IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
Kuber Enterprises - Appellant
Versus
Doosan Power Systems India Pvt Ltd - Respondent
O.M.P.(I) (COMM.) 158 of 2021
Decided on : 19-05-2021
Arbitration and Conciliation Act, 1996 - Section 9(1) - Agreement - Performance Bond - Seeking Direction to Respondent not to invoke and/or encash Performance Bank Guarantees and cheque till further orders - Whether any request had been made by the petitioner for return of said cheque, Mr Nath fairly states that no such request was made by petitioner to respondent - Petitioner claims that scope of work was considerably enhanced and petitioner requested respondents to correspondingly enhance value of Agreement
Finding of the court: It is well settled that a bank guarantee can be interdicted only in exceptional circumstances. Mere contractual disputes cannot be asserted to give rise to special equities. The expression ‘special equities’ is not nebulous. It means peculiar or special circumstances which result in irretrievable injustice. These special equities or special circumstances must be pleaded - Court finds no valid grounds for interdicting invocation of Bank Guarantee - Directed that in event, any request is made by petitioner to respondent for return of cheque, respondent shall either return same or respond to request setting out reasons for its refusal to do so.
Result: Petition is disposed of
JUDGMENT :
VIBHU BAKHRU, J.
IA Nos. 6495/2021, IA 6496/2021
1. Allowed, subject to all just exceptions.
O.M.P.(I) (COMM.) 158/2021
2. The petitioner has filed the present petition under Section 9(1) of the Arbitration and Conciliation Act, 1996 (hereinafter the ‘A&C Act’), inter alia, praying as under:-
ii) Direct the Respondent not to encash the HDFC bank cheque bearing No. 000209 amounting to Rs. 1,18,75,000/- till further orders;
iii) Restrain the Respondent from taking any coercive steps against the Petitioner in relation to the Contract dated 27.12.2017.”
3. Mr Nath, learned counsel appearing for the petitioner has, essentially, stressed on two reliefs. First, that this Court should restrain the invocation of the bank guarantee in question (Performance Bank Guarantee No. 003GT02180720033 of Rs.1,18,75,000 - hereinafter ‘the Bank Guarantee’); and second, that the respondent be directed not to encash the cheque furnished by the petitioner (Cheque bearing No. 000209 amounting to Rs.1,18,75,000/-) till further orders.
4. On 27.12.2017, the parties had entered into an Agreement (Contract No: DPSI-HO-Jawa-15 - hereafter ‘the Agreement’) whereby the respondent sub-contracted CHS Civil Works of Jawaharpur Super Thermal Power Station (2 x 660 MW Project) to the petitioner. In terms of Clause 9.1 of the Agreement, the petitioner furnished the Bank Guarantee as a Performance Guarantee. The petitioner claims that it also issued a cheque for an equivalent value.
5. Clause 9.1 of the Agreement is relevant and set out below:-
a) The Subcontractor shall submit to the Contractor as a guarantee of the faithful performance of the obligations under this Subcontract and a guarantee of the quality of Works and materials provided by the Subcontractor, an unconditional Performance Bond acceptance to the Contractor In the following manner
Performance Bank Guarantee equivalent to Two point Five percent (2.5%) of Contract Value.
In leu of Performance Bank Guarantee equivalent to Two point Five percent (2.5%) of Contract Value, Signed Cheque without date equivalent to Two point Five percent (2.5%) of Contract Value and Five Percent payment hold from progressive payment.
Contractor shall return the cheque and hold amount once Subcontractor submits Performance Bank Guarantee equivalent to Two point Five percent (2.5%) of Contract Value.
The Performance Bond shall expire after expiry date of Warranty Period as defined in Clause 12 [WARRANTY] in this Sub-contract. Such guarantee shall be binding notwithstanding any variations, alterations or extensions of time that may be given or be agreed upon. No interest shall be paid for this bond.
b) The Performance Bond shall be provided by a first class bank of the Country at Contractor’s discretion in the form attached hereto acceptable to the Contractor.”
6. The petitioner claims that the scope of the work was considerably enhanced and the petitioner requested the respondents to correspondingly enhance the value of the Agreement. It is stated that on 08.01.2019, a meeting was held between the parties to sort out the issue of additional financial implication and thereafter, on 21.08.2019, to commensurate with the enhanced scope of work, the value of the Agreement was revised to Rs.66.26 crores.
7. The petitioner claims that there was significant delay in making the payments under the Agreement and the petitioner continued to pursue the respondent for making the payment for extra work executed by it. The petitioner has also annexed several letters along with the petition to the aforesaid effect.
8. By a letter dated 02.04.2021, the respondent reminded the petitioner that the completion date of the Agreement is 30.06.2021 and substantial works are to be completed within the said period. It also cautioned the petitioner that in the event the contr
Svenska Handelsbanken v. M/s. Indian Charge Chrome and Others: (1994) 1 SCC 502
BSES Ltd. V. Fenner India Ltd.
U.P. State Sugar Corpn. v. Sumac International Ltd.
Hindustan Steel Works Construction Ltd. V. Tarapore & Co. and Anr.
U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. (1988) 1 SCC 174
Svenska Handelsbanken v. Indian Charge Chrome (1994) 1 SCC 502
UP State Sugar Corporation v. Sumac International Ltd.: 1997 (1) SCC 568
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.