SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(Del) 1011

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
SHRI SANJEEV MALHOTRA & ANOTHER – Petitioners
Versus
B.S. PROMOTER & DEVELOPERS – Respondent
O.M.P. (COMM) Nos. 52, 56 of 2016 & I.A. Nos. 2705, 2982, 2984 of 2016
Decided On : 27-03-2017

Advocates Appeared:
For the Petitioners: Ms. Rekha Aggarwal with Mr. Sanjeev Malhotra.
For the Respondent: Mr. Akhil Mittal.

Agreements not capable of specific enforcement can still entitle the aggrieved party to damages for breach, and the scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996, is limited.

Headnote:

Arbitration - Property Development Agreement - Arbitration and Conciliation Act, 1996 - Section 34 - 14(3)(c) of the Specific Relief Act, 1963 - [Property Development Agreement] - [Arbitration and Conciliation Act, 1996 - Section 34, Specific Relief Act, 1963 - Section 14(3)(c)] - The court discussed the provisions of the Arbitration and Conciliation Act, 1996, particularly Section 34, and the Specific Relief Act, 1963, specifically Section 14(3)(c), in relation to the enforcement and breach of the Property Development Agreement. The court's decision was influenced by the interpretation of these provisions in determining the enforceability of the agreement and the entitlement to damages for breach.

Fact of the Case:

The petitioners entered into a Property Development Agreement (PDA) with the respondent for the development of a plot. Disputes arose, and the respondent sought specific performance of the PDA and damages. The petitioners alleged breach by the respondent and terminated the PDA. The Arbitral Tribunal awarded compensation to the respondent for breach of the PDA.

Finding of the Court:

The court found that the PDA could not be specifically enforced due to lack of sufficient details, but the petitioners were in breach of the agreement, entitling the respondent to damages. The court held that the Arbitral Tribunal's assessment of damages was not fundamentally flawed and fell within the limited scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996.

Issues: Enforceability of the Property Development Agreement, Breach of the Agreement, Assessment of Damages

Ratio Decidendi: The court held that agreements not capable of specific enforcement can still entitle the aggrieved party to damages for breach. The court also emphasized the limited scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996, particularly in assessing the quantum of damages awarded by the Arbitral Tribunal.

Final Decision: The petitions and pending applications were dismissed, and the parties were left to bear their own costs.

JUDGMENT :

VIBHU BAKHRU, J.

1. These petitions have been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter ‘the Act’) inter-alia for setting aside the arbitral award dated 28.10.2015 (hereafter ‘the impugned award’) delivered by the Arbitral Tribunal, constituted by the sole arbitrator, Justice V.K. Jain (Retd.), a former judge of this Court.

2. By the impugned award, M/s B.S. Promoter and Developers was awarded an amount of Rs. 2 crores with interest at the rate of 12 % p.a. from the date of the impugned award till the realization of the amount. The impugned award was rendered with respect to disputes arising under the Agreement dated 09.09.2003 (Property Development Agreement) entered into amongst M/s B.S. Promoter and Developers, Mr. Sanjeev Malhotra, Smt. Sudesh Kapoor and Mr. Suresh Malhotra (since deceased).

Factual Background

3. Mr. Sanjeev Malhotra, Smt. Sudesh Kapoor (hereafter ‘petitioners’) and late Suresh Malhotra were the co-owners of the plot measuring about 4840 sq yds. bearing Khasra no. 266 in the Revenue Estate of village Tughlaqabad, now known as Chittaranjan Park, New Delhi (hereafter ‘the plot’). On 25.11.1980, the petitioners and late Suresh Malhotra entered into an agreement to sell with M/s Competent Builders (P) Ltd. (hereafter ‘Competent Builders’) for sale of the aforesaid plot. Pursuant to the said agreement, the possession of the plot was handed over to Competent Builders. However, the transaction could not materialize and petitioners filed a suit (Suit No. 938/90) in this Court. The said suit was settled and a compromise decree dated 21.03.1991 was passed. The petitioners state that in terms of the compromise decree, they were required to pay Rs. 11 lacs to Competent Builders to recover possession of the plot.

4. Thereafter, the petitioners and late Suresh Malhotra entered into a Property Development Agreement dated 09.09.2003 (hereafter ‘the PDA’) with M/s B.S. Promoter and Developers (hereafter ‘respondent’) for development of the plot in question after getting the plan sanctioned under a Group Housing Scheme from Delhi Development Authority (DDA). According to the terms of the PDA, it was agreed that all expenses till the recovery of possession of plot from Competent Builders and upto sanction of plans from DDA had to be borne by the respondent. Further, it was agreed that the respondent would be entitled to 70% of the built-up area constructed on the plot by it along with remaining undivided right in the plot underneath the superstructure for an amount of Rs. 3 crores to be paid to the petitioners. Accordingly, the respondent paid a sum of Rs. 11 lacs to the petitioners and a further sum of Rs. 2.89 lacs was agreed to be paid on transfer of the aforesaid interest in the plot. In addition to the above, the respondent was required to commence construction within 6 months from the date of sanction of plans by DDA and complete the same within 3 years from the said sanction.

5. In the meantime, a petition (Ex. Pet. No. 95/2003) was also filed against Competent Builders for recovery of the plot.

6. The petitioners claim that by communication dated 20.09.2004, the petitioners requested the respondent for a sum of Rs. 50 lacs to be paid to Competent Builders for restoration of possession of plot in favour of the petitioners. The said request was not acceded to. Thereafter, by a notice dated 25.10.2004, the petitioners terminated the PDA. These notices are disputed by the respondent and were subject matter of controversy in the arbitration.

7. Competent Builders filed a Special Leave Petition (being SLP (C) No. 23250/2012) in the Supreme Court. The petitioners state that in those proceedings, the petitioners and Competent Builders settled their disputes by entering into a settlement deed dated 05.04.2013 (hereafter ‘settlement agreement’), by virtue of which possession of the plot was to be handed back to the petitioners in lieu of Rs. 2 crores.

8. In the meanwhile, the respondent s





























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top