IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Ms J J Fabtex Pvt. Ltd. – Appellant
Versus
United India Insurance Co. Ltd. – Respondent
O.M.P. (COMM) 310 of 2021 & I.A. 13224 of 2021 & I.A. 13225 of 2021
Decided On : 21-03-2023
Arbitration Act - Challenge to Arbitral Award - Section 34
Fact of the Case:
The petitioner sought coverage for a fire at their factory, which was allegedly not acted upon by the respondents as per their scheme and policies. The petitioner challenged the Award passed by the Arbitral Tribunal, citing various objections.
Finding of the Court:
The Court dismissed the petition on the grounds of significant delay in filing, absence of application seeking condonation of delay, and contravention of procedural and technical requirements.
Issues: Delay in filing the petition, challenge to the Award, and maintainability of the petition.
Ratio Decidendi: The Court emphasized the importance of adhering to the time limits stipulated under Section 34(3) of the Arbitration Act and the need for due diligence in exercising powers for allowing condonation of delay.
Final Decision: The petition was dismissed along with pending applications, as it was not maintainable for being barred by limitation.
ORDER
Chandra Dhari Singh, J. (Oral)
1. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter "the Arbitration Act") seeking the following reliefs:
"a) To allow the present petitioner in the favour of the petitioner and against the respondent and set aside the imposed award dated 15th July, 2019 to the effect whereby the Arbitral Tribunal has no objection Reply to the petitioner.
b) Pass any other order deem fit and proper to this Hon'ble Court in the interest of justice."
2. The petitioner, by way of the instant petition, has assailed the Award dated 12th July 2019, which has been passed by the Arbitral Tribunal in the arbitration proceedings initiated between the parties pursuant to the disputes arisen amongst them stemming from the insurance coverage sought by the petitioner from the respondent.
3. On 13th June 2015, a fire broke out at the NOIDA factory of the petitioner, for which the petitioner sought coverage, however, it has been alleged that the same was not acted upon by the respondents as per its scheme and policies, after which the said reference to arbitration was sought.
4. The learned counsel for the petitioner has taken several objections with respect to the Award, which have been summarised hereunder:
a. The Arbitral Tribunal while ignoring the aspect of arbitrary deductions in claim as well as an additional 20% interest on the same, allowed the interest on account of delay in payment of the claim.
b. The Arbitral Tribunal did not allow any interest towards the delay in issuing the Survey Report dated 28th July 2016 by M/s Sandeep Bharti Insurance Surveyor and Loss Assessors Pvt. Ltd. The surveyors took 13 months to release the Report from the date of the fire, thereby violating the IRDA guidelines for settlement of the claims.
c. In addition to disallowing Interest on account of delay in issuing the survey report by the surveyor, the Arbitral Tribunal allowed interest @ 9% per year only, despite the provision of payment of interest @ 2% over and above the Bank rate, in the IRDA guidelines.
d. The impugned Award has been passed on the basis of presumption and suspicion without appreciation of the facts and circumstances.
e. The impugned Award is in conflict with the public policy of the country. Moreover, the Award is also not reasoned.
5. On the last date of hearing, notice was issued to the respondent and today, the learned counsel for the respondent has appeared and vehemently opposed the instant petition on the ground of limitation. The respondent has also filed its written synopsis which records the objections to the delay in filing the petition.
6. The learned counsel appearing on behalf of the respondent at the very outset submitted that the petition has not been filed in accordance with Section 34(3) and 34(5) of the Arbitration Act and there is a significant delay in filing the instant petition challenging the impugned Award. It is submitted that the Award had been passed in the month of July 2019, whereas the petition has been filed in March 2021.
7. It is submitted that, despite the inordinate delay, the petitioner has failed to file any application seeking the condonation of such delay. The petitioner has not shown any cause or reason for the delay of over two years. Moreover, instead of seeking condonation of delay in filing the petition, the petitioner only filed an application for condonation of 154 days' delay in re-filing of the petition, when the same was marked under objections, on the grounds of inability during the second wave of Covid- 19 pandemic.
8. The learned counsel strongly urged that the petition is liable to be dismissed on the grounds of delay as well as for the reason of being devoid of merit.
9. Heard the learned counsel for the parties and perused the record.
10. The preliminary objection taken on behalf of the respondent to the petition is on the ground of limitation as stipulated under Section 34(3) of the Arbitration Act. Therefo
Adherence to time limits stipulated under the Arbitration Act and the requirement of due diligence in seeking condonation of delay.
The main legal point established in the judgment is the significance of adhering to the prescribed limitation period under the Arbitration Act and the requirement for parties to exercise their rights....
The Court emphasized the importance of due diligence and dispatch in exercising the right to challenge an Arbitral Award within the prescribed time, as per the provisions of the Arbitration Act.
The judgment establishes the strict interpretation and application of the limitation period under Section 34(3) of the Arbitration Act, emphasizing the requirement for sufficient cause and the mandat....
The law of limitation aims to prevent outdated, fictitious, or fraudulent claims and requires parties to exercise their rights within the prescribed time. The Court emphasized the need for due dilige....
The scope of interference in an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is limited and narrow. The Courts shall not sit in an appeal while adjudicating a challen....
Delay beyond 120 days (90+30) in Section 34 petitions or corresponding appeals under Section 37 of Arbitration Act not condonable via Limitation Act Section 5; negligence, inaction, lack of bonafides....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.