IN THE HIGH COURT OF DELHI AT NEW DELHI
S. RAVINDRA BHAT, A.K. CHAWLA, JJ.
M/s Jayaswal Neco Industries Ltd. - Appellant
Versus
M/s Goyal M.G. Gases Pvt. Ltd. – Respondent
FAO(OS) (COMM) 21 of 2018, CAV. 99 of 2018, C.M. APPL. 4549-4551 of 2018
Decided On : 05-04-2018
Arbitration & Conciliation Act, 1996 - Section 34, 37(1)(c) - Evidence Act, 1872 - Section 34 and 65B - Arbitral award - Air Separation Plant - Lease of - Lease charges were payable on pro rata basis - Performance was not conducted - Old oxygen compressor was causing loss in lakhs per month due to excess consumption of 8000 units of electricity - Repair and replacement of the Oxygen Compressor - Whether the old oxygen compressor was in good working condition is a purely factual question - Tribunal decided in favour of Goyal MG - Both parties have adduced contradictory evidence on power consumption - Court cannot engage in a fact-finding enquiry at advanced stage - Counter claim based on ledger entries were not proved - Tribunal's decision to allow Goyal MG's counterclaim cannot be faulted - Appeal is without merit and the same is dismissed.
S. RAVINDRA BHAT, J.
Facts
1. The appellant has approached this Court under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (“the Act”) impugning the order of the learned Single Judge dated 21.12.2017 (‘impugned order’), which dismissed its application under Section 34 confirming the arbitral award dated 04.08.2017 read with correction order dated 15.09.2017 (collectively the “award”).
2. The relevant facts of the case are that the respondent (hereafter “Goyal MG”) agreed to lease its 70 TPD (tonne per day) Air Separation Plant to the appellant (hereafter “Jayaswal”). The Agreement was for 10 years from the date of commissioning of the plant; lease charges were capped at Rs. 30 lakhs per month plus taxes. In terms of Article 6(f) of the Agreement, lease charges were payable on pro rata basis from the date of plant commissioning till the date of performance test. On 14.03.2003, the parties entered into another agreement pursuant to which Goyal MG undertook to operate and maintain the Plant. The O&M Agreement was for a period of 10 years from the date of commissioning of the Plant, and O&M charges were Rs. 11 lakhs per month plus taxes. The plant was commissioned in March 2005, and, therefore, the Lease Agreement and the O&M Agreement would both continue till March 2015.
3. Under Article 15 of the Lease Agreement and Article 3 of the O&M Agreement, the Plant was required to produce 2040 Nm3/hour of oxygen and power consumption had to be limited to 0.82KWH/Nm3. Between 23.12.2009 and 27.08.2013, Jayaswal wrote several letters requesting Goyal MG to (a) take the performance test, (b) repair the new oxygen compressor and replace the old oxygen compressor, and (c) replace the main air compressor motor which was prone to frequent breakdowns. In these letters, Jayaswal claimed that it was suffering significant losses due to short supply of oxygen and excess consumption of electricity. This includes letters by Jayaswal dated 23.12.2009 and 13.05.2011, requesting Goyal MG to take the performance test. On 24.07.2012, Goyal MG replied stating that it had been continuously requesting Jayaswal to conduct the performance test since 2006. Goyal MG disavowed any responsibility for excess power consumption because Jayaswal had failed to conduct a performance test. On 12.06.2014, Goyal MG asserted that the performance test would be deemed to have been conducted because the Plant was producing required quantity and quality of oxygen. Goyal MG also relied on the Minutes of the Meeting dated 04.02.2015, in this regard. The other issue was with respect to oxygen compressors. Jayaswal informed Goyal MG on 07.01.2012 that the old oxygen compressor was causing loss of Rs. 3.2 lakhs per month due to excess consumption of 8000 units of electricity. On 19.05.2012, Jayaswal informed the Goyal MG that its 70 TPD Plant was consuming as much electricity as its 100 TPD Plant. On 18.09.2013, Goyal MG requested Jayaswal to pay Rs. 75 lakhs for purchase of new oxygen compressor, and it agreed that the amount could be adjusted against the insurance claim or any outstanding amount due at the end of the lease period. However, on 16.12.2013, Goyal MG stated that Jayaswal was responsible for replacement of burnt equipment pursuant to Article 18(b) of the O&M Agreement. Through letter dated 26.12.2013, Jayaswal insisted that compressor replacement was Goyal MG’s responsibility, and it placed reliance on Articles 2(d) and 16 of the O&M Agreement to support its position. Finally, on 27.03.2014, Goyal MG agreed to an arrangement whereby Jayaswal would provide Rs. 75 lakhs as an interest free advance for the purchase of the new compressor and this advance would be repaid at the time of sale of the Plant. Goyal MG specified that it had agreed to this arrangement to maintain good business relationship with Jayaswal. However, on 12.06.2014, Goyal MG once again adopted the stance that Article 18(b) of the O&M Agreement cast an obligation upon Jayaswal to r
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.