IN THE HIGH COURT OF DELHI AT NEW DELHI
Sachin Datta, J.
Pele Khezhie – Appellant
Versus
National Highways And Infrastructure Development Corporation Limited – Respondent
Arb.P. 840 of 2023
Decided On : 21-08-2023
Arbitration - Construction Contract - Arbitration and Conciliation Act 1996 - [ARBITRATION] - [CONSTRUCTION CONTRACT] - [Section 11, Section 26] - The court appointed an independent sole arbitrator to adjudicate the disputes between the parties. The court held that the conciliation process was not mandatory and the petitioner was justified in seeking arbitration due to the urgency in preserving its rights. The court also distinguished previous judgments to support its decision.
Fact of the Case:
The petitioner sought the appointment of an independent sole arbitrator to adjudicate the dispute arising from a construction contract. The respondent had declared the petitioner a non-performer, sought to levy liquidated damages, and issued a notice of intention to terminate the contract. The petitioner invoked the arbitration clause, but the respondent argued that the petition was premature as conciliation had not been exhausted and no disputes had arisen.
Finding of the Court:
The court found that the conciliation process was not mandatory and the petitioner was justified in seeking arbitration due to the urgency in preserving its rights. The court also held that serious disputes had arisen between the parties, justifying the appointment of an independent sole arbitrator.
Issues: The issues revolved around the mandatory nature of the conciliation process, the existence of serious disputes between the parties, and the urgency in seeking arbitration to preserve the petitioner's rights.
Ratio Decidendi: The court held that the conciliation process was not mandatory and the petitioner was justified in seeking arbitration due to the urgency in preserving its rights. The court also distinguished previous judgments to support its decision.
Final Decision: The court appointed an independent sole arbitrator to adjudicate the disputes between the parties and directed the pending application to be treated as an application under Section 17 of the Arbitration & Conciliation Act, 1996.
JUDGMENT
Sachin Datta, J. (Oral)
ARB.P 840/2023
1. The present petition under Section 11 of the Arbitration and Conciliation Act 1996 (the "A&C Act") seeks appointment of an independent sole arbitrator to adjudicate the dispute between the parties.
2. The disputes between the parties have arisen in the context of a tender process initiated by the respondent for "Construction of two lane with paved shoulder of Kohima-Bypass Road connecting NH-39 (New NH-02), NH-150 (New NH-02), NH-61 (New NH-29) and NH-39 (New NH-02) from Design Km 32.00 to design Km 43.454 [Design Length-11.454 Km] in the state of Nagaland under SARDP-NE on EPC Mode (Package IV)". The bid submitted by the petitioner for the said tender was accepted by the respondent vide Letter of Acceptance dated 14.08.2020. Accordingly, the petitioner and the respondent entered into the Engineering, Procurement and Construction Contract dated 05.09.2020.
3. The stipulated date for completion of the work was 18 months from the appointed date. For slow progress of work and non-completion of milestones by the petitioner, the respondent, vide letter 07.03.2023, declared the petitioner a Non-Performer. Further, vide letter dated 17.04.2023, the respondent sought to levy liquidated damages on the petitioner, and vide letter dated 22.05.2023 issued notice of intention to terminate the Contract. The petitioner contends that the sole reason the progress of work was slow and the milestones were not achieved, was the non-provision of the `Right of Way' by the respondent as per its contractual obligations.
4. A petition under Section 9 of the A&C Act has also been filed by the petitioner seeking stay of the respondent's letter dated 07.03.2023, restraining the respondent from taking any coercive or precipitative action on the basis of the letter dated 22.05.2023 and seeking status quo in relation to the Performance Bank Guarantees.
5. The Contract Agreement contains a dispute resolution clause in the following terms:
" \Article 26
Dispute Resolution
26.1 Dispute Resolution
(i) Any dispute, difference or controversy of whatever nature howsoever arising under or out of or in relation to this Agreement (including its interpretation) between the Parties, and so notified in writing by either Party to the other Party (the "Dispute") shall, in the first instance, be attempted to be resolved amicably in accordance with the conciliation procedure set forth in Clause 26.2.
(ii) The Parties agree to use their best efforts for resolving all Disputes arising under or in respect of this Agreement promptly, equitably and in good faith, and further agree to provide each other with reasonable access during normal business hours to all non-privileged records, information and data pertaining to any Dispute.
26.2 Conciliation
In the event of any Dispute between the Parties, either Party may call upon the Authority's Engineer, or such other person as the Parties may mutually agree upon (the "Conciliator") to mediate and assist the Parties in arriving at an amicable settlement thereof. Failing mediation by the Conciliator or without the intervention of the Conciliator, either Party may require such Dispute to be referred to the Chairman of the Authority and the Chairman of the Board of Directors of the Contractor for amicable settlement, and upon such reference, the said persons shall meet no later than 7 (seven) business days from the date of reference to discuss and attempt to amicably resolve the Dispute. If such meeting does not take place within the 30 (thirty) business day period or the Dispute is not amicably settled within 30 (thirty) days of the meeting or the Dispute is not resolved as evidenced by the signing of written terms of settlement within 30 (thirty) days of the notice in writing referred to in Clause 26.1.1 or such longer period as may be mutually agreed by the Parties, either Party may refer the Dispute to arbitration in accordance with the provisions of Clause 26.3 but before resorting to s
Demarara Distilleries Pvt. Ltd. v. Demerara Distilleries Ltd.
The conciliation process in the contract agreement was not mandatory, and non-compliance did not bar the petitioner from invoking arbitration.
The main legal point established in the judgment is that the appointment of an independent sole arbitrator is necessary, and the refusal of the petitioner to participate in conciliation proceedings d....
The main legal point established is that invoking the conciliation clause as per the contract and the respondent's failure to respond allows the petitioner to seek the appointment of an Arbitrator un....
The court affirmed that the inquiry under Section 11(6) of the Arbitration Act is restricted to the existence of an arbitration agreement, allowing disputes to proceed to arbitration without mandator....
The main legal point established in the judgment is that the petitioner's failure to exhaust the mandatory dispute resolution procedure as per the contract rendered the petition premature and non-mai....
The main legal point established is that the arbitration application was not premature, and a case was made for the appointment of an arbitrator to decide the disputes between the parties.
The main legal point established in the judgment is that a party can invoke arbitration in accordance with the arbitration agreement between the parties, and the voluntary nature of conciliation as a....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.