IN THE HIGH COURT OF DELHI AT NEW DELHI
Navin Chawla, J.
Delhi Metro Rail Corporation Ltd. – Appellant
Versus
M/s. Parasvnath Developers Ltd. – Respondent
CS(COMM) 463 of 2022 & I.A. 10691 of 2022
Decided On : 09-05-2023
Order VII Rule 11 - Suit Barred by Limitation - Code of Civil Procedure, 1908, Sections 73(3) and 74 of the Arbitration and Conciliation Act, 1996
Fact of the Case:
The plaintiff filed a suit claiming damages for latent defects in a construction project. The defendant sought rejection of the plaint citing the conciliated Settlement Deed and limitation.
Finding of the Court:
The court found that the Settlement Deed and limitation did not warrant rejection of the plaint at the current stage.
Issues: Validity of Settlement Deed, Limitation
Ratio Decidendi: The court held that the Settlement Deed and limitation were not sufficient grounds to reject the plaint at the current stage.
Final Decision: The application was dismissed, and the parties were directed to file a Joint Schedule of Documents.
JUDGMENT
I.A. 15283/2022
1. This application has been filed by the defendant under Order VII Rule 11 (a) and (d) of the Code of Civil Procedure, 1908 (hereinafter referred to as the `CPC') seeking rejection of the plaint, primarily on the submission that the Suit is barred by Limitation and in terms of Sections 73(3) and 74 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the `Act').
CASE OF THE PLAINTIFF IN THE PLAINT
2. To appreciate the challenge of the defendant, it would be essential to take note of the averments made in the plaint.
3. It is the case of the plaintiff that pursuant to a Notice Inviting Tender for construction of three (3) blocks of staff quarters i.e. Block A, B & C, with a combined capacity of 144 dwelling units, at Mundka Depot for Phase-II of Delhi MRTS Project (hereinafter referred to as the `Project'), the defendant was awarded the said work vide Letter of Acceptance dated 27.05.2009 for a total contract value of Rs.19,86,85,437.51. The project was taken over by the plaintiff from the defendant on 05.10.2012, 10.11.2012 and 03.12.2012 for Block A, B and C respectively. The flats constructed by the defendant were allotted and taken over by the employees of the plaintiff between March to May 2013, and around 140 families started residing in the Project. Immediately after occupation of the flats by the residents, a large amount of seepage problem was discovered in all the three (3) blocks. In the meantime, on 18.06.2014, the Completion Certificate was issued by the plaintiff stating the date of completion to be 15.02.2013, for a total value of Rs.25,02,70,420.07/-. The Defect Liability Period got over on 14.02.2014.
4. The plaintiff states that on 09.12.2014, the plaintiff informed the defendant about visible cracks on the structural members of the building towers being noticed within a period of two years from the date of completion of the building. The plaintiff finally appointed a Committee to investigate the reasons for the worsening condition of the residential blocks. The Committee vide its report dated 20.06.2015, revealed the deficiencies in the work, including the fact that the chloride content in the concrete was very high compared to the permissible limit. The Committee recommended that a complete and thorough assessment on retrofitting design be done with the help of a competent and expert Structural Consultant and remedial measures be taken.
5. On 20.06.2015, the plaintiff engaged M/s Sri Ram Institute for carrying out investigations by conducting various technical tests to ascertain the strength of the structure built by the defendant. M/s Sri Ram Institute, on 27.05.2015, submitted its report, which again pointed out various construction deficiencies in the Project. The plaintiff, thereafter, issued a legal notice dated 24.09.2015 to the defendant pointing out the structural defects noticed and demanded a sum of Rs.13,68,87,646/- from the defendant as damages.
6. The plaintiff, on 20.07.2015, also appointed M/s Epicon Consultants Pvt. Ltd. for carrying out the detailed structural assessment of the buildings and suggest further action. M/s Epicon Consultants Pvt. Ltd., in November, 2015, after examination and inspection of the Project inter-alia reported that the chloride content at various locations of reinforcement was more than 10 times the allowable limit for the same. The report also, while providing remedial measures, stated that the presence of excessive chloride is a permanent defect which is irreversible.
7. On 10.02.2016, a Conciliator was appointed for settlement of the disputes between the parties. By a Deed of Settlement dated 04.07.2016, the parties entered into a settlement whereby the defendant agreed to pay to the plaintiff an amount of Rs.4,11,75,690/- towards the repairs of the structure and the lease charges of the employees.
8. The plaintiff asserts that after entering into the above settlement, the plaintiff appointed M/s Cembond Construc
Shakti Bhog Food Industries Ltd. v Central Bank of India & Arn.
Sparham-Souter & Anr. v. Town and Country Development (Essex) Ltd. & Anr.
The court emphasized that while considering an application under Order VII Rule 11 of the CPC, only the averments made in the plaint and the documents produced along with the plaint are required to b....
Plaint cannot be rejected under Order VII Rule 11 CPC at threshold for limitation if pleadings disclose triable issues on mixed questions of law and fact regarding cause of action accrual and continu....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.