IN THE HIGH COURT OF DELHI AT NEW DELHI
Manoj Kumar Ohri, J.
Italian Thai Development - Appellant
Versus
National Thermal Power Corporation Ltd. - Respondent
O.M.P. (COMM) 343 of 2022
Decided On : 17-11-2023
Disputes arose between the parties regarding a contract for Main Civil Works Package-1. The Arbitral Tribunal awarded a sum to the petitioner, which was directed to be set off against the advance paid by the respondent. The petitioner challenged the set off and refund awarded by the Arbitral Tribunal. The court considered the power of courts to grant unconditional stay on the enforcement of arbitral award challenged under Section 34. The court found that the petitioner was not entitled to an unconditional stay against the enforcement of the arbitral award, as no case was made out for such a stay.
Fact of the Case:
Disputes arose between the parties regarding a contract for Main Civil Works Package-1. The Arbitral Tribunal awarded a sum to the petitioner, which was directed to be set off against the advance paid by the respondent.
Finding of the Court:
The court found that the petitioner was not entitled to an unconditional stay against the enforcement of the arbitral award.
Issues: The main issue was whether the petitioner was entitled to an unconditional stay against the enforcement of the arbitral award.
Ratio Decidendi: The court held that no case was made out for unconditional stay against the enforcement of the arbitral award.
Final Decision: The application for unconditional stay against the enforcement of arbitral award was dismissed.
JUDGMENT (Oral)
I.A. 18268/2023 (stay)
1. Petitioner, by way of present application filed under Section 36(3) of the Arbitration and Conciliation Act (hereafter, referred to as `A&C Act'), seeks unconditional stay of the arbitral award dated 16.03.2022 whereby it has been asked to refund a sum of Rs.1,69,43,54,488 to the respondent.
2. Facts relevant for consideration of the captioned application are that disputes arose between the parties in the context of work relating to contract for Main Civil Works Package-1: Dam, Spillway and Power Intake of Kol Dam Hydro Electric Project located in Bilaspur District. The disputes were referred to the Arbitral Tribunal resulting in passing of the impugned award.
3. The Petitioner raised a claim for Rs.3,66,34,27,582.45/- but was awarded only a sum of Rs.1,30,23,45,512/-. However, the said sum was directed to be set off against the sum of Rs.299.67 Crores paid to the petitioner by the respondent towards advance. Since the sum awarded to the petitioner is less than the advance in its possession, the Arbitral Tribunal directed refund of the excess advance of Rs.1,69,43,54,488/- by the petitioner to the respondent. The petitioner has challenged the said set off and refund awarded by the Arbitral Tribunal by filing objections under Section 34 alleging that the Arbitral Tribunal travelled outside the limits of reference in granting the refund when no specific relief of set off was claimed by the respondent from the Arbitral Tribunal in its statement of defense.
4. Petitioner has challenged the impugned award by way of the captioned petition which is pending consideration. Pending disposal of objections under Section 34, the petitioner is seeking unconditional stay of the impugned arbitral award and has contended that this court is empowered to pass such unconditional stay under Section 36(3) of the A&C Act.
5. Petitioner has referred to Malwa Strips Pvt. Ltd. v. Jyoti Ltd., (2009) 2 SCC 426; Polimer Media Pvt. Ltd. v. Ultra Media & Entertainment Pvt. Ltd., Arbitration Petition (L) No. 34542 of 2022; Damodar Valley Corporation v. Reliance Infrastructure Ltd., 2022 SCC OnLine Cal 553 and Future Market Networks Ltd. v. Laxmi Pat Surana and Ors., I.A. No. G.A. 1 of 2022 in A.P. 698 of 2016 to contend that even under Order XLI Rule 5 of CPC, which is the guiding provision referred to in Section 36(3) of the A&C Act, the courts are conferred with discretionary powers to grant unconditional stay of execution of the impugned decrees.
6. On the contrary, the respondent has cited Mahanagar Telephone Nigam Limited v. Canara Bank and Anr., 2023 SCC OnLine Del 1172; Power Mech Projects Ltd. v. Sepco Electric Power Construction Corporation, 2020 SCC OnLine Del 2049; Pam Developments Pvt. Ltd. v. State of West Bengal, (2019) 8 SCC 112 and National Highway Authority of India v. Transstroy (India) Ltd., 2022 SCC OnLine SC 832 to contend that power to grant unconditional stay of the decrees is confined to cases where the making of the Arbitral Award is induced by fraud and none else.
7. On merits, the respondent has refuted the contention of the petitioner that the Arbitral Tribunal strayed beyond the limits of its reference in awarding set-off and the consequential refund of the excess advance in favour of the respondent. Respondent has referred to an application dated 27.10.2015, filed by it whereby a specific relief of set-off and consequential refund of excess advance was sought from the AT. Respondent would contend that the Arbitral Tribunal has adjudicated the claim of set off, which it was empowered to do under Section 23(2A) of the A&C Act.
8. The question of power of courts to grant unconditional stay on the enforcement of arbitral award challenged under Section 34, is beyond debate given the rulings of various courts passed from time to time. The decision of Co-ordinate bench of this Court in Power Mech Projects (Supra) was assailed upto Supreme Court, where the Supreme Court vide judgment dated 19.09.2022 in
The court's decision emphasized that no case was made out for unconditional stay against the enforcement of the arbitral award.
Arbitration Award – Execution - By virtue of the provisions of Section 36, since it is a money decree and the Code of Civil Procedure in Order XLI Rule 1(3) mandates imposition of the terms and condi....
The power to grant unconditional stay of an arbitral award is not unfettered and is subject to conditions, including the condition of securing the award by deposit in Court.
The court emphasized the need for a prima facie case of fraud or corruption to grant an unconditional stay to an arbitral award for payment of money, and highlighted the importance of following the p....
The court emphasizes the need for real and sufficient security to cover the entirety of the arbitral award value when considering a stay of the award under Section 36 of the 1996 Act.
An arbitrator's reliance on an unproven valuation report constitutes a patent illegality, and parties must be afforded a fair opportunity to respond to claims and counterclaims in arbitration proceed....
An unconditional stay of an arbitral award is impermissible unless specific statutory conditions under Section 36(3) of the Arbitration Act are fulfilled.
Automatic suspension of execution of the award, the moment an application challenging the said award is filed under section 34 of Act leaving no discretion in court to put parties on terms, in court ....
Court emphasizes equity in execution of arbitral awards under challenge, mandating expedited resolution of related petitions while staying execution proceedings.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.