IN THE HIGH COURT OF DELHI AT NEW DELHI
Vipin Sanghi, Navin Chawla, JJ.
JMC Projects (india) Limited & Anr. - Appellantss
Versus
National Highways Authority Of India & Ors. - Respondents
LPA 154 of 2022 & CM Appl. 10729 of 2022
Decided On : 11-04-2022
Security Clearance - Construction Contract - Clause 2.1.12(a) of the Request for Proposal - [Clause 2.1.12(a)] - [Summary of Acts and Sections]
Fact of the Case:
The appellants challenged the denial of security clearance for a construction contract in Jammu & Kashmir due to the involvement of a Turkish company in the joint venture. The court rejected the challenge and upheld the denial of security clearance.
Finding of the Court:
The court found that the denial of security clearance was justified under Clause 2.1.12(a) of the Request for Proposal, and the appellants' argument that security clearance was not required was rejected. The court also held that the absence of a list of eligible or ineligible countries did not exempt the appellants from seeking security clearance.
Issues: Challenge to denial of security clearance, interpretation of Clause 2.1.12(a) of the Request for Proposal, absence of list of eligible or ineligible countries for security clearance.
Ratio Decidendi: The denial of security clearance was upheld as justified under Clause 2.1.12(a) of the Request for Proposal, and the absence of a specific list of eligible or ineligible countries did not exempt the appellants from seeking security clearance.
Final Decision: The appeal was dismissed with no order as to costs.
ORDER
1. This appeal has been filed challenging the judgment dated 04.02.2022 passed by the learned Single Judge of this Court in WP(C) 13160 of 2021, inter alia rejecting the challenge of the petitioners/appellants to the communication dated 18.11.2021 whereby the respondent no. 1 informed the appellants that its security clearance in terms of Clause 2.1.12(a) of the Request for Proposal for construction of four laning of Part of Ramban to Banihal Section of NH-1A (Now NH-44), from Ch.154+210 to Ch.158+650 (North Bound) and from Ch.155+940 to Ch.160+282 (South Bound) including Construction of Twin Tube Tunnels (Package-I) in the UT of Jammu & Kashmir on EPC Mode (hereinafter referred to as the RFP) has been denied by the Competent Authority.
2. The impugned order further directs the respondent no. 1 to forward the proposal for grant of the security clearance to respondent no. 3 for consideration by the respondent no. 2, and a further direction to the respondent no. 2 to take a decision on such request within a period of three weeks. The impugned order clarifies that, in case, the security clearance to respondent no. 3 is declined for any reason whatsoever, the respondent no. 1 will be free to proceed further as per the terms of RFP to award the contract to the next bidder, subject to its meeting the criteria under Clause 2.1.12(a) of the RFP, if applicable.
3. The above-mentioned writ petition was filed by the petitioners/appellants seeking the following reliefs:
(i) Issue a writ of mandamus/certiorari or a writ in the nature of mandamus/certiorari or any other writ, order or direction quashing and setting aside the impugned communication dated 18.11.2021 and actions of the Respondents 1 and 2, disqualifying it from further participation in the tender process and award of contract to JMC-AGE JV, for the construction of construction of four laning of part of Ramban to Banihal Section of NH-1A (now NH-44), from CH.154+2.0 to CH.158+675 (North Bound) and from CH.155+940 to CH.l60+282 (South Bound) including construction of Twin Tube Tunnel (Package-1) in the Union Territory of Jammu & Kashmir by EPC Mode;
(ii) Issue a writ of mandamus or a writ in the nature of mandamus or any other writ, order or direction directing the Respondents to award the contract to JMC-AGE JV, pursuant to the tender issued and bid submitted by JMC-AGE JV, for the consumption of four laning of part of Ramban to Banihal Section of NH-1A (now NH-44), from CH.154+2.0 to CH.158+675 (North Bound) and from CH.155+940 to CH.160+282 (South Bound) including construction of Twin Tube Tunnel (Package-1) in the Union Territory of Jammu & Kashmir by EPC Mode;
4. It was the case of the appellants that the appellant no. 2 is a Joint Venture (in short, JV), of which the lead member, holding 74% participation share, is an Indian company, that is, appellant no. 1. The minority participation partner with the remaining 26% share is a Turkish company, M/s Age Insaat Ve Ticaret Anonim Sirketi (hereinafter referred to as the M/s Age).
5. The said JV was declared as technically qualified in the RFP and, thereafter, was declared as a L-1 bidder in the financial bids.
6. At that stage, the respondent no. 1 issued the impugned communication dated 18.11.2021, informing the petitioners/appellants that their security clearance was denied by the Competent Authority.
7. It is the case of the appellants that in terms of Clause 2.1.12(a) of the RFP, since the JV had an Indian partner holding more than 50% share therein, Clause 2.1.12(a) of the RFP was not attracted. It was further contended that the respondent no. 1 had adopted a pick and choose policy for obtaining security clearance, inasmuch, as, for the respondent no. 3, which also had a Ukrainian JV partner, respondent no. 1 did not obtain security clearance and proceeded to issue a Letter of Acceptance in its favour.
8. As noted hereinabove, the learned Single Judge has rejected the submission of the appellants that Clause 2.1.12(a) o
AI
The denial of security clearance was justified under Clause 2.1.12(a) of the Request for Proposal, and the absence of a specific list of eligible or ineligible countries did not exempt the appellants....
The main legal point established in the judgment is the importance of adhering to the terms of the RFP and the interpretation given by the author of the document, while also considering the public in....
The court affirmed that public authorities must act reasonably and fairly, finding that the failure to seek required security clearance in contractual bids constituted arbitrariness, impacting public....
The Court would not normally interfere with the policy decision and in matters challenging the award of contract by the State or public authorities
Courts defer to executive in denying security clearance for foreign bidders in strategic projects on national security grounds, limiting review to arbitrariness; prior clearances do not entitle futur....
The cancellation of an Air Operator Permit without disclosing reasons for denial of security clearance violates principles of natural justice, rendering the process invalid.
Tendering authorities have discretion in setting eligibility criteria, which must be clear and cannot be deemed vague or arbitrary unless proven otherwise, emphasizing principles of fairness and natu....
The restriction on construction to ground floor only was arbitrary and discriminatory, violating Article 14 of the Constitution, as prior permissions for G+2 were not duly considered.
The judgment emphasizes the importance of providing reasons and a reasonable opportunity for the petitioner to respond in administrative actions affecting civil rights, highlighting that the absence ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.