2017 Supreme(Del) 3504

IN THE HIGH COURT OF DELHI AT NEW DELHI
S. RAVINDRA BHAT, S.P. GARG, JJ.
AHLUWALIA CONTRACT (INDIA) LIMITED - APPELLANT
Versus
THE UNION OF INDIA - RESPONDENTS
FAO (OS) (COMM) 143 of 2017, C.M. APPL.25112 of 2017
Decided On : 17-10-2017

Important Points

The need for reasonable certainty in establishing damages and the limited scope of judicial review in arbitration cases.

Subject

Arbitration Law - Contract Disputes

Act Referred

ARBITRATION AND CONCILIATION ACT : S.37, S.34

Headnote

Arbitration - Ahluwalia Contract (India) Ltd - Arbitration and Conciliation Act - Section 37, Section 34

Fact of the Case:

Ahluwalia Contract (India) Ltd appealed the decision of a learned Single Judge under Section 37 of the Arbitration and Conciliation Act, seeking to set aside the award of an arbitral tribunal under Section 34. The case involved a contract for 'Package III, Electrical Services at AIIMS, Raipur' entered into with the Ministry of Health and Family Welfare. Disputes arose regarding delays in performance, compensation claims, and rejection of certain claims by the tribunal.

Finding of the Court:

The court upheld the rejection of the claim for loss of profits during the extended period, citing the need for reasonable certainty in establishing such damages. It also sustained the rejection of the claim for bonus for the extended period, emphasizing the limited scope of judicial review in arbitration proceedings.

Issues: The main issue was the rejection of Ahluwalia's claim for damages towards loss of profits during the extended period, along with the rejection of the claim for bonus for the extended period.

Ratio Decidendi: The court emphasized the need for reasonable certainty in establishing damages, citing precedents and the limited scope of judicial review in arbitration cases. It found that while various other claims for extra expenditure and overheads were granted based on contractual formulae, there was insufficient evidence to justify the claim for damages towards loss of profits.

Final Decision: The appeal was dismissed without order on costs.

Advocates Appeared:
For the Appellant : Sh. Dhruv Mehta, Sh. S.K. Maniktala, Sh. Sanjay Kumar
For the Respondents: Sh. Arun Bhardwaj

JUDGMENT :

S. RAVINDRA BHAT, J.

1. Ahluwalia Contract (India) Ltd (the appellant, hereafter “Ahluwalia”) appeals the decision of a learned Single Judge, under Section 37 of the Arbitration and Conciliation Act (“the Act”), declining to set aside the award of an arbitral tribunal, under Section 34.

2. The facts are that Ahluwalia was awarded the contract for 'Package III, Electrical Services at AIIMS, Raipur entered into on 11.08.2011 (hereafter 'the Agreement') after it successfully bid in a tender process floated by the Respondent, through the Ministry of Health and Family Welfare (hereafter “the Principal”). The agreement involved the supply, installation, testing and commissioning of electrical equipments. The total contract value was Rs. 41,20,09,326/-. The completion period of the contract was 16 months, starting from 19.08.2011. Ahluwalia alleged that the Principal did not hand over the entire site till December 2015. In the meanwhile, the tenure of completion under the Agreement was extended eleven times. Accordingly, it alleged that delays in the performance of the Agreement – attributable - to the Principal’s acts and omissions, resulted in losses to it. It claimed compensation. The Principal refuted these allegations and blamed Ahluwalia for the delays; it further alleged that in terms of the General Conditions of Contract (hereafter 'GCC'), no compensation was payable for any delay in handing over of the site. Since these disputes could not be resolved through mutual negotiation, they were referred to arbitration, in terms of a condition under the contract.

3. Ahluwalia sought an Award in respect of 17 heads of claims. 12 claims (nos. 1 to 6, 8, 9, 10, 11, 15 and 16) were allowed. 4 claims, i.e. nos. 3 to 5 and 7 were concerned with expenses alleged to have been incurred by Ahluwalia during the extended period of agreement. They were, however, rejected by the tribunal, which held that the contract did not provide for such expenses separately. The arbitrator furthermore held that the claims were in fact covered within the mark-up of 15% costs of materials/labour provided to cover all overhead profits. An important claim, i.e. no.12 relating to loss of profits suffered during the extended period of agreement was rejected on the basis that it was hypothetical and conjectural. Likewise, claim no.13 for bonus in terms of clause 2A of the GCC was rejected.

4. In the petition under Section 34, eight claims rejected by the tribunal were impugned. Learned Single Judge took note of clause 2X – which defined “market rates” and clause 40h of the Special Conditions of Contract (SCC) which had prohibited compensation on account of delay in the starting of work – on account of acquisition of land, encroachment and in case of clearance work or towards sanction to estimates etc. The learned Single Judge was of the opinion that the reasoning given by the tribunal was unsustainable.

5. With respect to the rejection of the claim for loss of profits, the learned Single Judge held as follows:

“16. The arbitrator had also rejected ACIL's Claim no.12 for loss of profits during the extended period. The arbitrator found such claim to be hypothetical and this court is unable to accept the contention that the aforesaid view is not a plausible one. It is well settled that the claim for loss of profits is in the nature of damages and it would be incumbent on any party claiming such damages to establish the same with reasonable certainty.

17. In Bharat Coking Coal Ltd. v. L K Ahuja: (2004) 5 SCC 109, the Supreme Court had observed as under:-

“It is not unusual for the contractors to claim loss of profit arising out of diminution in turnover on account of delay in the matter of completion of the work. What he should establish in such a situation is that had he received the amount due under the contract, he could have utilised the same for some other business in which he could have earned profit. Unless such a plea is raised and established, claim for loss










1
2
3
4
5
6
7
8
9
10
11