2023 Supreme(Del) 287
IN THE HIGH COURT OF DELHI AT NEW DELHI
Prathiba M. Singh, J.
Municipal Corporation of Delhi & Ors. – Petitioners
Versus
Lokpal of India - Respondent
W.P.(C) 17745 of 2022 & CM APPL. 56702 of 2022
Decided On : 18-01-2023
Subject
Administrative Law - Judicial Review
Act Referred
CRIMINAL PROCEDURE CODE : S.173
Lokpal and Lokayuktas Act : S.14, S.20, S.20(1)(a), S.20(1)(b), S.20(3), S.20(3)(a), S.25(3)
Headnote
Illegal constructions - Investigation by CBI against public servants - Case of Petitioners is that in terms of impugned order, Lokpal has directed an omnibus investigation by CBI against public servants belonging to MCD and other agencies responsible for allowing illegal constructions in South Delhi area – Held, CVC sought a Report from Vigilance department of MCD - Upon received said report, CVC merely forwarded same to Lokpal - In effect therefore, there has been no enquiry by CVC at this stage - Insofar as Lokpal is concerned, it gave an opportunity to officials to file a reply and after considering matter, directed investigation by CBI, vide impugned order - After perusing record, hearing submissions and also perusing original file, this court is of prima facie opinion that various legal issues including that of jurisdiction of Lokpal and legality of manner in which Lokpal has proceeded would arise for consideration in present case - Respondent shall place their position on record by way of a counter affidavit within four weeks - In meantime, CBI shall not proceed with investigation in terms of impugned order – Ordered accordingly.
For the Petitioner:Mr. Sandeep Sethi & Mr. Rajshekhar Rao, Sr. Advocates, with Mr. Sanjay Vashishttha and MR. Ajjay Arora, Standing Counsels for MCD with Mr. Kapil Dutta, Mr. Anuj Bhargava and Mr. Rahul Kumar, Advocates
For the Respondent:Mr. Apoorv Kurup and Ms. Swati Bhardwaj, Advocates, Mr. Ripu Daman Bhardwaj, SPP with Mr. C.P. Ojha Advocate.
JUDGMENT :
Prathiba M. Singh, J.
1. This hearing has been done through hybrid mode.
2. The present petition has been preferred by the Municipal Corporation of Delhi along with three officials seeking setting aside/ quashing of the impugned order dated 28th November, 2022 passed by the Respondent- Lokpal of India. By way of the impugned order, the Respondent has directed investigation in respect of unauthorized construction in South Delhi during January, 2020 to May, 2021 by the CBI under section 20(3)(a) of the Lokpal & Lokayuktas Act, 2013 (hereinafter ‘Act’).
3. The case of the Petitioners is that in terms of the impugned order, the Lokpal has directed an omnibus investigation by the CBI against public servants belonging to MCD and other agencies responsible for allowing illegal constructions in South Delhi area. The operative part of the impugned order reads as under:-
“The learned Advocate has vigorously pleaded the case of the respondent public servants (Respondent No.1, 2 and 3) arguing that they are in no way accountable/responsible for illegal construction within their jurisdiction. He has also pleaded that apart from MCD, several other authorities like Delhi Police, DJB, BSES and Sub-Registrar offices have a role to play in ensuring that illegal construction does not take place. From the Status Report received from MCD through CVC as also from the personal hearing conducted by this Bench so far, the precise role of the respondent public servants in the unauthorized construction in South Delhi area is not forthcoming. However, it goes without saying that illegal construction of properties has taken place on a massive scale in South Delhi area during the relevant periods. By their own admission, MCD has informed that 1141 properties were booked for unauthorized construction in the area. They have also informed that they have written to various other agencies for taking appropriate action in these cases. During the course of personal hearing, it was specifically asked what action was taken by other agencies on the basis of letters written to them by the MCD. The respondent public servants were clueless on this and submitted that they have no information about action taken by other agencies on their letters. It, therefore, appears that the letters were written by the MCD officers in a routine manner and no follow-up action was taken to ascertain whether any preventive or punitive or punitive action has been taken by other agencies. The role played by other agencies and their accountability is also not forthcoming either from the Status Report or from the proceedings during the course of personal hearing conducted in this case. The only undisputed fact is that illegal construction has been going on unabated in South Delhi area on a massive scale. It is, therefore, in the fitness of things that public servants belonging to MCD and other agencies responsible for allowing illegal construction in South Delhi commission indulged in by them. We, therefore direct that detailed investigation in the cases of unauthorized construction in South Delhi area during the period for January, 2020 to May, 2021 may be conducted by the CBI under Section 20(3)(a) of the Lokpal & Lokayuktas Act, 2013.
We also direct that the investigation may be conducted as expeditiously as possible and may be completed within a period of six months i.e. by 31.05.2023.
We also direct under Section 25(3) of the Act that the Investigation Officer (IO) entrusted with the investigation of this case by the CBI may not be transferred without the approval of Lokpal of India.”
4. The matter was first listed before this Court on 23rd December, 2022. On the said date, intimation was directed to be issued to the Lokpal and Mr. Apoorv Kurup, ld. Standing Counsel has appeared on behalf of the Respondent. On 5th January, 2023, certain legal issues were raised by the learned Senior Counsels appearing for the Petitioners and the matter was adjourned to 9th January, 2023 on which dat