NAVIN CHAWLA
Delhi State Industrial Infrastructure Development Corporation Ltd. (DSIIDC) – Appellant
Versus
Bawana Infra Development (P) Ltd. – Respondent
NAVIN CHAWLA, J.
1. This petition under Section 39(2) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act) has been filed by the petitioner primarily seeking an interpretation of the fee schedule that is provided in the Fourth Schedule to the Act, introduced in the Act by way of the Arbitration and Conciliation (Amendment) Act, 2015. The Fourth Schedule is reproduced hereinunder:-
“THE FOURTH SCHEDULE
[See section 11(14)]
Sum in dispute
Model fee
Upto Rs. 5,00,000
Rs. 45,000
Above Rs. 5,00,000 and upto Rs.20,00,000
Rs. 45,000 plus 3.5 per cent. of the claim amount over and above Rs.5,00,000
Above Rs. 20,00,000 and upto Rs.1,00,00,000
Rs. 97,500 plus 3 per cent, of the claim amount over and above Rs. 20,00,000
Above Rs. 1,00,00,000 and upto Rs.10,00,00,000
Rs. 3,37,500 plus 1 per cent. of the claim amount over and above Rs. 1,00,00,000
Above Rs. 10,00,00,000 and upto Rs. 20,00,00,000
Rs. 12,37,500 plus 0.75 per cent. of the claim amount over and above
Rs.1,00,00,000
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.