SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2019 Supreme(Del) 1771

IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M Singh, J.
Apco-Titan (JV) – Appellant
Versus
National Highways and Infrastructure Development Corporation Ltd. – Respondent
Civil Suit (OS) No. 215 of 2019
Decided On : 22-10-2019

Advocates Appeared:
A.K. Ganguli, Adv., Dharmendra Rautray, Adv., Tara Shahani, Adv., Shivansh Jolly, Adv., Maninder Acharya, Adv., Ramji Srinivasan, Adv., Vikash Kumar Jha, Adv., Karan Khanna, Adv., Nikhil Yadav, Adv., Tishta Tandon, Adv., Prasenjit Keswani, Adv., Kabir Shankar Bose, Adv., Upmanyu Tewar, Adv., Gumoor Kaur, Adv.

The main legal point established in the judgment is that a claim under Section 70 of the Indian Contract Act, 1872 is not maintainable if the conditions for such a claim are not satisfied, and a party cannot be forced to pay a sub-contractor directly if there is a subsisting contract with the main contractor.

Headnote:

Construction Contracts - Infrastructure Projects - Indian Contract Act, 1872 - Section 70 - State of West Bengal v. B.K. Mondale & Sons, AIR 1962 SC 779, Mahanagar Telephone Nigam Ltd. v. Tata Communications Ltd., [Civil Appeal No. 1766/2019, decided on 27th February, 2019], Pannalal v. Dy. Commissioner, Bhandara & Anr., (1973) 1 SCC 639

Fact of the Case:

The Plaintiff, a construction contractor, sought payment for work executed on an infrastructure project from the Defendant, NHIDC, claiming that NHIDC indirectly benefited from the work and was obligated to compensate the Plaintiff under Section 70 of the Indian Contract Act, 1872.

Finding of the Court:

The court found that the Plaintiff's claim under Section 70 was not maintainable as the Plaintiff had a subsisting contract with ITNL, and NHIDC could not be forced to pay the Plaintiff directly. The court allowed the impleadment of ITNL and SSTL as necessary parties and directed the Plaintiff to approach the NCLAT for legal remedies.

Issues: The main issue was whether NHIDC was obligated to compensate the Plaintiff directly for work executed on the project, despite the Plaintiff's subsisting contract with ITNL.

Ratio Decidendi: The court held that the Plaintiff's claim under Section 70 was not maintainable as the conditions for such a claim were not satisfied, and NHIDC could not be forced to break its contract with ITNL and make any payment directly to the Plaintiff.

Final Decision: The court allowed the impleadment of ITNL and SSTL as necessary parties and directed the Plaintiff to approach the NCLAT for legal remedies. The court also directed a meeting between the Secretary, MORTH, representatives of the Plaintiff, and the newly impleaded Defendants to attempt a resolution of the payments to the sub-contractor.

JUDGMENT :

Prathiba M. Singh, J.

I.A. Nos. 5576/19, 10680/19 and 6834/19

Brief Facts

1. The present case demonstrates the difficulties plaguing construction contracts involving the development of infrastructure projects.

2. The Ministry of Road Transport and Highways (hereinafter, "MORTH") is concerned with the promotion, building, maintenance and upgradation of national highways and strategic roads, including interconnecting roads in various parts of the country which share international boundaries with neighbouring countries.

3. Morth had entrusted to the Border Roads Organization (hereinafter, "BRO") the existing road from Km 69 to Km 81.3 on the Srinagar-Gumri road section of National Highway-1 in the State of Jammu and Kashmir and construction of a Z-Morh Tunnel including its approaches (approximately 6.5 km tunnel and 6 km approaches) (hereinafter, "Project"). The BRO was required to augment the said road by two-laning the same.

4. On 16th April, 2012, the BRO, through a Request for Qualification, invited bidders to submit their bids. One M/s Soma Enterprise Private Limited (hereinafter, "M/s Soma") was the successful bidder who was issued a letter of award on 12th March, 2013. The bidder M/s Soma, promoted a special purpose vehicle company called Srinagar Sonamarg Tunnelway Limited (hereinafter, "SSTL") to undertake the Project.

5. On 30th April, 2013, a Concession Agreement was entered into between BRO and SSTL. This Concession Agreement was subsequently transferred from BRO to the Defendant - National Highways & Infrastructure Development Corporation Limited (hereinafter, "NHIDC"), a fully owned company of MORTH, on 12th November, 2014. The Project was to be executed on a design, build, finance, operate and transfer annuity basis. Despite the transfer, the terms of the Concession Agreement continued to bind the Project. The total term of the agreement was for a period of twenty years, which included the construction period of five years. As per the Concession Agreement, NHIDC was obligated to pay the annuities.

6. Sstl appointed IL&FS Transportation Networks Limited (hereinafter, "ITNL"), a company with 48.99% share in SSTL, as the Engineering, Procurement and Construction Contractor (hereinafter, "EPC"), under an agreement dated 9th November, 2015.

7. On 5th July, 2014, i.e. prior to the EPC agreement dated 9th November, 2015, ITNL had floated a RFP for appointment of a Construction Contractor. The Plaintiff i.e., APCO-Titan (JV), submitted its offer letter on 13th December, 2014. On 9th June, 2015, i.e., even prior to the Construction Contract between the Plaintiff and ITNL dated 11th November, 2015, a letter of intent cum notice to proceed had been issued by ITNL to the Plaintiff to commence work on the Project.

8. Itnl is a group company of Infrastructure Leasing and Financial Services Limited (hereinafter, "IL&FS"), against whom liquidation proceedings are pending in the National Company Law Appellate Tribunal (hereinafter, "NCLAT").

Plaintiff's Case

9. The Plaintiff, who was undertaking the construction, claims to have been submitting regular Running Account Bills (hereinafter, "RA Bill") to ITNL. It states that it had imported specialised machinery for undertaking the tunnelling works, exclusively for the Project and the same was done with the knowledge and assistance of the Defendant i.e., NHIDC. Monthly progress reports were also being submitted by the Plaintiff to ITNL. According to the Plaintiff, it has carried out a total value of work to the tune of approximately Rs. 261 crores, however, it has only been paid approximately a sum of Rs. 171 crores. The case of the Plaintiff is that despite the RA bills being duly certified by ITNL engineers and independent engineers, the outstanding amounts have not been paid.

10. Thereafter, ITNL and SSTL began facing financial difficulties and due to non-payment of their dues, the

            Click Here to Read the rest of this document
            1
            2
            3
            4
            5
            6
            7
            8
            9
            10
            11
            SupremeToday Portrait Ad
            supreme today icon
            logo-black

            An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

            Please visit our Training & Support
            Center or Contact Us for assistance

            qr

            Scan Me!

            India’s Legal research and Law Firm App, Download now!

            For Daily Legal Updates, Join us on :

            whatsapp-icon Back to top