SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(Del) 978

High Court of Delhi
PRADEEP NANDRAJOG, PRATIBHA RANI, JJ.
Gail (India) Ltd.
Versus
Surya Roshini Ltd.
FAO(OS) 357 of 2007
Decided On : 11-04-2012

Advocates Appeared:
For the Appellant:Jagjit Singh, Advocate.
For the Respondents:Samrat Nigam, & Ms. Ankita Mahajan, Advocates.

The main legal point established in the judgment is the interpretation of contractual provisions regarding reimbursement for pipe failure under field hydrostatic test and the liability of the seller for providing equipment necessary for the functioning of the pipeline.

Headnote:

Arbitration - Contract Dispute - Article 20.3.2 of General Conditions of Contract - [Arbitration] - [Contract Dispute] - [Article 20.3.2] - The court discussed the interpretation of Article 20.3.2 of the General Conditions of Contract, which deals with reimbursement for pipe failure under field hydrostatic test. The court highlighted the reimbursement cost, overall limit for reimbursement, and consequential damages due to failure. The court held that the seller is bound to provide equipment, fittings, and accessories necessary for a satisfactory functioning of the pipeline, and allowed all claims raised by GAIL except claim No.5 and reduced claim No.4. The court rejected claim No.5 in the sum of `61,72,728/- as the pipeline was meant to connect tap off point at village Chainsa with the power plant of the NTPC at Ballabhgarh, and the de-rating of the pipes did not affect its profitability.

Fact of the Case:

The case involved a contract dispute between Gas Authority of India Ltd. (GAIL) and Surya Roshni Ltd. regarding the supply of natural gas at a power plant. GAIL claimed reimbursement for expenses incurred due to the failure of pipes during field hydrostatic test and sought damages for the difference in the cost of line pipes supplied by Surya Roshni Ltd.

Finding of the Court:

The court allowed all claims raised by GAIL except claim No.5 and reduced claim No.4. The court rejected claim No.5 in the sum of `61,72,728/- as the pipeline was meant to connect tap off point at village Chainsa with the power plant of the NTPC at Ballabhgarh, and the de-rating of the pipes did not affect its profitability.

Issues: The main issue was the interpretation of Article 20.3.2 of the General Conditions of Contract and the liability of Surya Roshni Ltd. for the failure of pipes during field hydrostatic test.

Ratio Decidendi: The court held that the seller is bound to provide equipment, fittings, and accessories necessary for a satisfactory functioning of the pipeline. The court also emphasized that the de-rating of the pipes did not affect the profitability of GAIL, leading to the rejection of claim No.5.

Final Decision: The court dismissed the appeal and affirmed the judgment of the learned Single Judge, holding that the award passed by the Arbitrator did not warrant any interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment :

PRADEEP NANDRAJOG, J.

1. This is an appellate challenge to the award dated April 19, 2007 passed by the learned Sole Arbitrator insofar claim in sum of `61,72,728/-on account of the stated price difference between the costs of the pipe line actually laid and what was required to be laid has been declined.

2. The appellant, Gas Authority of India Ltd.(GAIL) had an agreement with National Thermal Power Corporation (NTPC) to supply natural gas at its power plant in village Mujheri, district Faridabad, Haryana, and for which, from the main pipeline already laid by GAIL from Bijapur to Dadri, a tap had to be provided at the said main line by GAIL at village Chainsa wherefrom the respondent/contractor, Surya Roshni Ltd. Had to lay down a 14 KM spur pipe-line of 14 inch diameter connecting the point of tap with the plant of NTPC in village Mujheri. This was as per a contract entered into between GAIL and Surya Roshni Ltd. The tender documents, gave in detail the chemical composition of the steel pipes, the tensile strength etc., and suffice would it be to highlight that the steel pipes were required to withstand a design pressure of 92 kg. per square centimeter and a hydrostatic pressure of 129 kg. per square centimeter. The thickness of the steel sheets of which pipes were to be fabricated was to be 6.4 mm. Surya Roshni Ltd. laid down the pipe-line and when subjected to field hydrostatic test, by removing three pipe segments and subjecting them to field hydrostatic test, all three pipes failed the test inasmuch as much before the stipulated pressure was reached the pipes burst at the seam. As informed to us during arguments of the appeal, the pipes burst due to poor quality of welding when steel sheets were rolled to form a cylinder and the edges welded. It was a case of loose welding, as informed to us, and this explaining the pipes notwithstanding the requisite pressure and bursting at the seam.

3. Since time was running out for GAIL to comply with its contractual obligations with NTPC, the long drawn out process of replacing the entire 14 KM pipe-line was opined to be a counter-productive rectification procedure and a viable alternative found out was to de-rate the entire spur line to design pressure of 58.27 kg. per square centimeter and this required works to be executed at the tap of terminal at village Chainsa for safe operation of the pipe-lines at low pressure. Of course, the three pipes which had burst while conducting the field tests had to be replaced.

4. GAIL took resort to the latter and claimed six amounts under six different heads from Surya Roshni Ltd. which disputed liability. Proceeding to encash the performance guarantee in sum of `15,84,357/-, GAIL filed a civil suit against Surya Roshni Ltd. and since the contract between the parties had an arbitration clause, being Article 30.4.1 of the General Conditions of Contract, the dispute was referred to the sole arbitration of Justice Anil Dev Singh (Retd.), before whom GAIL submitted a statement of claim having an element of principal sums claimed and pre-claim interest. The principal sums claimed were as under:-S.No. Particulars Amount (in `)

5. The stand taken by Surya Roshni Ltd. before the learned Arbitrator was that in view of Article 20.3.2 of General Conditions of Contract it is only liable to reimburse GAIL for the cost incurred by it for replacing the pipes which had burst during field hydraulic test to the extent of 10% of the value of contract but is not liable to pay any damages to GAIL on account of failure of pipes during field hydraulic test.

6. As evident from the aforesaid, the controversy involved in the present case necessitated the interpretation of Article 20.3.2 of the General Conditions of Contract,

S.No. Particulars Amount (in `)

1. Cost of replacement of three burst pipe(s). Cost of one quoted price of M/s Krupp Hoesch Stahlen Port, GmbH used for replacing one burst pipe. 40,222.59

2. Costs of 2 quoted price of Respondent us



















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top