SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 1720

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Unison Hotels Private Limited - Appellant
Versus
M/s Value Line Interiors Private Limited - Respondent
O.M.P. (Comm) No. 97 of 2016
Decided On : 01-03-2021

Advocates appeared:
Darpan Wadhwa, Advocate, Ajay Bhargava, Advocate, Aseem Chaturvedi, Advocate, Wamika Trehan, Advocate, Shivank Diddi, Advocate, Namit Suri, Advocate, Purnima Singh, Advocate, Priyanka Kumar, Advocate, Shivani Malik, Advocate

Parties in arbitration proceedings must comply with orders and actively participate in the proceedings, failing which they may be deemed to have obstructed the proceedings and disentitled to relief.

Headnote:

Unison - Arbitration - Arbitration and Conciliation Act, 1996 (Section 34(2)(iii)) - The court considered whether the impugned award fell foul of Section 34(2)(iii) of the A&C Act. The court found that Unison had ample opportunity to file its defence and raise counter-claim(s) but willfully obstructed the arbitral proceedings. The court dismissed the petition, finding no reason to interfere with the impugned award.

Fact of the Case:

Unison filed a petition to set aside an Arbitral Award, claiming it was passed without affording Unison a proper opportunity to be heard. Unison engaged VIPL for services and works, but disputes arose regarding payment. Despite multiple opportunities, Unison failed to file its Statement of Defence and counter-claim(s) and obstructed the arbitral proceedings.

Finding of the Court:

The court found that Unison had ample opportunity to contest the claims made by VIPL but willfully obstructed the arbitral proceedings instead of contesting the claims/proceedings. The court dismissed the petition, finding no reason to interfere with the impugned award.

Issues: Whether Unison was denied the opportunity to present its case and whether the impugned award fell foul of Section 34(2)(iii) of the A&C Act.

Ratio Decidendi: Unison had ample opportunity to file its defence and raise counter-claim(s) but willfully obstructed the arbitral proceedings. The court found that Unison's conduct disentitled it to any relief and dismissed the petition.

Final Decision: The court dismissed the petition, finding no reason to interfere with the impugned award.

JUDGMENT

Vibhu Bakhru, J. - Unison Hotels Private Limited (hereinafter 'Unison') has filed the present petition impugning an Arbitral Award dated 08.05.2015 (hereinafter 'the impugned award') rendered by the Arbitral Tribunal comprising of a Sole Arbitrator on the ground that it was passed without affording Unison a proper opportunity to be heard.

2. Mr. Darpan Wadhwa, learned senior counsel appearing for Unison had, at the outset, submitted that the impugned award is liable to be set aside on the sole ground that Unison was denied the opportunity to present its defence and therefore, the impugned award is liable to be set aside in terms of Clause (iii) to Sub-section (2) of Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter 'the A&C Act'). Thus, the principal question that falls for consideration by this Court is whether the impugned award falls foul of Section 34(2)(iii) of the A&C Act.

    Factual Matrix

    3. Unison is a company incorporated under the Companies Act, 1956 and is engaged in the Hospitality business. It had launched a hotel named "The Grand" New Delhi (earlier known as "Grand Hyatt", New Delhi). The said property is a 400 room hotel, which opened for guests in the year 2000. The respondent (hereinafter 'VIPL') is engaged in the business of interior decoration on turn-key basis, providing infrastructure, improvements, interior designing etc.

    4. Unison had engaged VIPL for providing certain services and executing works in connection with redevelopment/development of its hotel - The Grand. Admittedly, Unison had issued four separate Work Orders to VIPL - Work Orders dated 01.07.2008; Work Order dated 28.08.2008; Work Order dated 28.11.2008; and Work Order dated 28.12.2008 for executing certain works. VIPL claims that the rates for such extra items were to be derived in terms of the contract. It claims that at the request of Unison, it executed certain extra works but its claims, in that regard, were not paid. VIPL raised final bill aggregating to Rs. 9,14,97,478/- and against the same, Unison paid a sum of Rs. 6,97,25,620/-. According to VIPL, Unison failed and neglected to pay the balance amount of Rs. 2,43,71,848/-, without any justifiable reason. VIPL claims that the only reason provided by Unison for withholding the said payment was the non-receipt of a completion certificate by the Engineer appointed by Unison. According to VIPL, the said reason was without any substance, as the Engineer had cleared and approved the measurements, as submitted by VIPL, along with the Final Bill at the material time. However, certain objections were made regarding the quality of work after a considerable period had elapsed.

    5. Since Unison failed to release the payments, which according to VIPL were owed by Unison, VIPL issued a notice of demand dated 30.06.2011 and invoked the Arbitration Clause. It also suggested the name of a former Additional District and Sessions Judge for being appointed as the Sole Arbitrator. Unison responded to the said notice by a letter dated 29.07.2011, denying the claims raised by VIPL. Further, it did not concur with the appointment of an Arbitrator as suggested by VIPL.

    6. In view of the impasse, VIPL filed a petition under Section 11(6) of the A&C Act (being ARB.P. 316/2011) in this Court praying that an Arbitrator be appointed. And, by an order dated 09.10.2012 passed in the said matter, this Court appointed Justice Devinder Gupta, a former Judge of this Court as the Sole Arbitrator to adjudicate the disputes between the parties. This Court further directed that the Arbitration would be conducted under the aegis of Delhi International Arbitration Centre (then known as 'Delhi High Court Arbitration Centre').

    7. Thereafter, by a letter dated 28.10.2012, the learned Arbitrator informed the parties that he had accepted his appointment as an Arbitrator and called upon the parties to appear for a preliminary hearing on 09.11.2012. However, none of the parties appeared before him on that date.

    8

                      Click Here to Read the rest of this document
                      1
                      2
                      3
                      4
                      5
                      6
                      7
                      8
                      9
                      10
                      11
                      SupremeToday Portrait Ad
                      supreme today icon
                      logo-black

                      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                      Please visit our Training & Support
                      Center or Contact Us for assistance

                      qr

                      Scan Me!

                      India’s Legal research and Law Firm App, Download now!

                      For Daily Legal Updates, Join us on :

                      whatsapp-icon Back to top