SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 541

IN THE HIGH COURT OF DELHI AT NEW DELHI
Siddharth Mridul, Anup Jairam Bhambhani, JJ.
Union of India and Anr. - Appellants
Versus
M/S Annavaram Concrete Pvt. Ltd. - Respondent
FAO(OS) (COMM) 96 of 2020 & CM.APPL. 18980 of 2020
Decided On : 31-08-2021

Advocates:
Advocate Appeared:
For the Appellant :Ms. Geetanjali Mohan, Advocate.
For the Respondent:Mr. R.K. Sanghi, Senior Advocate with Mr. Satjendar Kumar, Advocate and Mr. Ishan Sanghi, Advocate.

Point of Law : Arbitration - Arbitral award - It is evident that in case an arbitral award has been confirmed by court under Section 34 and by the court in an appeal under Section 37, this Court must be extremely cautious and slow to disturb such concurrent findings.

Headnote:

Commercial Courts Act 2015 - Section 13 - Delhi High Court Act 1966 - Section 10 - Arbitration & Conciliation Act 1996 - Section 37, 34 - Liquidated damages – Application for setting aside arbitral award – Appealable orders – That completion period for 10,000 sleepers was given 4 months and for the remaining 1,40,000 sleepers, the completion period was given 6 months which is against the principle of natural justice.

Finding of the court : so long as the view taken by an arbitrator, is a possible view based on facts, it is irrelevant whether this court would or would not have taken the same view on the merits of the matter; and the arbitral award is required to be upheld - Being of the opinion that the view taken by the learned Sole Arbitrator, is certainly a possible view based on facts in relation to the merits of the disputes, court find no ground to interfere in the arbitral award or the impugned judgment.

Result : Appeal dismissed.

JUDGMENT :

ANUP JAIRAM BHAMBHANI, J.

The present appeal under section 13 of the Commercial Courts Act 2015 read with section 10 the Delhi High Court Act 1966 and section 37 of the Arbitration & Conciliation Act 1996 (‘A&C Act’) has been filed by the Union of India, Ministry of Railways and North Eastern Railways (‘Railways') impugning judgment dated 27.02.2020 rendered by the learned single Judge of this court in O.M.P. (COMM) No. 112/2020 (‘impugned judgment’), whereby the learned single Judge has upheld arbitral award dated 08.02.2011 (‘arbitral award’) made by the learned Sole Arbitrator in arbitral proceedings between the Railways and M/s Annavaram Concrete Pvt. Ltd., Hyderabad (‘Annavaram’).

2. The Railways had filed a petition under section 34 of the A&C Act challenging arbitral award dated 08.02.2011; in which award the learned Sole Arbitrator had directed the Railways to refund to Annavaram the sum of Rs. 1,22,38,125/-, which had been deducted/withheld by the Railways as ‘liquidated damages’ imposed upon Annavaram for alleged breach of the terms and conditions of a tender bearing No. CS 160/2007, pursuant to which a Letter of Acceptance dated 15.09.2008 (‘1st LoA’) was issued by the Railways to Annavaram for supply of 10000 Pre-Stressed Concrete Sleepers (‘sleepers’) by 14.01.2009.

3. By the impugned judgment, the learned single Judge has upheld the arbitral award and has also awarded interest for the delay in payment of the awarded sum.

4. Briefly, disputes arose between the Railways and Annavaram in relation to alleged non-performance and non-compliance by Annavaram with the terms of the 1st LoA. As per the record, after issuance of the 1st LoA, vidé its letter dated 22.12.2008 Annavaram requested the Railways for an additional order, representing that their capacity was to manufacture 25000 sleepers per month; whereupon vidé a Second Letter of Acceptance dated 27.01.2009 (‘2nd LoA’) the Railways ordered an increased quantity of 150000 (one lac fifty thousand) sleepers to be supplied by Annavaram by 14.07.2009, which order was accepted by Annavaram. It is the Railways’ contention that Annavaram failed to supply even a single sleeper within the stipulated time; nor did they obtain any extension of time for making such supply; whereupon, the contract comprised in the 1st LoA and 2nd LoA lapsed by efflux of time on 14.07.2009. Consequently, it is the contention of the Railways, that as per IRS Condition 0702, the Railways imposed liquidated damages to the tune of Rs. 1,22,38,125/- (Rupees One Crore Twenty-two Lacs Thirty-eight Thousand One Hundred and Twenty-five Only) upon Annavaram on 27.05.2009. It is further contended that on grounds of non-performance, on 08.04.2010 the Railways also terminated the contract with Annavaram.

5. Disputes having arisen between the parties, on 21.06.2010 the learned Sole Arbitrator came to be appointed and entered upon reference. Subsequently he rendered the arbitral award awarding Rs. 1,22,38,125/- (Rupees One Crore Twenty-two Lacs Thirty-eight Thousand One Hundred and Twenty-five Only) in favour of Annavaram and against the Railways, which sum was directed to be refunded within 03 months from the date of the award. For completeness, it may be mentioned that the Railways had also preferred a counter-claim in the sum of Rs. 10,00,000/- (Rupees Ten Lac Only) against Annavaram in the arbitral proceedings.

6. It is the contention of the Railways that the 1st LoA was amended by the 2nd LoA, whereby, apart from increasing the quantity of sleepers to be supplied by Annavaram, clause 1.0 and clause 1.1 were amended and a new clause 1.2 was inserted in the terms and conditions of the contract. Clauses 1.1 and 1.2 as amended/inserted by way of the 2nd LoA read as under :

    * * * * *

“1.1 The supply against this order shall be completed by 14.07.2009.

1.2 On finalisation of the new tender, the ordered quantity in CS-160/2007 shall be reduced to the number of sleepers manufactured till the date of issue of L

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          Judicial Analysis

          SupremeToday

          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top