IN THE HIGH COURT OF DELHI AT NEW DELHI
SANJEEV NARULA, J.
Braithwaite Burn and Jessop Construction Company Limited (BBJ) - Appellant
Versus
Rail Vikas Nigam Ltd (RVNL) - Respondent
Original Miscellaneous Petition (Comm) No. 127 of 2019
Decided On : 15-04-2019
Arbitration and Conciliation Act - Delay in Completion of Contract - Sections 34, 13.8, 8.2, 8.4, 8.7 - The court upheld the Arbitral Tribunal's decision on the claims of reimbursement of ground rent, price adjustment, and extended stay compensation, based on the interpretation of the contract terms and the conduct of the parties. The court emphasized that the Arbitral Tribunal's findings were based on the evidence on record and were not liable to be interfered with. The court also highlighted the principle that an arbitrator is the final adjudicator of the sufficiency and extent of the evidence, and the court will not interfere unless there is something perverse or irrational in the arbitral award.
Fact of the Case:
The case involved a dispute over delay in the completion of a construction project, with both parties holding each other responsible for the delay. The Petitioner challenged the Arbitral Award on three claims related to reimbursement of ground rent, price adjustment, and extended stay compensation.
Finding of the Court:
The court found that the Arbitral Tribunal's decision was based on the evidence on record and the interpretation of the contract terms. The court emphasized that the Arbitral Tribunal's findings were not liable to be interfered with and highlighted the principle that an arbitrator is the final adjudicator of the sufficiency and extent of the evidence.
Issues: The issues revolved around the attributability of delay in the completion of the contract, the interpretation of contract terms related to reimbursement of ground rent and price adjustment, and the substantiation of the claim for extended stay compensation.
Ratio Decidendi: The court upheld the Arbitral Tribunal's decision based on the interpretation of the contract terms, the conduct of the parties, and the sufficiency of evidence. The court emphasized the principle that an arbitrator is the final adjudicator of the evidence and will not interfere unless there is something perverse or irrational in the arbitral award.
Final Decision: The court dismissed the petition challenging the Arbitral Award, upholding the findings of the Arbitral Tribunal on the claims of reimbursement of ground rent, price adjustment, and extended stay compensation.
Sanjeev Narula, J.
The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter referred to as the "Act") impugns the Arbitral Award dated 11th October 2018 (hereafter the impugned award), passed by the Arbitral Tribunal comprising of three Arbitrators (hereinafter the Arbitral Tribunal).
2. By the impugned award, the Arbitral Tribunal has adjudicated the disputes that had arisen between the parties in respect of the contract agreement dated 4th June 2010 for fabrication, assembly and launching of 16 x 45.7m triangulated open web welded steel through girder confirming to MBG Loading Over Br. No. 553 (Kathjodi River) in connection with Cuttack-Barang doubling in Khurda road division of East Coast Railway in the state of Orissa, India.
3. The seven claims raised by the Petitioner, have been decided by the Arbitral Tribunal as follows :
S.No.
Claim
Amount (Rs.)
Decision
1.
Reimbursement of amount recovered as ground rent of fabrication yard
21,15,078
Rejected
2.
Refund of delay damages deducted from various bills
1,11,84,669
Allowed, with interest 12% from the date of recovery till payment.
3.
Price adjustment (bill no-02) upto 12.12.2014
2,16,62,211
Rejected
4.
Reimbursement of bank charges for extension of bank guarantee on account of RVNL
18,61,891
Allowed, refund of guarantee extension charges beyond 31.07.2013 along with interest @12% per annum.
5.
Extended stay compensation
5,95,000,00
Rejected
Aggregated amount
9,63,23,849
6.
Compensation @18% for amount on unpaid sum of Rs.9,63,23,849 from 08.10.2016 till realisation of claim
As accrued
Allowed to the extent of on delayed damages and refund of bank guarantee charge
7.
Cost of arbitration
As per actual
Divided equally.
Petitioner challenges the award in respect of findings on Claims No.1, 3 & 5.
Analysis and Findings
4. The controversy in the arbitration and the present proceedings centers around the question of delay in completion of the contract. The project was to be completed within a period of nine months. However, it was delayed by 45 months and was completed after several extensions on 12th December 2014.
5. Petitioner holds the Respondent responsible for the delay. On the other hand, Respondent alleges that the Petitioner is accountable for not completing the project within the stipulated period. The question of attributability of delay was the pivot of dispute between the parties. The Arbitral tribunal has concluded that both the Petitioner and the Respondent were at fault and responsible for the delay.
6. The Court has heard Mr. Jayant Mehta learned counsel appearing for the Petitioner and Mr. Saurabh Mishra, learned counsel for the Respondent. Claim No.1 - Reimbursement of amount recovered as ground rent of fabrication yard
7. The ground rent of fabrication yard amounting to Rs. 21,15,078/- (Twenty One Lakh Fifteen Thousand and Seventy-Eight Rupees) has been recovered from the final Bill of the Petitioner.
8. Facts giving rise to the present claim are that during the pre-bid meeting held on 30th November 2009, Petitioner had enquired from the Respondent if it could utilise the infrastructure setup at Jagatpur end of 2nd Mahanadi Bridge, Cuttack for fabrication, inspection metalizing, painting, etc. The Respondent permitted the use of the abovementioned site, however, it informed the Petitioner that the necessary ground rent will have to be paid to East Coast Railway to whom the land belonged. The abovementioned fabrication yard was occupied by the Petitioner from 25th May 2010 and it continued to occupy it till the completion of the work. Petitioner impugns the recovery of ground rent from 25th May 2010 till 1st April 2013, relying upon a letter of the Respondent da
Associate Builders v. Delhi Development Authority
Bharat Coking Coal Ltd. v. L.K. Ahuja
McDermott International Inc. v. Burn Standard Co. Ltd.
Northern Railway v. Sarvesh Chopra
P.R. Shah, Shares and Stock Brokers Private Limited v. B.H.H. Securities Private Limited
Pure Helium India (P) Ltd. v. Oil and Natural Gas Commission
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.