IN THE HIGH COURT OF DELHI AT NEW DELHI
Manmohan, Mini Pushkarna, JJ.
Indian Oil Corporation Limited - Appellant
Versus
Petroleum And Natural Gas Regulatory Board New Delhi & Ors. - Respondents
LPA 208 of 2024 & CM APPL. 14812 of 2024, CM APPL. 14813 of 2024, CM APPL. 14814 of 2024
Decided On : 22-03-2024
Pipeline - Authorization Dispute - Petroleum and Natural Gas Regulatory Board Act, 2006 - Section 16
Fact of the Case:
The appellant, Indian Oil Corporation Limited (IOCL), started laying a pipeline without authorization from the Petroleum and Natural Gas Regulatory Board (PNGRB), which had authorized another entity for the same route. The court restrained IOCL from further laying down the pipeline during the pendency of the writ petition.
Finding of the Court:
The court found that only the authorized entity had the right to lay, build, and operate the pipeline as per Section 16 of the PNGRB Act. It also noted that the conflicting claims and the legal right of IOCL to lay pipelines for its own use without PNGRB authorization were still to be considered and decided.
Issues: The main issue was the authorization dispute between IOCL and the entity authorized by PNGRB for laying the pipeline.
Ratio Decidendi: The court held that under Section 16 of the PNGRB Act, no entity can lay, build, or operate a pipeline without authorization by the Board. It also emphasized the need to consider the conflicting claims and the legal right of IOCL to lay pipelines for its own use without PNGRB authorization.
Final Decision: The appeal was dismissed, and the court upheld the stay restraining IOCL from continuing to lay the pipelines during the pendency of the writ petition. The court clarified that the decision did not express an opinion on the merits of the case.
JUDGMENT
Mini Pushkarna, J.
1. The present appeal challenges the judgment dated 08th February, 2024 passed by the learned Single Judge in W.P.(C) 15285/2023. Vide the said judgment, the learned Single Judge has granted a stay, thereby restraining the appellant herein from proceeding further with laying down of the pipeline from Ennore Port to Manali Industrial Area, Chennai, Tamil Nadu during the pendency of the writ petition.
2. Pursuant to a bidding process, respondent no.3-IMC Limited was authorized on 18th December, 2015 by respondent no.1, i.e., Petroleum and Natural Gas Regulatory Board ("PNGRB") to lay, build and operate the Ennore Port-Manali Industrial Area petroleum products pipeline.
3. The appellant, Indian Oil Corporation Limited ("IOCL") is a Public Sector Undertaking ("PSU"). The appellant had also participated in the aforesaid bid process of PNGRB, but was unsuccessful. However, subsequently the appellant-IOCL started laying a pipeline at Ennore Port, grass root terminal at Vallur (Chennai). The said pipeline is along the very same route on which the respondent no. 3-IMC Limited has been authorized to lay, build and operate the pipeline. The said work was started by the appellant on 22nd August, 2023 and as on date, the appellant is stated to have constructed 10 Kms of the pipeline, which as per the appellant is a captive pipeline for its self use.
4. Since the appellant-IOCL started constructing the pipeline along the very same route on which respondent no.3-IMC Limited had been authorized to lay, build and operate the pipeline, the respondent no.3 approached this Court by filing a writ petition, being W.P.(C) 15285/2023.
5. When the said petition was listed for hearing before the learned Single Judge, the learned Single Judge by judgment dated 08th February, 2024, allowed the application, being CM No. 7081/2024 filed on behalf of respondent no.3-IMC Limited, thereby restraining the appellant-IOCL from proceeding further with the laying down of the pipeline from Ennore Port to Manali Industrial Area, during the pendency of the writ petition. Against the said judgment dated 08th February, 2024 passed by the learned Single Judge, the present appeal has been filed.
6. Learned Senior Counsel appearing for the appellant has raised the following contentions:
6.1. The stay against the appellant has a cascading effect on its firm commitments and has effectively jeopardized the project of the appellant costing approximately Rs. 2,577 Crores (Rupees Two Thousand Five Hundred and Seventy Seven Crores).
6.2. The appellant, which is a PSU, has already spent about Rs. 996 Crores. Thus, irreparable harm/loss would be caused to the appellant if the impugned judgment is not stayed during the pendency of the present appeal. Every day the work stays stagnant, the loss is mounting for the appellant.
6.3. The laying of the pipeline undertaken by the appellant-IOCL, are for the exclusive use of IOCL and are being laid for transportation of its own petroleum products between its own facilities.
6.4. The pipelines are being laid as part of the captive system of IOCL and are neither dedicated pipelines, which cater to a single consumer nor are they common/contract carrier lines. Since the said pipelines do not fall within the ambit of the definition of common/contract carrier, provisions of Section 16(a) of the Petroleum and Natural Gas Regulatory Board Act, 2006 ("PNGRB Act"), do not apply.
6.5. No provision of the PNGRB Act or its congruent Regulations, require IOCL to take authorization for such pipelines. For captive/self use pipelines, meant only for the own use of IOCL, no authorization is required from the PNGRB. The captive/self use pipelines of the appellant are outside the purview of the PNGRB Act.
6.6. Respondent no.3-IMC Limited has not laid even a single inch of pipeline in more than eight years from the date of its authorization on 18th December, 2015. Therefore, respondent no.3-IMC Limited could not possibly suffer any irreparable l
AI
Unauthorized construction of pipelines for transportation of petroleum products without necessary authorization is contrary to the PNGRB Act and can lead to financial loss to the authorized entity.
The court upheld the legality of the gas pipeline acquisition, emphasizing public interest and proper procedural adherence by the competent authority.
The court emphasized the importance of following the prescribed procedures under the PNGRB Act and Regulations for the issuance of authorizations, and highlighted the appellate remedy available under....
A retired Tahsildar with a trained legal mind and experience in exercising quasi-judicial powers can be appointed as the competent authority under the Petroleum and Minerals Pipelines (Acquisition of....
Point of Law : To construct a Pipeline avoiding every residential area - whether there are constructed buildings thereon or otherwise - would be a sisyphean task, if not an impossible one
Petitioners' lack of standing under the Petroleum and Minerals Pipelines Act affirmed; emergency safety protocols acknowledged to protect public interest.
Permission for laying pipelines must cover the specific area in question, and evidence of permission is required to support claims of legality.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.