IN THE HIGH COURT OF DELHI AT NEW DELHI
Prateek Jalan, J.
M/s Kbg Engineers – Appellant
Versus
Delhi State Industrial And Infrastructure Development Corporation Ltd. – Respondent
Arb.P. 26 of 2023
Decided On : 07-02-2023
Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - Section 11 - Clause 25 of the General Conditions of Contract
Fact of the Case:
The petitioner sought appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 for disputes arising from a contract for construction of roads and SW drains. The respondent-Delhi State Industrial and Infrastructure Development Corporation Limited had not paid the petitioner for the work done.
Finding of the Court:
The Court held that the issue of limitation and compliance with the procedure for Dispute Redressal Committee (DRC) under Clause 25 should be left for consideration by the arbitrator. The respondent was directed to constitute a DRC and if the DRC does not give a decision within 90 days, or either party is dissatisfied with the decision, disputes will be referred to arbitration.
Issues: The issues were the limitation of claims and the compliance with the procedure for DRC under Clause 25 of the General Conditions of Contract.
Ratio Decidendi: The Court followed the principle of 'when in doubt, do refer' and decided to leave the question of limitation for the arbitrator. It also directed the respondent to constitute a DRC and provided for arbitration if the DRC does not give a decision within 90 days or if either party is dissatisfied with the decision.
Final Decision: The petition was disposed of with directions for the respondent to constitute a DRC and for arbitration if the DRC does not give a decision within 90 days or if either party is dissatisfied with the decision.
JUDGMENT
Prateek Jalan, J. (Oral)--The petitioner has approached this Court under Section 11 of the Arbitration and Conciliation Act, 1996 ["the Act"], for appointment of an arbitrator to adjudicate disputes between the parties under a contract for construction of roads and SW drains at Qutub Vihar, Phase-1, Najafgarh, Matiala. The contract was awarded to it by the respondent-Delhi State Industrial and Infrastructure Development Corporation Limited ["DSIIDC"] vide letter of acceptance dated 14.02.2012, pursuant to a tender issued by the respondent.
2. Notice of this petition was issued on 11.01.2023, and the respondent was granted time to file a reply. Although DSIIDC's reply has not come on record, a copy has been handed up in Court and is taken on record.
3. The contract incorporates Clause 25 of the General Conditions of Contract ["GCC"], which provides for settlement of disputes and arbitration. The relevant parts of the said clause are reproduced below:
"Settlement of Disputes & Arbitration
Except where otherwise provided in the Contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the Contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:
3) If the Contractor considers any work demanded of him to be outside the requirements of the Contract, or disputes and drawings, record or decision given in writing by the Engineer on any matter in connection with or arising out of the Contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days request the superintending engineer shall give his written instructions or decision within a period of one month from the receipt of the Contractor's letter.
If the superintending engineer fails to give his instructions or decision in writing within the aforesaid period or if the Contractor is dissatisfied with the instructions or decision of the superintending engineer, the Contractor may, within 15 days of the receipt of the superintending engineer decision, appeal to the chief engineer who shall afford an opportunity to the Contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Chief Engineer shall give his decision within 30 days of receipt of contractor's appeal. If the Contractor is dissatisfied with this decision of the Chief Engineer, the contractor may within 30 days from the receipt of the Chief Engineer decision, appeal before the Dispute Redressal Committee (DRC) along with a list of disputes with amounts claimed in respect of each such dispute and giving reference to the rejection of his disputes by the Chief Engineer. The Dispute Redressal Committee (DRC) shall give his decision within a period of 90 days from the receipt of Contractor's appeal. The constitution of Dispute Redressal Committee (DRC) shall be as indicated in Schedule `F \ If the Dispute Redressal Committee (DRC) fails to give his decision within the aforesaid period or any party is dissatisfied with the decision of Dispute Redressal Committee (DRC), then either party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), give notice to the Chief Engineer for appointment of arbitrator on prescribed proforma as per appendix XV, failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator.
It is the term of contract that each party invoking arbitration must exhaust the aforesaid mechanism of set
The Court emphasized the principle of 'when in doubt, do refer' and left the issues of limitation and compliance with the procedure for DRC under Clause 25 for consideration by the arbitrator.
The court emphasized that objections of time-bar and prematurity cannot prevent the constitution of an Arbitral Tribunal, and relied on precedents to appoint a Sole Arbitrator.
The court ruled that claims regarding limitation and the validity of invoking arbitration must be determined by the Arbitral Tribunal, reaffirming the applicability of Article 137 of the Limitation A....
The pre-arbitration procedures under the arbitration clause are not always mandatory, and the court may refer disputes to arbitration if the requisites of arbitrability and notice under the Arbitrati....
Arbitration - Appointment of Arbitrator - Court is not required to examine any other contentious issues regarding the disputes between the parties at the stage of referring the parties to arbitration....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.