IN THE HIGH COURT OF DELHI
S. Ravindra Bhat, J.
J.S. Chaudhary – Appellant
Versus
The Vice Chairman, DDA and Another – Respondents
C.S. (OS) 1347 of 1998
Decided On : 31-01-2011a
The plaintiff, a contractor, filed a suit against the defendant, Delhi Development Authority (DDA), seeking payment of various amounts due under a works contract for construction of flats. The plaintiff claimed a balance of final bill amount, release of bank guarantee, payment for work done beyond the stipulated date, refund of amounts withheld from running bills, reimbursement of costs incurred for revalidation of bank guarantee, payment for extra work done, and compensation for delay in completion of the contract. The DDA denied the claims, contending that the plaintiff was not entitled to the payments and that the delay in completion of the contract was attributable to the plaintiff's own conduct.
Fact of the Case:
The plaintiff, a contractor, entered into a works contract with the defendant, Delhi Development Authority (DDA), for construction of flats. The plaintiff claimed a balance of final bill amount, release of bank guarantee, payment for work done beyond the stipulated date, refund of amounts withheld from running bills, reimbursement of costs incurred for revalidation of bank guarantee, payment for extra work done, and compensation for delay in completion of the contract. The DDA denied the claims, contending that the plaintiff was not entitled to the payments and that the delay in completion of the contract was attributable to the plaintiff's own conduct.
Finding of the Court:
The court found that the plaintiff was entitled to the balance of final bill amount, release of bank guarantee, payment for work done beyond the stipulated date, refund of amounts withheld from running bills, reimbursement of costs incurred for revalidation of bank guarantee, and payment for extra work done. However, the court rejected the plaintiff's claim for compensation for delay in completion of the contract, holding that the plaintiff had agreed not to claim damages for delays caused by the DDA.
Issues: 1. Whether the suit is bad for non-joinder of necessary parties? 2. Whether a valid notice was served u/s 53-B of Delhi Development Act, 1957? If not, to what effect? 3. Whether there was any delay in completion of the contract attributable to the Defendant? 4. Whether the plaintiff is entitled to the payment of Rs. 81,54,667/-under various heads as mentioned in para 6 of the plaint? 5. Whether the plaintiff is entitled to his claims in view of the undertaking given by him at the time request for extension was made by him? 6. Whether the plaintiff is entitled to interest on Rs. 81,54,667/-, if so at what rate and from what period? 7. Relief.
Ratio Decidendi: The court held that the plaintiff was entitled to the payments claimed, except for the compensation for delay in completion of the contract, because the plaintiff had agreed not to claim damages for delays caused by the DDA. The court also held that the plaintiff was entitled to interest on the amounts awarded.
Final Decision: The court decreed the suit in favor of the plaintiff for Rs. 13,58,924.97/- (Rupees thirteen lakhs, fifty eight thousand, nine hundred and twenty four and ninety seven paise only) against the Defendant DDA. The plaintiff will be entitled to pendente lite and future interest on Rs. 7,30,451/- at the rate of 12% on the said amount, from the date of institution of the suit, till payment. The suit is decreed in the above terms. The plaintiff is also entitled to costs; in addition, counsel's fee is quantified at Rs. 55,000/-.
S. Ravindra Bhat, J.
The plaintiff claims a money decree, based on the sum of Rs. 81,54,667/-towards various heads, on account of amounts due from the Defendant (hereafter called "DDA") in a works contract; additionally, the plaintiff claims interest, at a quantified rate, as well as pendent lite and future interest. The claim is premised on the performance of a works contract, entered into by the parties, for construction of 448 flats at Jhilmil Colony.
2. The facts, to the extent they are uncontroverted, are that the plaintiff, who describes himself as sole proprietor of a firm, successfully bid, and was awarded the contract, by the DDA. The bid was accepted on 09.9.1991; the written contract (Ex-PW-1/2) was entered into on 16.09.1991. The time for performance, agreed upon by the parties, was 15 months, from the date of signing the agreement. It was however, extended. The plaintiff says that this was due to various defaults by DDA; the latter however denies that position. Eventually, the construction was completed on 12.12.1994. The completion certificate was issued on 6th July, 1995. The plaintiff relies on a document (Ex.PW-1/3) issued on 12.12.1994, evidencing the date of completion of construction.
3. The plaintiff contends that in terms of the Agreement, Ex. PW-1/2, the Final Bill had to be settled by DDA, within six months of completion. The suit claims the sum of Rs. 81,54,667/50 from the DDA towards various heads, which are described briefly hereafter. Claim (i) pertains to balance of final bill amount, i.e. Rs. 5,23,195/-. According to the plaintiff, the final bill was payable within six months from completion, i.e. 11.6.1995; DDA is alleged to have failed to pay this. The bill was submitted on 16.06.1996. The plaintiff admits to some part payment on 11.09.1996, after which it submitted a fresh bill on 10.09.1997. The sum of Rs. 5,23,195/-is claimed on this score.
4. Claim (ii) is for the release of bank guarantee to the extent of Rs. 3,00,000/-, which the plaintiff furnished in favour of DDA, for the due performance of the contract. It is alleged that in terms of the contract, the guarantee had to be released within six months after completion, yet the DDA has not done so. The plaintiff claims the sum of Rs. 3,00,000/-on this account. Claim (iii) relates to incidental expenses towards revalidation of bank guarantee for the period beyond the contract, after its completion; the plaintiff says that a sum of Rs. 50,000/-is to be paid by DDA.
5. According to the suit, the cost of work done beyond the stipulated date of competition @30% extra amounts to Rs. 34,43,818.00/-; the plaintiff claims this. It is contended that the work could not be completed within the stipulated period on account of the following defaults of DDA:
(a) delay in handing over of site for work;
(b) delay in issue of stipulated material;
(c) delay in release of payments for work done,
(d) delay in laying of electrical conduits by the agency appointed by the Defendant.
(e) delay in conveying of decisions to the plaintiff from time to time during/relating to the execution of work.
6. The suit says that due to the aforesaid defaults of DDA, the work could be completed only on 12.12.1994, i.e. in a period of 39 months, as against the stipulated period of 15 months contained in the agreement between the parties. During the delayed period, the price of material and labour increased in the market. It became impractical and un-economical for the plaintiff to execute the work within the accepted/ quoted rates. The plaintiff says that the rates quoted by him were in the month of May 1991; he however, was made to complete the work at the same rates even in the 1994. DDA is therefore, liable to make good the loss incurred (by the plaintiff) on this account before the completion of the work and after the originally stipulated date of completion. The plaintiff
A.T. Brij Paul Singh and Others Vs. State of Gujarat
Continental Construction Co. Ltd. Vs. State of Madhya Pradesh
Dwaraka Das Vs. State of Madhya Pradesh and Another
Mohd. Salamatullah and Others Vs. Government of Andhra Pradesh
Pt. Munshi Ram and Associates (P) Ltd. Vs. Delhi Development Authority
Santok Singh Arora v. Union of India and Ors. AIR 1992 SC 1809
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.