SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
SPML Infra Limited - Appellant
Versus
Hitachi India (P.) Ltd. - Respondent
Arb. A. (COMM.) 75 of 2021 & IA Nos. 16156 of 2021 and 16157 of 2021
Decided On : 07-12-2021




Interim measures under the Arbitration and Conciliation Act allow arbitration tribunals to secure claims, especially under concerns of insolvency, as long as the actions align with just and convenient standards.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37(2)(b) and Section 17 - Interim measures ordered by arbitral tribunal - Appellant appealed against order of Arbitral Tribunal requiring submission of bank guarantee for securing claim - Court found that arbitration proceedings need protection given the financial status of appellant and confirmed outstanding amount is payable - Section 17(1) permits such interim measures as deemed just and convenient. (Paras 1, 2, 5, 11, 19)

(B) Arbitral proceedings - Parties' rights - The discretion exercised by an Arbitral Tribunal is not to be disturbed unless it is patently illegal - Scope of interference on merits is limited. (Paras 20, 22, 26) Facts of the Case: The appellant awarded a contract referred to as 'Sauni Yojna' and engaged the respondent as sub-contractor. Disputes arose due to unpaid invoices raised by the respondent, which the Arbitral Tribunal ruled to be due and ordered a bank guarantee.

Findings of Court:
The Court upheld the Arbitral Tribunal's decision, emphasizing the need for securing the respondent's claim amid the appellant’s alleged financial troubles.

Issues: Whether the Arbitral Tribunal's order for securing the respondent’s claims was justified and the merits of any alleged waiver by the respondent regarding their claims.

Ratio Decidendi: The Court noted that while the CPC provides guidance, the Arbitration Act governs the interim measures, allowing the arbitral tribunal to take necessary actions for preserving rights.

Result: Appeal dismissed.

Table of Content
1. background of arbitration and claims (Para 1 , 2 , 3 , 4 , 5 , 6)
2. challenges to securing claims and financial obligations (Para 7 , 9 , 10 , 11 , 26)
3. court's analysis of arbitral tribunal discretion (Para 8 , 12 , 15 , 17 , 19 , 22 , 23)
4. interpretation of interim measures and arbitral powers (Para 14 , 20 , 24)
5. dismissal of appeal with observations (Para 27)

JUDGMENT

Vibhu Bakhru, J. (Oral)--The appellant has filed the present appeal under Section 37 (2)(b) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning the order dated 16.11.2021 passed by the Arbitral Tribunal under Section 17 of the A&C Act. The respondent had filed an application, inter alia, praying that directions be issued to the respondent to secure the appellant to the extent of Rs.3,40,66,948/-. The Arbitral Tribunal has allowed the same in terms of the impugned order and had directed the appellant to furnish a Bank Guarantee in the sum of Rs.1,51,40,981/- for securing the respondent.

Factual Context

2. The appellant was awarded a contract by the Bhavnagar Irrigation Project Division, Government of Gujarat (BIPD). The said contract was referred to as "Sauni Yojna, Link 2, Package 3". The appellant, in turn, engaged the respondent as a sub-contractor to perform the following works under the EPC contract:

    "(i) design, engineering, supply, shifting, transportation, erection, commissioning and testing storage, loading and unloading of turnkey package with 30 days of trial run of electrical equipment pertaining to switchyard and substation in pumping station including cabling, earthing, lighting and other ancillary work (the "Electrical Work"); and

    (ii) design, engineering, supply, shifting, transportation, erection, commissioning and testing storage, loading and unloading of turnkey package including supply of mandatory spares with 30 days of trial run of PLC SCADA and instrumentation package (the "C&I Work")."

3. It is the respondent's case that it had diligently performed its part of the work, however, could not continue the same beyond a particular point as the appellant was not clearing the invoices raised by it in terms of their agreement.

4. It is also the respondent's claim that a meeting was held in the month of July, 2018 and the appellant had agreed that it would pay a sum of Rs.1,50,00,000/- to the respondent but the appellant failed to pay the entire amount. In addition, the respondent had also relied on the Minutes of the Meeting held between the representatives of the parties in the month of October, 2018. According to the respondent, the appellant had admitted that a sum of Rs.1,70,00,000/- was due and payable and had agreed to pay the same subject to confirmation.

5. There is no dispute that the appellant had raised invoices, which have remained unpaid. The Arbitral Tribunal examined the disputes and found that, prima facie, a sum of Rs.1,51,40,981/- was admittedly outstanding and payable by the appellant in respect of the unpaid invoices for the Electrical Work. In addition, the Arbitral Tribunal also examined the Minutes of the Meeting and found that the said outstanding amount was also confirmed by the appellant.

6. The respondent has serious apprehension that the entire exercise of proceeding against the appellant in arbitration would be rendered futile as the appellant is being pursued by several creditors as well and it may be put in liquidation. It is also alleged that the appellant had defaulted in making payments to other creditors, who have since sought recourse by filing petitions under Section 7 of the Insolvency & Bankruptcy Code, 2016.

7. In the aforesaid context, the appellant contended that the award that may ultimately be made in favour of the respondent would in fact be a paper award with little hope for the respondent to enforce the same.

8. Considering the rival contentions and after briefly surveying the disputes between the parties, the Arbitral Tribunal con

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top