2021 Supreme(Del) 572

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
M/s Abir Infrastructure Private Limited – Appellant
Versus
Teestavalley Power Transmission Limited & Ors. - Respondent
O.M.P.(I) (COMM.) 163 of 2020
Decided on : 20-09-2021

Advocates:
Advocate Appeared:
For the Appellant :Mr S.S. Ray, Advocate with Ms Rakhi Ray and Mr Vaibhav Gulia,
For the Respondent:Mr Tarun Johri, Advocate with Mr Vishwajeet Tyagi and Mr Ankur Gupta.

Point of Law : Work Contract – Termination of Contract – Stay of invocation of Bank guarantees – BGs to be conditional upon a demand being made in express terms thereof - Court did not hold that conditions regarding failure of the Contractor to fulfil its obligations under the Contract would be met only on a competent court determining the same.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 9- Work Contract – Termination of Contract - Bank Guarantees – Stay of invocation of Bank guarantees – Petitioner has completed more than 50 % of the works – Respondent issued the cure notice post the invocation of the bank guarantees.

Finding of the Court :

TPTL had terminated the Contract and consequently the remaining works had to be contracted to another contractor, who has since completed the same - BGs in question were issued to secure TPTL against the advance payments made to AIPL. The said advance payments were to be adjusted against the demand to be made pursuant to the RA bills. It is not disputed that part of the advances were duly adjusted against the RA bills and the value of the BGs in question were reduced correspondingly - BGs in question are sought to be invoked in respect of advances that remain unrecovered or unadjusted. AIPL claims that it has presented the RA Bills to the extent of Rs.12.44 crores. However, TPTL does not admit that the same is payable. The disputes between the parties are yet to be adjudicated/resolved -Court is unwilling to accept that TPTL can be interdicted from invoking the BGs in question in terms thereof -Court is unable to accept that TPTL is required to be injuncted from invoking the BGs in question or SBI is required to be restrained from making any payments against the same, pending adjudication of the disputes between the parties.

Result: Petition dismissed

JUDGMENT :

VIBHU BAKHRU, J

1. Abir Infrastructure Private Limited (hereafter ‘AIPL’) has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter the ‘A&C Act’), inter alia, praying that respondent no.1, Teestavalley Power Transmission Limited (hereafter ‘TPTL’), be restrained from invoking the Bank Guarantees bearing no. 0910310BG0000163 and 0910310BG0000165 issued by respondent no.2, State Bank of India. In the alternative, AIPL further prays that respondent nos. 2 and 3 (collectively referred to as ‘SBI’) be directed to not entertain any invocation of the aforementioned Bank Guarantees and to not encash the same.

2. The aforementioned Bank Guarantees are referred to as BG-163 and BG-165 and are collectively referred to as ‘the BGs in question’.

The present value of BG-163 is Rs.7,11,04,475/-and that of BG-165 is Rs.61,71,284/-.

3. Mr Ray, learned counsel appearing for AIPL, contended that TPTL is not entitled to invoke the BGs in question as the same are not unconditional Bank Guarantees and the requisite conditions for invoking the same – that AIPL has failed to perform the contract in question; has been called upon to pay the sum advanced; and has failed to pay the same – have not been met. According to him, it is not established that AIPL has failed to perform the contract in question, and therefore, the conditions in the underlying Contract have not been fulfilled. He submitted that since there is no finding of any Court or Tribunal of competent jurisdiction that AIPL has failed to fulfil its obligations under the terms of the Contract with TPTL, the BGs in question cannot be invoked.

4. It is AIPL’s case that the issues involved in the present petition are no longer res-integra in view of the decision of a Coordinate Bench of this Court in Abir Infrastructure Private Ltd. v. Teestavalley Power Transmission Ltd. & Ors : 214 (2014) DLT 235. AIPL contends that this Court had considered the wordings of the BGs in question and had rejected TPTL’s contention that the BGs in question were unconditional. The Court found that the BGs in question were conditional and could be invoked only if the conditions were met.

5. The controversy in the present case arises in the following context :-

5.1 The disputes between AIPL and TPTL arises in respect of an Agreement dated 22.02.2010 (hereafter ‘the Contract’) that was entered into between TTPL and a consortium of AIPL and M/s Deepak Cable India Limited for “the construction of 400 KV D/C Transmission Line from the 1200 MW TEESTA III Hydro Electric Project in the State of Sikkim to the Kishanganj Pooling Station in the State of Bihar spanning a length of approximately 212 KM” (hereafter ‘the Project’).

5.2 The Project was divided into two geographical sections. The first section stretched from TEESTA III Hydro Electric Project in the State of Sikkim to Panighata, West Bengal (termed as ‘Package A-1’). The second section stretched from Panighata, West Bengal to Kishanganj, Bihar (termed as ‘Package A-2’). The scope of work under the Project in respect of each section was covered under two Agreements – being the Supply Agreement and Service Agreement.

5.3 The consideration payable for the Supply and Service Agreements for the first section Package A-1 was agreed at Rs.1,08,39,99,596/-(Rupees One Hundred and Eight Crores, Thirty Nine Lakhs, Ninety Nine Thousand, Five Hundred and Ninety Six only) and Rs.117,41,06,487/-(Rupees One Hundred and Seventeen Crores, Forty One Lakhs, Six Thousand, Four Hundred and Eighty Seven only) respectively. The consideration for the Supply and Service Agreements for Package A-2 was agreed at Rs.54,97,41,986/-(Rupees Fifty Four Crores, Ninety Seven Lakhs, Forty One Thousand, Nine Hundred and Eighty Six only) and Rs.36,72,49,533/-(Rupees Thirty Six Crores, Seventy Two Lakhs, Forty Nine Thousand, Five Hundred and Thirty Three only) respectively. Thus, the aggregate consideration for the works under the Supply and Service Agreeme

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top