2010 Supreme(Del) 628
IN THE HIGH COURT OF DELHI AT NEW DELHI
JUSTICE S. MURALIDHAR
BASANT BAGDE ..... Petitioner
versus
HINDUSTAN PREFAB LIMITED & ORS ..... Respondents
W.P.(C) 13836/2009 & CMs 15675-78/09, 9603-04 /2010
Reserved on: 20th September 2010
Decision on: 27th September 2010
Subject
Contract Disputes - Cancellation of Contract
Act Referred
Headnote
Constitution of India, 1950 - Article 226 - Notice inviting sealed percentage rate tender (`NIT') for construction of houses - Order cancelling the six packages - Obligation to furnish a performance guarantee in a construction contact cannot possibly be linked to outstanding payments against completed works of other contracts between the parties - It is not possible for court to render a finding on the quality of construction and to simply accept the report of the expert cited by the Petitioner - For the illegal termination of a construction contract the only relief that can be granted is of damages if at all - Writ petition dismissed.
Dr. A.M. Singhvi, Senior Advocate with Mr. Amit Anand Tiwari and Mr. Amit Bhandari, Advocates.
Mr. Manoj Sharma with Mr. Sarad Jha and Mr. Sumit Bhardwaj, Advocates for R-1 and R-2. Mr. A.P. Mayee and Ms. Praveena Gautam, Advocates for R-3 with Mr. V.P. Sharma, Deputy CEO, SUDA.
1. This is the second round of litigation involving the parties stemming from the award to the Petitioner, by the Respondent No.1 Hindustan Prefab Limited (`HPL), the contract of construction of low cost houses in eleven packages, in two lots of five and six packages each, at Raipur in Chhattisgarh. This time around, the petitioner seeks a writ of certiorari to quash the decision of the HPL conveyed by its letter dated 16th September 2009 cancelling six of the eleven packages awarded to the Petitioner. This petition also seeks a writ of mandamus directing the Respondents “not to cancel the contract of the Petitioner in respect of the remaining five packages.”
2. The background to the present petition under Article 226 of the Constitution is that on 20th March 2008 HPL issued a notice inviting sealed percentage rate tender („NIT) for construction of houses under the Basic Services for Urban Poor (`BSUP) Scheme of Jawaharlal Nehru National Urban Renewal Mission (`JNNURM) in Raipur City. Clause 5 of the Special Conditions of Contracts (`SCC) required the tenderer to quote rates on percentage basis “(below/at par/over) Madhya Pradesh (Chhattisgarh) Schedule of Rates, 1999.” Clause 11.01 of the NIT provided that in case of percentage rate tenders, “the tenderer should quote a unique single percentage (plus/at par/minus) over the total estimated amount given in the schedule/bill of quantities.” It further stated that “under no circumstances, such a tenderer is allowed to quote separate percentages for individual items, trades or group of items.” 2a. The Petitioner states that prior to the above NIT dated 20th March 2008, HPL had already invited four tenders with respect to the same project. However, no contract could be awarded since the bids received were non-competitive. On 1st April 2008, the Competent Authority, i.e., the Engineer-in-Chief of Public Works Department (PWD), Chhattisgarh amended the Madhya Pradesh (Chhattisgarh) Schedule of Rates, 1999 (`SOR) for building works in PWD by enhancing the rate of Item No. 8 of Chapter No. IV (Steel) from `24 per kg to` 50 per kg.
3. It is stated that on 3rd April 2008 the Petitioner submitted six tenders on percentage rate basis. The quoted rates were 109% above the SOR, after taking into account the amended rates. The tenders were opened on that very day. The lowest (L-1) bidder was awarded seven packages out of total 18 packages at the rate of 59% of SOR. It is stated that on 9th May 2008, the HPL negotiated with the Petitioner in terms of Clause 7 of NIT. The Petitioner was asked to submit his acceptance for executing the contract at the L-1 rate. In response thereto, by a letter dated 9th May 2008 the Petitioner agreed to quote its rates at the L-1 price which was 59% above SOR, subject to grant of a minimum of five packages.
4. It is stated that the HPL entered into an Agreement dated 7th June 2008 with the Petitioner at Delhi whereby five packages were awarded to the Petitioner. This entailed the Petitioner having to construct in each package 1536 dwelling units (DUs). The total time period was 18 months. A supplementary agreement was entered into on 23rd August 2008 for the remaining six packages of the NIT.
5. The Petitioner states that he commenced the work and submitted his first running account bill to the HPL. In the said bill, the Petitioner while quoting the rates of steel, took into account the rate of steel as amended up to 1st April 2008 by the Competent Authority. However, HPL refused to entertain any claim on the basis of the revised rates of steel, and conveyed this by its letter dated 18th September 2008.
6. Aggrieved by the above decision dated 18th September 2008, the Petitioner filed a Writ Petition (Civil) No. 7044 of 2008 before this Court. On 19th March 2009 a learned Single Judge of this Court dismissed the writ petition on the ground that the Petitioner had an alternative remedy by way of arbitration. It was further held that this Court did not have t