IN THE HIGH COURT OF DELHI AT NEW DELHI
Rajiv Shakdher, Poonam A. Bamba, JJ.
Jasmine Buildmart Pvt. Ltd. - Appellant
Versus
Neeru Jain - Respondent
First Appeal From Order (OS) (COMM) No. 148 of 2020, Civil Miscellaneous Application No. 29253 of 2020
Decided On : 28-03-2022
Arbitration - Interim Relief - Interpretation of Section 9(1) and 9(2) of the Arbitration and Conciliation Act, 1996
Fact of the Case:
The appeal challenged the order of the learned Single Judge in an arbitration matter where interim directions were issued in favor of the respondent under Section 9(1) of the Arbitration and Conciliation Act, 1996. The appellant sought further clarification on the steps taken during the period of the interim order.
Finding of the Court:
The court directed the appellant to seek necessary clarification/modification/review of the order dated 27.07.2020 from the learned Single Judge, and disposed of the appeal with liberty to the appellant to move the learned Single Judge with an appropriate application for clarification.
Issues: Interpretation of Section 9(1) and 9(2) of the Arbitration and Conciliation Act, 1996, and the need for further clarification on the steps taken during the period of the interim order.
Ratio Decidendi: The court interpreted that when the proceedings commence prior to the court passing an order granting interim relief under Section 9(1) of the Act, the provisions of Section 9(2) would have no application, and allowed the appellant to seek necessary clarification/modification/review of the order dated 27.07.2020.
Final Decision: The appeal was disposed of with liberty to the appellant to seek necessary clarification/modification/review of the order dated 27.07.2020 from the learned Single Judge.
JUDGMENT
Rajiv Shakdher, J. - This appeal is directed against the order dated 27.07.2020, passed by the learned Single Judge in Ia No.721/2020 in O.M.P. (I) (COMM.) No.280/2019.
1.1. a perusal of the order dated 27.07.2020 would show that there were several other interlocutory applications [Ias] moved, which were also dealt with by the learned Single Judge via very same order. Suffice it to state that these applications, including the application adverted to hereinabove i.e., I.a. No.721/2020, were applications moved by the original petitioners (including the respondent herein) for clarification/modification of the judgment dated 21.10.2019.
2. The learned Single Judge, via judgment dated 21.10.2019, had, in exercise of powers vested in her under Section 9(1) of the arbitration and Conciliation act, 1996 [in short, 1996 act'], passed an interim order in favour of the respondent i.e., the original petitioner. The interim directions issued by the learned Single Judge, via the said judgment, were to remain in place for a period of 90 days, as prescribed under Section 9(2) of the 1996 act.
2.1. It appears that this direction was issued, based on an understanding by the learned Single Judge, that no steps had been taken for initiation of arbitration proceedings. It is based on this aspect, that applications were moved for clarification/modification of the judgment dated 21.10.2019.
2.2. Based on the facts brought to the notice of the learned Single Judge, the following operative directions were passed by her via the impugned order:
'9. Reading Section 9(2) conjointly with Section 21 can lead only to one inevitable conclusion that when the proceedings commence prior to the Court passing an order granting interim relief to a party under Section 9(1) of the act, provisions of Section 9(2) would have no application. In view of this settled position of law applications seeking modification deserve to be allowed.
10. Direction of the Court in para 52 of the judgement dated 21.10.2019, whose modification is sought, is as follows :-
"52. Petitioners must take steps for constitution of the arbitral Tribunal as the present interim order shall remain in operation only for the period as prescribed in 9(2) of the act....."
11. This direction is deleted and the Judgement dated 21.10.2019 stands modified to this limited extent. applications are disposed of accordingly.'
3. Ms Bina Gupta, who appears for the appellant i.e., the original respondent, says that a further clarification is required as to what would happen with regard to the steps that the appellant [i.e., the original respondent] took while the judgment dated 21.10.2019 was in place i.e., before the impugned order i.e., order dated 27.07.2020 was issued.
3.1. In these circumstances, we are of the view that the appellant should move the learned Single Judge for necessary clarification/modification/review of the order dated 27.07.2020.
3.2. accordingly, the appeal is disposed of, with liberty to the appellant to move the learned Single Judge with an appropriate application for the purpose articulated hereinabove.
4. The pending application shall, consequently, stand closed.
5. Needless to add, if the application, as indicated above, is moved by the appellant, appropriate orders will be passed by the learned Single Judge after hearing the respondent.
Interpretation of Section 9(1) and 9(2) of the Arbitration and Conciliation Act, 1996 in the context of granting interim relief and the need for further clarification on the steps taken during the pe....
Interim relief under Section 9(1) of the Arbitration Act does not apply once arbitration proceedings have commenced; directions made under such circumstances may be modified.
The residuary clause of Section 9(1)(ii) of the Arbitration and Conciliation Act, 1996 does not cover orders passed by the Tribunal concerning the calculation of fee based on the interpretation of th....
The court clarified that the residuary clause in Section 9(1)(ii)(e) of the Arbitration and Conciliation Act does not permit intervention for issues pertaining to fee calculation by the Tribunal.
The court clarified that once an application for interim relief under Section 9 of the Arbitration Act is entertained, it can proceed despite the constitution of an Arbitral Tribunal, unless the reme....
The main legal point established in the judgment is that an interim order under section 9 of the Arbitration and Conciliation Act, 1996 must continue to safeguard the interest of the claimant till th....
The main legal point established in the judgment is that interim orders in arbitration proceedings, not falling within the appealable orders under the Act, are not subject to correction by the High C....
The court emphasized the importance of timely action in arbitration proceedings and deemed the appellant's conduct objectionable, leading to dismissal of the appeal and enhancement of costs.
The main legal point established in the judgment is the maintainability of an appeal under section 37(1)(b) of the Arbitration & Conciliation Act, 1996, and the need for clear authority of law for th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.