SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Del) 478

IN THE HIGH COURT OF DELHI AT NEW DELHI
JAYANT NATH, J.
Brahmaputra Cracker and Polymer Limited - Petitioner
Versus
RVR Projects Private Limited - Respondent
O.M.P. (COMM) 43 of 2018
Decided On : 01-02-2018

Advocates Appeared:
For the Petitioner: Mr. N.L. Ganpathi and Mr. Shaleen Srivastava
For the Respondents: Mr. Sridhar Potaraju, Mr. Prabhat and Ms. Ankita Sharma

The central legal point established in the judgment is the significance of the arbitrator's interpretation of contract terms and the relevance of the parties' conduct in determining the outcome of claims under the Arbitration and Conciliation Act.

Headnote:

Arbitration and Conciliation Act - Petition under Section 34 - Clause 44 of the Special Conditions of the Contract - [Section 34] - [Clause 44 of the Special Conditions of the Contract] - The court discussed the provisions of Clause 44 of the Special Conditions of the Contract and its application in the context of the claims made by the parties. The court highlighted the interpretation of the contract terms by the Arbitrator and its relevance in determining the outcome of the claims. The court also referred to the Supreme Court's decision in McDermott International Inc. v. Burn Standard Co. Ltd., emphasizing the arbitrator's jurisdiction in interpreting the contract and considering the conduct of the parties.

Fact of the Case:

The petitioner, a Central Public Sector Enterprise, filed a petition under Section 34 of the Arbitration and Conciliation Act seeking to set aside a part of the Award passed by the Arbitrator. The dispute arose from a contract for Civil and Structural Works of a petrochemical complex. The petitioner challenged the acceptance of certain claims by the respondent, citing non-compliance with the provisions of the contract.

Finding of the Court:

The court found that the conduct of the petitioner, particularly in relation to the application of Clause 44 of the Special Conditions of the Contract, led to the allowance of claim No.1. However, the court disallowed claim No.2, emphasizing the lack of evidence to support the claim and its inconsistency with the public policy of India.

Issues: The issues revolved around the interpretation and application of the contract provisions, particularly Clause 44, and the sufficiency of evidence to support the claims made by the parties.

Ratio Decidendi: The court's decision was based on the interpretation of the contract terms by the Arbitrator, the conduct of the parties, and the lack of evidence to support claim No.2. The court also referred to the Supreme Court's decision in McDermott International Inc. v. Burn Standard Co. Ltd. to emphasize the arbitrator's jurisdiction in interpreting the contract.

Final Decision: The court disposed of the petition, allowing claim No.1 and disallowing claim No.2. All pending applications were also disposed of accordingly.

JUDGMENT :

JAYANT NATH, J.

1. This order is passed in continuation with the order dated 31.1.2018. I have heard learned counsel for the respondent. The contents of the order dated 31.1.2018 are somewhat repeated herein for the sake of continuity of the order.

2. This petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act) seeking to set aside a part of the Award dated 15.11.2017 passed by the learned Arbitrator.

3. The brief facts which come out from the petition are that the petitioner is a Central Public Sector Enterprise for the Government of India. It had invited bids for the Civil and Structural Works of Linear Low Density Polyethylene and High Density Polyethylene Unit of the petitioner’s petrochemical complex in Dibrugarh, Assam. The respondent emerged as L1 bidder and its bid was accepted. Letter of acceptance dated 08.02.2010 was issued by the petitioner to the respondent. Engineers India Ltd. was the Engineer-in-Charge for the contract. It is pleaded that the date of commencement of the contract was 17.12.2009 and the time for completion was 18 months. The contract completion date was 16.06.2011. 75% of the original time schedule of the contract applicable for claiming price variation/escalation for Structural Steel and Reinforcement Bar as provided in Clause 44 of the Special Conditions of the Contract was said to be 30.01.2011. The actual date of completion of the contract was 30.10.2013.

4. By the consent of the parties, Mr. S.M. Chopra, Former ADSJ was appointed as a sole Arbitrator. The learned Arbitrator has now given his Award dated 15.11.2017.

5. As per the Award two of the claims of the claimant/respondent have been accepted, namely, claim No.1 for Rs.41,90,393/- and claim No.2 whereby the parties have been directed to carry out a joint measurement for the subject matter of the bill in question failing which the bill submitted by the respondent for a sum of Rs.6,47,066/- was to be accepted.

6. I have heard learned counsel for the parties.

7. Learned counsel for the petitioner has made two submissions. Firstly, he submits that the Award of Rs.41,90,393/- under claim No. 1 is totally contrary to Clause 44 of the Special Conditions of the Contract. As per Clause 44, escalation could be claimed for structural Steel and Reinforcement Bar only if the purchase order was made within 75% of the time schedule and the material is delivered before the expiry date of the Contract. He pleads that under the Contract, the petitioner had to give drawings for the said Structural Steel and Reinforcement Bar. Where the drawings have been given after 30.01.2011 (being the relevant 75% time schedule), the petitioner has accepted the escalation bill of the respondent. However, where the drawings were given prior to 30.01.2011, the bills for escalation have been disallowed. He submits that in all the cases, the purchase orders were placed after 30.01.2011. Hence, he pleads that the award of Claim No. 1 is totally erroneous and against the provisions of the contract and is hit by Section 28 of the Act.

8. He further submits that as far as claim No. 2 is concerned, this is related to construction of RCC pavement. He points out that the consultant i.e. Engineers India Ltd.(EIL) had on 22.07.2011 informed the respondent that the RCC pavement is not required any further. He also submits that after the final bill was submitted, the respondent have woken up to submit a bill for this work which EIL had already requested them to not to carry out. As the bill was belated and after the final bill had already been processed, EIL vide its communication dated 02.04.2015 refused to process the bill inasmuch as the final measurement of the contract had been completed and recommendations had been sent to the petitioner for closure of the contract.

9. Learned counsel for the respondent submits that as far as claim No.2 is concerned the work was done by the respondent in December 2011. He submits th


































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top