High Court of Delhi
MANMOHAN SINGH, J.
Delhi Airport Metro Express Pvt Ltd.
Versus
CAF India Pvt Ltd. & Another
I.A. No. 10776 of 2014 in CS(OS) 1678 of 2014
Decided on : 14-08-2014
ARBITRATION - INTERNATIONAL COMMERCIAL ARBITRATION - ARBITRATION CLAUSE - VALIDITY - PUBLIC POLICY - SECTION 5 OF THE ARBITRATION AND CONCILIATION ACT, 1996 - SECTION 14(2) OF THE SPECIFIC RELIEF ACT, 1963 - SECTION 23 AND 28 OF THE INDIAN CONTRACT ACT, 1872 - ASSIGNMENT AGREEMENT - NOVATION - JOINT PROMISSORS - SECTION 43 OF THE INDIAN CONTRACT ACT, 1872.
Fact of the Case:
Plaintiff, a Special Purpose Vehicle incorporated for operating the Delhi Airport Metro Express Line, entered into a Rolling Stock Supply Contract and a Maintenance Services Agreement with Defendant No.2, a Spanish company. The Maintenance Contract contained an Arbitration Clause providing for arbitration under the rules of the International Chamber of Commerce, Paris (ICC), with the seat of arbitration in London and excluding the application of Part I of the Arbitration and Conciliation Act, 1996 (the Act). Defendant No.2 assigned the Maintenance Contract to Defendant No.1, its wholly owned subsidiary. Plaintiff terminated the Concession Agreement and the Maintenance Contract. Disputes arose between the parties. Defendant No.1 commenced arbitration proceedings against Plaintiff at ICC, London, jointly with Defendant No.2. Plaintiff filed a suit seeking a declaration that the Arbitration Agreement was illegal, null and void, and unenforceable, and a permanent injunction restraining the defendants from pursuing the arbitration proceedings. Defendants contended that the suit was barred by Section 5 of the Act and Section 14(2) of the Specific Relief Act, 1963, and that the Arbitration Clause was valid and enforceable.
Finding of the Court:
The Court held that the assignment agreement did not novate the Maintenance Contract and that Defendant No.2 continued to be a participant in the agreement. The Court found that the nature of the arbitration proceedings remained the same, i.e., international commercial arbitration, and that the parties could not be faulted for excluding Part I of the Act. The Court also held that the Arbitration Clause was not illegal or unenforceable under the laws of India or against the public policy of India. The Court dismissed the Plaintiff's application for an interim injunction and clarified that the parties could continue with the arbitral proceedings in accordance with the law.
Issues: 1. Whether the assignment agreement novated the Maintenance Contract and discharged the obligations of Defendant No.2 under the Maintenance Contract? 2. Whether the nature of the arbitration proceedings changed from international commercial arbitration to domestic or local arbitration? 3. Whether the Arbitration Clause was illegal or unenforceable under the laws of India or against the public policy of India? 4. Whether the suit was barred by Section 5 of the Act and Section 14(2) of the Specific Relief Act?
Ratio Decidendi: 1. The assignment agreement did not novate the Maintenance Contract and Defendant No.2 continued to be a participant in the agreement. The assignment agreement was executed in furtherance of the Maintenance Agreement and not to novate or alter the same so as to discharge the obligations contained in the Maintenance Agreement. 2. The nature of the arbitration proceedings remained the same, i.e., international commercial arbitration, as Defendant No.2 continued to be a party to the Maintenance Agreement. The parties could not be faulted for excluding Part I of the Act as the proceedings were in the nature of international commercial arbitration only and not domestic or local arbitration. 3. The Arbitration Clause was not illegal or unenforceable under the laws of India or against the public policy of India. The parties had agreed to the ICC Arbitration Rules, which provided that the arbitral tribunal was empowered in all respects to decide the question related to its jurisdiction and other preliminary matters. 4. The suit was barred by Section 5 of the Act, which limits the extent of judicial interference in arbitration proceedings. The Arbitration Clause was not against the public policy of India and the parties could not be relegated to arbitrate in a foreign court excluding Indian laws altogether.
