2017 Supreme(Del) 4763

IN THE HIGH COURT OF DELHI AT NEW DELHI
NAVIN CHAWLA, J.
WISHWA MITTAR BAJAJ & SONS (Constructions) Pvt. Ltd – Appellant
Versus
BPTP LTD - Respondent
OMP (COMM) NO.427 of 2017
Decided on : 21-12-2017

Advocates:
Advocate Appeared:
For the Appellant : Mr. Raghavedra Mohan Bajaj and Mr.Shreyas Mehrotra, Advs.

The main legal point established in the judgment is that the court found the settlement to be voluntary and not under coercion or duress, based on the analysis of the correspondence between the parties, the Settlement Agreement, and the Indemnity-Cum-Undertaking.

Headnote:

Coercion - Arbitration and Conciliation - Section 34 of the Arbitration and Conciliation Act, 1996 - 10.04.2011, 11.05.2010 - [Section 11(5), ONGC Vs. Western Geco International Limited, (2014) 9 SCC 263, National Insurance Company Vs. Boghara Polyfab Private Limited, AIR 2009 SC 170, Union of India and Others Vs. Master Construction Company, (2011) 12 SCC 349, New India Assurance Company Limited Vs. Genus Power Infrastructure Limited (2015) 2 SCC 424] - The court discussed the effect of the execution of the Settlement Agreement dated 10.04.2011 by the petitioner and the alleged coercion, pressure, or undue influence by the respondent. The court analyzed the correspondence between the parties, the Settlement Agreement, and the Indemnity-Cum-Undertaking, and concluded that the settlement was voluntary and not under coercion or duress. The court referred to various legal principles and judgments to support its decision.

Fact of the Case:

The petitioner challenged the Arbitral Award dated 14.07.2017, claiming coercion and undue influence in the execution of the Settlement Agreement dated 10.04.2011 by the petitioner.

Finding of the Court:

The court found that the settlement was voluntary and not under coercion or duress, based on the analysis of the correspondence between the parties, the Settlement Agreement, and the Indemnity-Cum-Undertaking.

Issues: The issues involved were the effect of the execution of the Settlement Agreement dated 10.04.2011, the alleged coercion, pressure, or undue influence by the respondent, and the validity of the Arbitral Award.

Ratio Decidendi: The court held that the settlement was voluntary and not under coercion or duress, based on the analysis of the correspondence between the parties, the Settlement Agreement, and the Indemnity-Cum-Undertaking. The court referred to various legal principles and judgments to support its decision.

Final Decision: The court dismissed the petition under Section 34 of the Arbitration and Conciliation Act, 1996, finding no merit in the petitioner's claim of coercion and undue influence in the execution of the Settlement Agreement.

JUDGMENT :

1. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) has been filed by the petitioner challenging the Arbitral Award dated 14.07.2017 passed by the Sole Arbitrator in Wishwa Mittar Bajaj & Sons (Constructions) Pvt. Ltd vs. BPTP Ltd., DAC/385/03-13 (hereinafter referred to as impugned Award).

2. The respondent vide its Letter of Intent dated 18.04.2007 had awarded the work of construction of Towers (G, H, J & K) for Group Housing Project at Sector-82, Faridabad to the petitioner. A work order dated 19.04.2007 was thereafter issued by the respondent in favour of the petitioner for the above-mentioned work. The stipulated cost of the project was Rs. 16,48,14,449/- and was to be completed within a period of 21 months from the date of possession of the site. The petitioner claims that there were defaults on the part of the respondent not only in supply of drawings, decisions, steel, Ready Mix Concrete (RMC) etc., but also in release of payments under the Running Bills. The petitioner in this regard has made reference to various correspondence that were exchanged between the parties, however, I need not deal with them in detail as the issue involved is to determine the effect of the execution of the Settlement Agreement dated 10.04.2011 by the petitioner of such purported default of the respondent. The petitioner alleges that it was also forced to sign the “Indemnity-Cum-Undertaking” dated 11.05.2010 for release of the amount that was even otherwise due to it under the agreement. It is submitted that in spite of taking the undertaking, the amount of Rs. 15 lakhs was released only after about 20 days of the same. The petitioner further submits that it had raised a final bill of approx Rs. 90 lakhs on the respondent, which was not accepted by the respondent and the petitioner was forced to submit a revised bill dated 01.06.2010 of Rs. 64,28,369.14/- for the “Tower Area” and Rs. 9,88,628/- for the “Non-Tower Area” totaling to Rs. 74,16,997/-. It is submitted that in terms of the “Indemnity-Cum-Undertaking”, this amount should have been released to the petitioner within a period of 20 days after the submission of the final bill, however, the respondent with malafide intention failed to pay the same forcing the petitioner to make representations dated 28.06.2010 and 05.07.2010 seeking release of the said amount. Instead of releasing the amount, the respondent forced the petitioner to submit a revised bill on 12.08.2010, reducing the amount of final bill to Rs. 40 lakhs. However, the respondent released only a payment of Rs. 4,58,556/- on 14.09.2010 to the petitioner. The petitioner again requested for release of amount vide its letter dated 20.09.2010 and 22.09.2010. The respondent on 06.10.2010 finally released another sum of Rs. 13 lakhs in favour of the petitioner. On further protest, an amount of Rs. 23,852/- was released in favour of the petitioner on 04.11.2010 and an amount of Rs. 10 lakhs was released in favour of the petitioner on 24.11.2010. Another amount of Rs. 6 lakhs was released in favour of the petitioner on 27.01.2011 by the respondent.

3. It is submitted by the petitioner that on 11.04.2011 the Director of the petitioner company was called by the respondent to its Gurgaon office where he was presented with three documents i.e., Deed of Settlement, Affidavit and Indemnity Bond as full and final settlement and as a pre-condition for releasing further amount of Rs. 3,07,491/-. It is submitted that the petitioner signed the above documents so that the payment can be released in favour of the petitioner and once the said payment was credited to the bank account of the petitioner, the petitioner vide its letter dated 21.04.2011 raised the claim for the balance payment in terms of the original bill and placing on record the fact that all payment subsequent to the Indemnity-Cum-Undertaking bond dated 11.05.2010 has been accepted by it under duress,