High Court of Delhi
S. MURALIDHAR
Bharat Sanchar Nigam Limited
Versus
Himachal Futuristic Communications Limited.
O.M.P. 427 of 2006
Decided on : 30-05-2012
Arbitration and Conciliation Act - BSNL - 34 - Summary of the acts and sections referenced and discussed by the court: The court discussed Section 34 of the Arbitration and Conciliation Act, 1996 and the terms and conditions of the Purchase Order (PO) including the imposition of Liquidated Damages (LD) and the extension of the delivery period. The court also considered the provisions of the General Conditions of Contract (GCC) and the implications of unilateral changes in the terms and conditions of purchase.
Fact of the Case:
The case involved a dispute between BSNL and HFCL arising from a Purchase Order for the supply of MARR systems. HFCL was granted extensions for delivery but failed to meet the deadlines, leading to a dispute over payment and Liquidated Damages (LD). The court analyzed the contract terms, delivery delays, and price adjustments.
Finding of the Court:
The court found that HFCL had accepted the conditions of the extension of time for delivery, including the reduced price, without protest. The court held that BSNL did not act arbitrarily in terminating the contract and that HFCL was in breach of the contract terms by failing to deliver the contracted quantities within the stipulated time.
Issues: The key issues included the acceptance of the extension conditions by HFCL, the implications of the delivery delays, and the validity of the price adjustments. The court also considered the applicability of public policy and the legal principles governing contract enforcement.
Ratio Decidendi: The court's decision was based on the finding that HFCL had accepted the modified contract conditions without protest, and therefore, BSNL's actions were not arbitrary. The court emphasized that in the realm of contract law, there is no room for the application of principles of reasonableness and non-arbitrariness flowing from Article 14 of the Constitution.
Final Decision: The court set aside the Arbitral Award dated 1st June 2006, ruling in favor of BSNL and ordering HFCL to pay costs of Rs. 10,000 within four weeks.
1. The Petitioner Bharat Sanchar Nigam Limited (‘BSNL’) has in this petition under Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’) challenged an Award dated 1st June 2006 passed by the learned sole Arbitrator in the dispute between it and the Respondent Himachal Futuristic Communications Limited (‘HFCL’), formerly known as Himachal Telematics Limited (‘HTL’), arising out of a Purchase Order (‘PO’) dated 22nd February 1996 for supply of 148 numbers of 4/36 MARR systems in UHF range along with accessories. By the impugned Award the sole Arbitrator held that HFCL was entitled to be paid the differential amount subject to deduction of 5% Liquidated Damages (‘LD’) for supplies made during the extended delivery period as claimed by HFCL together with simple interest at 6% per annum from the date when payment became due till the actual date of payment. HFCL was also held entitled to the return of the Performance Bank Guarantee (‘PBG’) dated 11th December 1995 for a sum of Rs.42 lakhs.
Background Facts
2. A tender was invited for procurement of 1125 systems each of 2/15 and 4/36 analog MARR system of UHF band along with accessories by the BSNL. The tender was opened on 20th June 1995 and HTL was found to be a technically and commercially eligible bidder. An Advance Purchase Order (‘APO’) dated 24th November 1995 was placed on HTL for the supply of 136 numbers package of 2/15 Shared Radio System and 148 numbers of package of 4/36 MARR system at a package price of Rs.3,20,897 and Rs.10,11,360 respectively. The APO was amended by a letter dated 27th November 1995 only in respect of PBG. By its letter dated 12th December 1995 HTL accepted the APO unconditionally only for 4/36 MARR systems and submitted a PBG for Rs.42 lakhs at 5% of the total value of 148 numbers of 4/36 MARR systems.
3. On the basis of acceptance of the APO, a PO was placed on HTL on 22nd February 1996 for supply of 148 numbers of 4/36 MARR systems in UHF range. The delivery schedule was up to three months from the date of issue of PO or two months from the date of issue of frequencies.
4. In accordance with the terms and conditions applicable to the PO, HTL had to obtain type approval from the Department of Telecommunications (‘DOT’) (QA) prior to the start of supplies to the consignees. The consignee details were also furnished along with the PO. The delivery period was said to be firmed and was not subject to any change. Clause 13.1 of Section III of the General Conditions of Contract (‘GCC’) provides as under:
“The purchaser may, at any time, by a written order given to the supplier, make changes within the general scope of the contract in any one or more the following:
(a) Drawing, designs or specifications, where goods to be furnished under the contract are to be specifically manufactured for purchaser;
(b) The method of transportation or packing;
(c) The place of delivery; or
(d) The service to be supplied by the supplier.”
5. On 4th June 1996, BSNL furnished frequency details and revised consignee details to HTL in respect of 146 numbers of 4/36 MARR systems i.e. (98.6% of the ordered quantity). The frequency and consignee details in respect of balance two numbers were furnished on 28th August 1996. By a letter dated 17th June 1996, BSNL enquired about the probable timeframe by which the systems would be supplied to the Circles.
6. By a letter dated 9th August 1996, HFCL informed BSNL that the frequency and consignee details have been received by it in respect of 146 numbers of 4/36 MARR systems only on 26th June 1996. Accordingly, it is requested that the delivery period of the above referred order be extended “up to two months from the issue of letter”. BSNL was also informed that HTL has been amalgamated with HFCL and issuance of suitable amendment to the PO to the above effect was requested.
7. On 9th October 1996, DOT wrote to HFCL extending the delivery period by two months “with levy of liquidated damage charges”. Further
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.