IN THE HIGH COURT OF DELHI
S. Ravindra Bhat, Yogesh Khanna, JJ.
Gail (India) Limited - Appellant
Versus
Punj Lloyd Limited - Respondent
RFA (OS)(Comm) No. 6 of 2016 and C.M. APPL. 41061-62 of 2016 and 352 of 2017
Decided On : 08-05-2017
LIQUIDATED DAMAGES - INTERIM COMPENSATION - EXTENSION OF TIME - CONTRACT INTERPRETATION - DAMAGES - SECTION 73 AND 74 OF THE INDIAN CONTRACT ACT, 1872 - [GAIL (INDIA) LTD. V. PUNJ LLOYD LTD.]
Fact of the Case:
GAIL (INDIA) LTD. (GAIL) awarded a contract to Punj Lloyd Ltd. (Punj Lloyd) for laying down gas pipelines for transportation of re-gasified natural gas. The contract consisted of four parts (called “spreads”). Punj Lloyd submitted its bid for spreads I, II and III from Dahej to Jagoti for a pipeline length of 423 kms consisting of spreads I, II and III. It also bid for overall commissioning of the four spreads for the Project. It was awarded the laying of pipeline work for the Spreads I, II and III. Spread IV was awarded to another bidder M/s RNGS. Punj Lloyd was also awarded the commissioning contract for the entire DVPL Project- for all four spreads. GAIL deducted liquidated damages on account of the failure of the plaintiff to complete the works at intermediate dates fixed for the spreads I, II and III of the pipelines laying project. Punj Lloyd sued GAIL for the amounts deducted, apart from other claims.
Finding of the Court:
The court held that the stipulation in clause 57.2.1and the amounts deducted were by way of liquidated damages and a genuine pre-estimate of the loss calculated in monetary terms. They were not merely precautionary conditions not meant to be enforced, but conditions that could be insisted upon, as is evident from clause 57.2.2, which clarifies that” compensation for Delay/Liquidated Damages stated in sub- clause 57.2.1 above shall be in addition to compensation for Delay/Liquidated Damages stated in sub-clause 57.1.1 of SCC.” Furthermore, the overall cap on damages at 20% (Clause 57.3) includes intermediate liquidated damages contemplated under clause 57.1.1. These intermediate delay liquidated damages were of the kind contemplated in Maula Bux (supra) and Bharat Sanchar Nigam (supra), which the parties agreed, would be payable by one of them (Punj Lloyd) without proof of actual loss.
Issues: 1. Whether the levy of the liquidated damages by the defendant was not in accordance with the agreement between the parties and the law and whether the plaintiff is entitled to recover the suit amount or any other amount from the defendant? 2. Whether the defendant could deduct intermediate liquidated damages?
Ratio Decidendi: The court relied on the principles laid down in Maula Bux v. UOI, 1969 (2) SCC 554, and Bharat Sanchar Nigam Ltd v. Reliance Communication Ltd, 2011 (1) SCC 394, to hold that the liquidated damages stipulated in the contract were a genuine pre-estimate of the loss and were not in the nature of a penalty. The court also held that the parties had agreed that the liquidated damages would be payable without proof of actual loss.
Final Decision: The appeal was allowed and the cross-objections were dismissed. Punj Lloyd’s suit was dismissed.
Mr. S. Ravindra Bhat, J.
1. The present appeal questions the judgment and order of a learned single judge, which decreed in part a civil suit filed by the respondent (Punj Lloyd). The said plaintiff, Punj Lloyd has also preferred cross objections, which were heard finally, with the consent of counsel for parties. The said cross objections shall be treated as admitted; the Registry shall accordingly register it and appropriately number it. The record of the suit and the proceedings before the learned single judge were called for and were part of the appeal file at the time of hearing, of this appeal.
2. Punj Lloyd sued to recover Rs. 29,15,07,084.80/- from the appellant (hereafter “GAIL”) The suit amount was deducted towards interim liquidated damages in terms of Clause 57.2 of the Special Conditions of Contract (SCC) to which the present disputants were parties. Punj Lloyd complained that GAIL had withheld amounts on account of the liquidated damages deducted for interim stages delays in the completion of works, in exercise of GAIL’s rights under Clause 57.2 of the SCC from Punj Lloyd’s bills.
3. GAIL was to lay down gas pipelines for transportation of re-gasified natural gas originating from Petronet LNG Terminal at Dahej in Gujarat and terminating at Vijaipur in Madhya Pradesh. This and other associated facilities was called the DAHEJ-VIJAIPUR Pipeline Project (DVPL Project). It consisted of four parts (called “spreads”). The invitation for bids described the spreads as follows:-
SPREAD
DETAILS
TOTAL LENGTH (IN KMS)
I.
Dahej to Sherpura
169.9
II.
Sherpura to Jhabua
100.8
III.
Jhabua to Jagoti
152.3
IV.
Jagoti to Vijaipur
193.3
4. Punj Lloyd submitted its bid for spreads I, II and III from DAHEJ to Jagoti for a pipeline length of 423 kms consisting of spreads I, II and III. It also bid for overall commissioning of the four spreads for the Project. It was awarded the laying of pipeline work for the Spreads I, II and III. Spread IV was awarded to another bidder M/s RNGS. Punj Lloyd was also awarded the commissioning contract for the entire DVPL Project- for all four spreads. GAIL’s Fax of Intent (FOI) intimating the grant of contract for laying of the pipelines for three spreads and for the commissioning of the entire pipelines of all four spreads was dated 05.05.2003 (Ex.PW2/2). The detailed Letter of Acceptance was issued on 14.05.2003 (Ex.PW2/3). The Contract Agreement was executed on 31.05.2003 (Ex.PW2/4).
5. The contractual time schedule for spreads I, II and III for laying pipeline, the completion schedule/period prescribed was as follows:-
SPREAD
DETAILS
COMPLETION PERIOD
I.
Dahej to Vemar
7 Months up to pre-commissioning II.
II.
Vemar to Sherpura
7½ Months up to pre-commissioning
III.
Sherpura to Jhabua
7½ Months up to pre-commissioning
IV.
Jhabua to Jagoti
6. With respect to commissioning of the DVPL Project, the completion period (Clause 45.1 of the General Conditions of Contract (GCC)) prescribed for Dahej to Vemar was 3 weeks for overall commissioning; Vemar to Sherpura was 6 weeks for overall commissioning, as was in the case of Sherpura to Jhabua and Jhabua to Jagoti. As compared to the scheduled date for pre-commissioning being 19.12.2003 (seven or seven and a half months from 5.5.2003) and the scheduled date for commissioning of the entire DVPL Project as 30.1.2004, the actual completion date for spreads I, II and III to the pre-commissioning stage was 22.2.2004 and the actual date of completion of commissioning of all the spreads was 10.4.2004. It is, therefore, seen that with respect to the pre-commissioning date there is a delay from 19.12.2003 to 22.2.2004 i.e delay of approximately 65 days. So far as the date of final commissioning of the complete DVPL Project is concerned, the actual date of completion was 10.4.2004 instea
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.