IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
Oyo Hotels and Homes Pvt. Ltd. - Appellant
Versus
Rajan Tewari - Respondent
Arb.P. 424 of 2020
Decided On : 09-02-2021
| Table of Content |
|---|
| 1. company-petitioner enters lease agreement. (Para 2 , 3 , 4 , 5 , 6 , 7) |
| 2. alleged breach of lease conditions. (Para 8 , 9 , 10 , 11 , 12) |
| 3. respondents' contested arguments on maintainability. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22) |
| 4. court's analysis of arbitrator's appointment validity. (Para 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30) |
| 5. court appoints new sole arbitrator. (Para 31 , 32 , 33) |
JUDGMENT
V. Kameswar Rao, J. This present petition has been filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (`Act', for short) with the following prayers:
"It is most respectfully prayed that this Hon'ble Court may be pleased to:
(i) appoint a Sole Arbitrator to adjudicate the claims of the Petitioner in accordance with the Arbitration and Conciliation Act, 1996 as amended;
(ii) declare that Hon'ble Justice Aruna Suresh (retired) has no jurisdiction to adjudicate the disputes between the parties;
(iii) Award costs of this Petition in favour of the Petitioner and against the Respondent;
(iv) Pass such other and further order(s) as this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case."
2. The petitioner herein is a company incorporated under the Companies Act, 2013 and having its registered office at Ground Floor-001, Mauryansh Elanza, Shyamai Cross Road, Nr. Parekh Hospital, Satellite Ahmedabad, Gujarat-380015 (formerly known as Alcott Town Planners Pvt. Ltd.).
3. The respondents herein are the joint owners of the premises/property situated at 3/16, Main Shankar Road, Old Rajinder Nagar, New Delhi (`Premises', for short).
4. It is the case of the petitioner and so contended by Mr. Jeevan Ballav Panda, learned counsel appearing for the petitioner that the petitioner and respondents entered into a Lease Deed dated May 27, 2019 (`Lease Deed', for short) in respect of the Premises.
5. Pursuant to the execution of the Lease Deed, petitioner started fulfilling the obligations contained thereunder on the assumption that the respondents will also do the same and even disbursed an amount of Rs.3,32,000/- to the respondents in order to expedite the refurbishment and upgradation of the Premises to make it at par with the petitioner's benchmark.
6. Thereafter it took over the Premises and started using the same for the purposes of its commercial activities as laid down in the Lease Deed. In the wake of the corona virus pandemic, the entire hospitality sector faced huge financial setback and on account of the same, the petitioner sought to invoke the force majeure clause in the Lease Deed vide email dated March 27, 2020.
7. He stated that after detailed discussion with the representatives of the petitioner, the respondents while agreeing to the invocation of the force majeure clause agreed to amend the commercial understanding between the parties in the interim.
8. Mr. Panda submitted that the respondents were in breach in terms of Clause 11.2.1 of the Lease Deed, which obligated the respondents to obtain as well as maintain all requisite building approvals required for running the Premises as a commercial establishment for the purposes as laid down in the Lease Deed. It is submitted by him that even after repeated communications and grant of time as sought by the respondents, the respondents failed to furnish the complete set of documents as mandated under Clause 11.2.1 of the Lease Deed.
9. That while attempts were being made to get the breach of Clause 11.2.1 cured, the respondents suddenly and to the complete shock and dismay of the petitioner, issued a letter date June 03, 2020 demanding a sum of money by misrepresenting the clauses of the Lease Deed.
10. Thereafter, the respondents, vide notice dated June 23, 2020, invoked arbitration clause citing the existence of disputes between the parties arising under the Lease Deed and nominated a learned Retd. Judge of this Court as the sole Arbitrator to adjudicate the disputes between the par
The main legal point established in the judgment is that the appointment of an arbitrator must be in accordance with the agreed procedure in the contract. If the appointment is not in line with the a....
Arbitration - Undisputedly both the parties had intended to refer the disputes to the arbitration and had accordingly agreed for the same. Hence, there being existence of arbitration agreement, and t....
Point of law: As per the legal position settled by the Supreme Court in catena of judgments, the High Court has the jurisdiction under Section 11(6) of the said Act to nullify the appointments made b....
Point of Law : S.13(2) provides that a party who intends to challenge appointment of an arbitrator shall, within fifteen days after becoming aware of the constitution of the arbitral tribunal or afte....
The court affirmed that the inquiry under Section 11(6) of the Arbitration Act is restricted to the existence of an arbitration agreement, allowing disputes to proceed to arbitration without mandator....
Adherence to the terms of the agreement and exhaustion of agreed procedures before seeking court intervention in arbitration disputes.
Where an Arbitrator had already been appointed and intimation thereof had been conveyed to the other party, a separate application for appointment of an Arbitrator is not maintainable. Once the power....
The main legal point established in the judgment is the limited scope of a legal drill under Section 11 of the Arbitration and Conciliation Act, 1996, and the expeditious disposal of petitions under ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.