2019 Supreme(Del) 1803
IN THE HIGH COURT OF DELHI AT NEW DELHI
G.S. SISTANI, SANGITA DHINGRA SEHGAL, JJ.
Union of India - Appellant
Versus
M/s Chenab Construction Company (Regd) - Respondent
First Appeal From Order (Os) (Comm) No. 16 of 2018
Decided On : 15-10-2019
Act Referred
COMMERCIAL COURTS ACT : S.13(3)
CONTRACT ACT : S.55, S.56
GENERAL CONDITIONS OF CONTRACT ACT : Cl.18, Cl.22(5), Cl.39, Cl.45(a), Cl.55(a)(5), Cl.55, Cl.61(2)
Headnote
Commercial Courts Act - Union of India - Section 13(3) of the Commercial Courts Act, Section 37 of the Arbitration and Conciliation Act, 1996 - 18.1, 17(4), 63 of the General Conditions of Contract - The court upheld the Arbitral Award on Claim No.4 of the respondent for Rs. 30,00,000 on account of escalation during the extended period of contract. The court dismissed the objections on the issue and observed the two types of claims, which would fall under the category of 'Excepted Matters'. The court found no infirmity with the claims awarded to the respondent by the Arbitral Tribunal and upheld the claims awarded to the respondent.
Fact of the Case:
The appellant/Union of India appealed the order dismissing objections to the award and upholding the award of the learned Arbitrator dated 26.12.2016. The appellant rescinded the contract due to slow progress of work and sought to challenge the claims of the respondent for escalation during the extended period of contract and extra expenses incurred.
Finding of the Court:
The court found no infirmity with the claims awarded to the respondent by the Arbitral Tribunal and also upheld the claims awarded to the respondent.
Issues: The issues revolved around the claims of the respondent for escalation during the extended period of contract and extra expenses incurred, and the interpretation of 'Excepted Matters' under the General Conditions of Contract.
Ratio Decidendi: The court upheld the Arbitral Award on Claim No.4 of the respondent for Rs. 30,00,000 on account of escalation during the extended period of contract. The court dismissed the objections on the issue and observed the two types of claims, which would fall under the category of 'Excepted Matters'. The court found no infirmity with the claims awarded to the respondent by the Arbitral Tribunal and upheld the claims awarded to the respondent.
Final Decision: The present appeal was dismissed, and the court upheld the claims awarded to the respondent by the Arbitral Tribunal.
Vijay Kumar Pandey, Adv., Anshuman Sinha, Adv., Sandeep Sharma, Adv., Sarthak Mannan, Adv.
JUDGMENT :
G.S. Sistani, J.
This is an appeal filed under Section 13(3) of the Commercial Courts Act read with Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the Act").
2. The appellant/Union of India has assailed the impugned order dated 22.09.2017 passed by a learned Single Judge of this Court by which the objections to the award have been dismissed and the award of the learned Arbitrator dated 26.12.2016 has been upheld.
3. The brief facts necessary to be noticed for disposal of this appeal are that the appellant/petitioner invited tenders for the work of FAO(OS) (COMM) No.16/2018 Page 2 of 26 Construction of Tunnel No.12 & 12-A from 42/450 Km to 42/500 Km & 42/585 Km to 42/775 Km and cut and cover from 42/425 Km to 42/450 Km and 42/450 Km to 585 Km and 42/775 Km to 42/805 Km including earth work in approaches, breast walls, retaining walls, protection works, drains etc. in zone No. E-24 from 42.400 Km to 42.825 Km on Jammu Udhampur Rail Line Project. On 24.05.1994, the letter of acceptance was issued in favour of the respondent for a consideration of Rs.2,10,37,997/-. On 19.09.1994, a formal agreement was entered between the parties.
4. The consistent stand of the appellant before the learned Arbitrator and also before the learned Single Judge was that although the work was to be completed within a period of 15 months i.e. between 24.05.1994 and 24.08.1995, the progress of the work was very slow and infact the respondent herein was unable to complete the work within the stipulated time period. During the passage of 15 months, the progress of the work was merely 17% while total payment of Rs.23,75,000/- had been made to the respondent up to 3.08.1995 excluding the mobilization advance and machinery advance. It is not in dispute that the appellant vide letter dated 26.09.95 accorded time extension up to 23.02.1996 without any penalty and PVC (Price Variation Clause). Subsequently, four extensions were sought and granted without imposing any penalty, damages and PVC.
5. It is also not in dispute that the last date of completion of work was finally extended up to 31.05.2001. Since the work was not completed the appellant rescinded the contract on 21.11.2001 under clause 62 of the General Conditions of the Contract (GCC) on risk and cost basis. The respondent achieved only 83% of the contractual work till September 2000 and thereafter, no work was done. Resultantly, the appellant rescinded the contract and was forced to issue a fresh tender for the balance work at much higher price.
6. The respondent vide letter dated 29.09.2004, invoked the arbitration clause for adjudicating 11 claims. On 05.06.2008, the appellant nominated Mr. N.C. Goel and Mr. Devender Rai as Arbitrators. Pursuant to which, in 2013, the respondent filed a petition being O.M.P No. 381/2013, claiming that on account of transfer of the Arbitrators, no effective hearing was taking place as per the directions of the court. The respondent sought the indulgence of the court for terminating the mandate of the Arbitral Tribunal and requested for appointment of a Sole Arbitrator. The learned Single Judge passed an order dated 25.02.2015, where the Single Judge terminated the mandate of the Arbitral Tribunal and appointed Hon'ble Mr. Justice Devinder Gupta (retd) as the sole arbitrator.
7. The respondent filed its modified statement of claim before the Arbitrator including Claim no.4 for Rs.30 lacs on account of escalation during the extended period of contract alongwith Claim no.6 for Rs.10 lacs being extra expenses incurred as hire charges of compressors, various cutting machines and equipments etc. for the additional period i.e. after expiry of stipulated period on 23.08.1995 and grant of interest @ 24% per annum on the aforesaid amounts from due dates till the date of payment.
8. The Arbitral Tribunal held the recession of the c