JUDGMENT
Sanjeev Sachdeva, J. (Oral)--The hearing was conducted through video conferencing.
2. Learned counsel for the petitioners submits that appeals of the petitioners are listed before the Tribunal on 16.02.2021.
3. Petitioners have filed the subject petition impugning the demolition order dated 28.12.2020.
4. Learned counsel for the petitioners submits that the Appellate Tribunal, MCD is still not operational.
5. Learned counsel appearing for respondent submits that the recommendations have already been sent to the concerned Ministry and the Tribunal is likely to become operational shortly.
6. By order dated 12.01.2021 it was directed that no demolition action shall be carried out consequent to the demolition order dated 28.12.2020 in respect of the properties of the petitioners.
7. Since the Appellate Tribunal, MCD is likely to commence functioning shortly, this petit
The court upheld the interim protection against a demolition order, ensuring the Appellate Tribunal considers appeals without bias from the High Court's order.
The court's decision was influenced by the operational status of the Appellate Tribunal, MCD and the need to ensure the continuation of interim protection for the petitioner.
A stay on a demolition order can be granted pending appeal, emphasizing the need for functioning appellate mechanisms in administrative law.
The court may grant interim protection against demolition orders pending appeals, with conditions on further construction activities to ensure adherence to existing regulations.
The court has the discretion to grant temporary protection from demolition while imposing restrictions and making the continuation of protection subject to the orders of the relevant appellate author....
A temporary stay on demolition cannot occur until the appellate tribunal is operational, allowing due process for appeals.
The court has the authority to restrain the respondent from proceeding with demolition proceedings for a limited period and can allow the petitioner to seek early hearing of the appeal and stay appli....
Court ensures procedural fairness by extending interim protection until the Appellate Tribunal MCD commences operations.
Court emphasized the necessity of protecting petitioners from demolition pending the outcome of their pending appeal to ensure due process.
The court has the discretion to grant interim protection during the pendency of an appeal, balancing the rights of the petitioner with the need to prevent unauthorized construction.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.