SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(SC) 875

SUPREME COURT OF INDIA
Jagdish Singh Khehar, CJI., D.Y. Chandrachud and Mr. Sanjay Kishan Kaul, JJ.
M/s Ambica Construction - Appellant
Versus
Union of India - Respondent
Civil Appeal No. 410 of 2008
Decided On : 26-04-2017

Advocates Appeared:
For the Appellant : Mr. Raj Kumar Mehta
For the Respondent: Mr. Ajit Kr. Sinha, Ms. Kiran Bhardwaj, Mr. Uday Prakash, Mr. Raj Bahadur, for Mr. Shreekant N. Terdal

Headnote:

INTEREST PENDETE LITE - Arbitration - The Arbitrator awarded interest pendente lite to the claimant, M/s Ambica Construction, at the rate of 15% per annum. The High Court set aside the determination of the arbitrator in awarding interest pendente lite, citing the contractual obligation that expressly barred the award of interest. The Supreme Court, relying on its previous judgment, held that the bar to award interest on delayed payment does not automatically bar the award of interest pendente lite by the Arbitral Tribunal. The Court affirmed the award passed by the arbitrator on the issue of pendente lite interest and set aside the impugned order passed by the Division Bench of the High Court on the question of pendente lite interest.

Fact of the Case:

The appellant, M/s Ambica Construction, was awarded interest pendente lite by the arbitrator, which was later set aside by the High Court based on the contractual obligation that expressly barred the award of interest.

Finding of the Court:

The Supreme Court affirmed the award passed by the arbitrator on the issue of pendente lite interest and set aside the impugned order passed by the Division Bench of the High Court on the question of pendente lite interest.

Issues: The main issue was whether the claimant could have been awarded interest pendente lite by the arbitrator, considering the contractual obligation that expressly barred the award of interest.

Ratio Decidendi: The bar to award interest on delayed payment does not automatically bar the award of interest pendente lite by the Arbitral Tribunal.

Final Decision: The Supreme Court allowed the appeal and directed the pendente lite interest determined by the arbitrator to be paid to the appellant within two months from the date of the judgment.

ORDER :

The only issue that arises for consideration before this Court is, whether the claimant, i.e., the appellant before this Court - M/s Ambica Construction, could have been awarded interest pendente lite by the arbitrator. The arbitrator by his award dated 28.06.1999, besides awarding a sum of Rs.9,20,694/- to the claimant, held the claimant also entitled to interest pendente lite, at the rate of 15% per annum. The operative part of the award passed by the arbitrator depicting the above position is extracted below:

"I therefore award a sum of Rs.9,20,694.00 in favour of the claimant and against the respondent. The claimant will also be entitled to interest pendente lite at the rate of 15% per annum and interest on award until recovery at the rate of 15% per annum."

2. The Union of India, namely, the respondent before this Court, assailed the award passed by the arbitrator in the High Court of Calcutta, by preferring A.P. No. 39 of 1999. A learned Single Judge of the High Court, by an order dated 3.8.2001, affirmed the award passed by the arbitrator on 28.6.1999, including the pendente lite interest, extended to the claimant. The relevant portion of the order of the learned Single Judge is extracted below:

"Apart from that there is no allegation of misconduct against the Arbitrator. There is no impropriety in the matter of procedure or norms of hearing before the Arbitrator. There is hardly any reason for the court to pass an order allowing the application. This application for setting aside the award is dismissed."

3. The award dated 28.6.1999, and the order passed by the learned Single Judge dated 3.8.2001 were then assailed by the Union of India, before a Division Bench of the High Court, by preferring A.P.O.T No. 678 of 2001. While disposing of the above intra-court appeal, the High Court accepted the prayer made by the Union of India, and set aside the determination of the arbitrator in awarding interest pendente lite, by observing as under:

"In respect of award of interest as payment of interest is excluded under clause 16(2) of the agreement and as no reason was assigned by the learned Arbitrator for awarding interest till then, in our opinion, interest could not be awarded and the award is modified by excluding interest therefrom.

In above view of the findings the award stands modified by excluding the award of interest and the appeal is allowed to that extent only."

4. The impugned order passed by the High Court dated 17.06.2005, limited to the determination with reference to pendente lite interest, has been assailed by the appellant, through the instant civil appeal. During the course of hearing, it was not disputed, that the contractual obligation between the parties expressly provided, that interest could not be claimed, either on earnest money or on the security deposit, and even on amounts payable to the claimant. The relevant clause affirming the above position is extracted herein below:

"(2) Interest on amounts. No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract, but Government Securities deposited in terms of sub-clause (1) of this clause will repayable with interest accrued thereon."

The aforesaid clause has been relied upon by the learned counsel representing the Union of India to contend, that when interest was not payable even on the principal amount, there was no question of the same being payable during the period the matter remained pending for adjudication. It is therefore apparent, that the learned counsel for the respondent, relied upon the contractual obligation contained in the clause, extracted herein above, to counter the claim of pendente lite interest and to support the impugned order passed by the High Court.

5. The only contention advanced at the hands of the learned counsel for the appellant, was based on the judgment of this Court in Union of India v. Ambica Construction, (2016) 6 SCC 36, wherein, having examined the l



Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top