issues: The main issues were whether the respondent had established a prima facie case for interim measures under Section 9, and whether the petitioner's actions posed a risk of irreparable injury to the respondent.

Ratio Decidendi: The court held that the respondent's success in the arbitral award constituted a prima facie case for interim measures, and the substantial fall in the petitioner's business demonstrated potential irreparable injury. The court also considered the balance of convenience in granting the application.

Final Decision: The court allowed the respondent's application for interim measures under Section 9 of the Arbitration Act, restraining the petitioner from alienating its factory premises.

ORDER

I.A No. 8776 of 2007 (of the respondent under Section 9 of the Arbitration Act. 1996) in OMP No. 1012007 under Section 34 of the Arbitration Act, 1996

1. Mr. Pradeep Jain, Director of the petitioner company is present in compliance to the directions on the last date. The objection of the Counsel for the petitioner that the application under Section 9 ought to have been filed by way of an independent has already been rejected on the last date. The Counsel for the parties have been heard.

2. The petitioner has preferred this petition under Section 34 of the Act with respect to a unanimous arbitral award dated 28th September, 2006 of a Arbitral Tribunal comprising nominees of each of the parties and the third arbitrator appointed, by this Court vide order dated 12th December, 2002 in an application under Section 11(6) of the Act. It is not in dispute that under the said award as on the date of filing of this application, a sum of approximately Rs. 60 lacs is due from the petitioner to the respondent.

3. The respondent has filed this application seeking interim measures during the pendency of this petition and till the award is enforced. It is contended, that the petitioner is a closely held Private Limited Company; that the share holders and Directors of the petitioner company, with a view to defeat the award against them, have set up another, company namely MI s. Bio Veda Research Laboratory Private Limited and have been siphoning off the business of the petitioner company to the said other company; in the event of the petition being decided against the petitioner, making the execution of the award as a decree a virtual impossibility. It is, contended by the respondent that if the petitioner succeeds in its designs, even in the event of the respondent succeeding in these proceedings would be left with a paper award or decree.

4. The petitioner has filed a reply to this application. Though it is not disputed therein that the share holders and Directors of the petitioner company are also the share holders and Directors and in control of the other company namely M/s. Bio Veda Research Laboratory Pvt. Ltd. but it is denied that any case of siphoning off the assets is made out. It is contended that the other company was incorporated as far back as in July, 1999 and it is not as if the other company was incorporated after the arbitral award.

5. The Counsel for the petitioner has today urged that the respondent has not beer: able to make out any case of diversion of funds/siphoning off assets. It is also urged that ?-n application under Section 9 of the Act is generally filed before the making of the award and ought not to be entertained at this stage. It is next contended that for the respondent to be entitled to any interim measures, it has to pass the same tests as under Order 39 Rules 1 and 2 of the CPC, i.e. of prima facie case, irreparable injury and balance of convenience. It is urged that the respondent has no prima facie case the arbitral award allows escalation to the respondent in spite of there being no clause for the same in the agreement; it is stated that the arbitrators have allowed other claims which were not certified by the architect and which was prerequisite for the said claims being entertained/allowed. The Counsel, for the petitioner has in this regard relied upon Maharwal Khewaji Trust (Regd.), Faridkot v. Haldev Dass, IV (2004) CLT 172 (SC)=VI (2004) SLT 366=AIR 2005 SC 104, Adhunik Steels Limited v. Orissa Manganese and Minerals Private Limited, VI (2007) SLT 538=III (2007) CLT 287 (SC)=AIR 2007 SC 2563; and Transmission Corporation of A.P. Limited v. Lanco Kondapalli Power (Private) Limited, 1(2006) SLT 95=1 (2006) CLT 86 (SC)=(2006) 1 SCC 540.

6. As far as Maharwal Khewaji Trust (Regd.), Faridkot is concerned, that was a case of interim orders in appeal. The Supreme Court therein inter alia held that without a case of irreparable loss being made out, injunction could not be granted merely on the ground of the

















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top