Final Decision: The Court dismissed the Plaintiff's application for an interim injunction and clarified that the parties could continue with the arbitral proceedings in accordance with the law.
Manmohan Singh, J.
1. This is a suit for declaration and permanent injunction filed by the plaintiff against the defendants seeking declaration that the arbitration agreement under the contract between plaintiff and defendant No.1 is illegal, null and void and unenforceable; the commencement of the arbitration proceedings by the defendants at London before ICC is null, void and of no legal consequence; and a permanent injunction restraining the defendants from pursuing the arbitration proceedings at ICC London. Along with the suit an application being I.A. No. 10776/2014 under Order 39 Rule 1 and 2 CPC was also filed.
2. Brief facts for the purpose of adjudication of the present matter are that the Plaintiff Company is a Special Purpose Vehicle incorporated for the purposes of operating the Delhi Airport Metro Express Line (hereinafter referred to as the "Project"). The Project connects the Indira Gandhi International Airport, New Delhi, India with the city of New Delhi.
3. For the purpose of bidding in a tender issued by the Delhi Metro Rail Corporation (hereinafter referred to as “DMRC”) for award of the Project, Reliance Infrastructure Limited (hereinafter referred to as "Reliance") and Construcciones Y Auxiliar De Ferrocarriles, SA (Defendant No.2) formed a consortium. The consortium's bid for the Project was accepted and it was awarded the Project on 21st January 2008. Pursuant to the requirements of the bid, the consortium incorporated the plaintiff with Reliance holding 95% equity and defendant No.2 holding the remaining 5%. Subsequently, the Concession Agreement was executed between the plaintiff and DMRC on 25th August, 2008 (hereinafter referred to as the "Concession Agreement”) for implementing the Project.
4. Pursuant to the Concession Agreement, the plaintiff and defendant No.2 entered into a Rolling Stock Supply Contract dated 30th June 2008 (hereinafter referred to as the “supply contract”) for supply of Rolling Stock for the Project. The plaintiff and defendant No.2 also entered into the Maintenance Services Agreement dated 30th June 2008 ("Maintenance contract") for the purpose of maintenance of the Rolling Stock. The Maintenance Contract contained a Dispute Resolution clause (hereinafter referred to as the "Arbitration Clause"). The same is reproduced as following :
"ARTICLE 14
DISPUTE RESOLUTION
14.1 In case of disputes, the Parties hereby agree to exhaust all informal senior level determination mechanisms before submitting a request to settle them under the formal dispute resolution system.
14.2 Any dispute arising in connection with the interpretation or performance of this Contract shall be finally settled by arbitration under the rules of the International Chamber of Commerce, Paris (“ICC”). The Arbitration Tribunal shall consist of three arbitrators.
One arbitrator shall be nominated by each of the Parties and the third arbitrator shall be a person nationality and origin other than India or Spain, and shall be appointed by the ICC in accordance with the “Rules of ICC as Appointing Authority in UNCITRAL or Adhoc Arbitration Proceedings”;
14.3 The arbitration shall take place in London and the language of the arbitration shall be English.
14.4 The Parties expressly exclude the application of Part 1 of the Indian Arbitration and Conciliation Act 1996.
14.5 Continuation of performance;
Pending final resolution of any dispute, the Parties shall continue to perform their respective obligations hereunder
14.6 Governing Law and Jurisdiction:
14.6.1 This Contract shall be governed by and construed in accordance with the laws of India.
14.7 Survival
14.7.1 It is expressly stated herein that the provisions of this Article 14 shall survive termination or expiry of this Contract.”
5. It is stated in the plaint that subsequently, defendant No.2 vide Assignment Agreement dated 17th May, 2010 (hereinafter referred to as the "Assignment Agreement") novated the Maintenance Contract in favour of defendant No.1 wh
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.