SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(Del) 960

IN THE HIGH COURT OF DELHI AT NEW DELHI
S. MURALIDHAR, J.
THDC HYDRO DEVELOPMENT CORPORATION LIMITED – Petitioner
Versus
M/S. BHAGIRATHI BUILDERS ENGINEERS AND CONTRACTORS – Respondent
O.M.P. 20 of 2008
Decided On : 21-03-2017

Advocates Appeared:
For the Petitioner:Mr. Sachin Dutta, Senior Advocate with Ms. Pritya Sharma, Advocate with Mr. Sushhil Kumar, Law Officer
For the Respondent:Mr. Sandeep Sharma with Ms. Devyani Sharma, Advocates

The court found no grounds for interference with the arbitration award, emphasizing the importance of upholding the arbitrator's decisions and the need for parties to raise objections at the appropriate time.

Headnote:

THDC filed a petition challenging an arbitration award passed by the Sole Arbitrator. The dispute arose from a construction contract, and the Respondent filed an arbitration application under Section 11 of the Act. The Sole Arbitrator passed two awards, and THDC raised objections to the jurisdiction and status of the Respondent. The court dismissed THDC's petition, finding no grounds for interference with the award.

JUDGMENT :

1. This is a petition by Tehri Hydro Development Corporation Limited (THDC) against the Respondent, M/s Bhagirathi Builders Engineers and Contractors, under Section 34 of the Arbitration & Conciliation Act, 1996 (‘the Act’) challenging an Award dated 22nd September, 2007 passed by the Sole Arbitrator.

Background facts

2. THDC invited tenders for construction of 100 houses for economically weaker sections including civil and electrical works. By a letter dated 22nd June, 1995, the said work was awarded to the Respondent. The work was to be completed in 9 months i.e., by 25th March, 1996. Later, the period was extended to 15 months and it was to be completed by 25th September, 1996. The total value of the work was revised to Rs.1,96,05,639/-.

3. When disputes arose between the parties during execution of the contract, the Respondent filed Arbitration Application No. 70 of 1998 in this Court under Section 11 of the Act. In the said application, inter alia, the Respondent set out Section 20.1 of the terms and conditions applicable to the contract between the parties which reads as under:

“20.0 Settlement of disputes and arbitration

20.1 It is specifically agreed so and between the parties that all the differences or disputes arisen out of the contract or touching the subject matter of the contract shall be decided by process of settlement and arbitration as per clause 56.0 of General Conditions of Civil Works and Provisions of Indian Arbitration Act 1940 shall apply and Delhi/Lucknow Court only shall have jurisdiction over the same. The arbitration shall give reasoned award.”

4. The said application also set out the summary of the claims of the Respondent. There were 10 claims aggregating to Rs.61,10,537/- together with interest @ 24% compounded quarterly from 26th September, 1997 till the date of payment. It was stated in the said application that the Respondent had invoked arbitration clause by a letter dated 8th October, 1997 and a further reminder dated 18th December, 1997 but that THDC had not responded thereto. The said petition was disposed of vide order dated 24th July, 2000 and a former Judge of this Court was appointed as the Sole Arbitrator.

5. The said Sole Arbitrator passed an Award on 24th September, 2003 (hereafter the 'First Award'). The summary of the First Award is as under:

The First Award      

S. No.

Claim Number

 Details of the Claim

Award of Ld. Arbitrator

1.

Claim No.1

Rs.11,76,338 on account of the work force and machinery that remained unutilized for 2 months due to delay on the part of THDC in supplying cement, steel and CC blocks.

Rs.10,04,600/- towards Claim Nos. 1,2 and 3 and Rs.99,000/- for transport of 330 tankers of water

2.

Claim No.2

Rs.5,88,169/- for delay in supply of drawings and designs, payment on account of work force and machinery remained idle

 

3.

ClaimNo.3

Rs.3,93,084/- - Rs.2,94,084/- towards delay due to non supply of water, Rs.99,000/- towards transport of 330 tankers of water @ Rs.300/- per tanker

 

4.

Claim No.4

Rs.40,000/- for non-arrangement of supply of electricity

 

5.

Claim No.5

Rs.3,96,711/- on account of the escalation

Rs.2,64,474/-

6.

Claim No.6

Rs.12,000/- per year from 25th September, 1996 for extra insurance

Held premature with liberty to raise it after finalization of the account.

7.

Claim No.7

Rs.4,50,000/- towards damages/ losses as security money not released

Held premature with liberty to raise it after finalization of account.

8.

Claim No.8

Rs.19,05,500/- towards losses suffered on account of contractor remained idle at site from 25th September, 1996

Rs.1,92,000/-

9.

Claim No.9

Interest @ 24% compounded quarterly

Simple Interest @ 12% per annum from 1st January, 1998 till the date of payment

10




















































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top