IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Huawei Telecommunications (India) Co. Pvt. Ltd. - Appellant
Versus
Wipro Limited - Respondent
Arb.P. 365 of 2019
Decided On : 24-01-2022
JUDGMENT
1. Petitioners claim to be engaged in the business of designing, developing, manufacturing, marketing and/or sale of telecommunications related products worldwide. According to petitioners, Bharat Sanchar Nigam Limited (BSNL) invited bids for planning, supply, installation and commissioning of IMPCS 20/30 Combo Network (Phase V) vide tender No.: MM/CMTS/032006/000301 dated 22.03.2006 and B&CCS (Billing and Customer Care System including DR) and COTS Solution, which were part of overall IMPCS 20/30 network (Phase V) solution designed by petitioners, were to be delivered to the BSNL as per tender specifications and requirement. For this purpose, petitioners entered into Cooperation Agreement Nos. PACIND3009032002RUB & PACCHNHW09032002 RUA dated 20.03.2009 with the respondent.
2. During the course of hearing, learned counsel for the petitioners submitted that Clause 4.4 of the Agreement clearly stipulated that time is of the essence under the agreement and the respondent is obligated to follow the project time line and ensure that no delay is there in supply and implementation; Clause 4.5 of Agreement stipulated that the respondent was to provide (one) year Operation and Maintenance support; Clauses 4.6 and 10.3 of the Agreements read with Clause 1.2.1 stipulated that respondent was required to provide three years' 7X24 warranty services from the date of commissioning of the complete network in the service area. It was also submitted that respondent was responsible for bearing all the expenses for repair and replacement of the supplied solution and provide the same free of charge to the petitioners during the subsistence of the warranty period. It was also stipulated in both the Agreements that in case BSNL imposes any penalty on the petitioners due to delay in restoration/replacement/fixing of the fault with B&CCS and COTS solution, the respondent shall pay the complete penalty imposed and also if the respondent has to get the defects remedied from a third party, that shall be at complete risk and expense of the respondent.
3. Learned counsel for the petitioners further submitted that based on the aforesaid agreements and assurances, the petitioners issued four purchase orders to respondent for hardware implementation, integration of B&CCS and other components, integration of new element with billing system and performance tuning with expanded billing system, disaster recovery and business continuity system, application, software, drives, modem, printer, web based application with customizable OUI for data analysis and COTS package. According to petitioners, the aforesaid work was commissioned after a delay on 25.06.2012 and was valid till 24.06.2013 and the associated warranted for complete solution/products supplied was valid till 24.06.2015.
4. Learned counsel next submitted that during the subsistence of warranty period under the said agreements, BSNL raised several issues with regard to solution and products supplied by the respondent, however, respondent in direct breach of its contractual obligation did not rectify/resolve certain issues. Several e-mails and communications were made by the petitioners to the respondent during that one year requesting respondent to fix the issues and admittedly, in a few of the communications, respondent acknowledged the pending issues and assured the petitioners that all the issues will be resolved/rectified. In order to rectify the defects and due to inaction of respondent, petitioners engaged a Third-Party Vendor and in terms of the agreements, the third party vendor was wholly at the risk and cost of respondent and the same was informed to the respondent.
5. According to counsel for petitioners, thereafter meetings were held between petitioners and respondent on 26.10.2016; 06.12.2016; 15.11.2018 and 27.11.2018 wherein respondent always assured the petitioners that their team will check the claims of petitioners and revert, however, respondent failed to perform its c
Court determined claims are not time-barred and appointment of an arbitrator is valid despite the respondent's challenges regarding jurisdiction and limitations.
Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing arbitration.
An application under Section 11 for appointment of an arbitrator is time-barred if filed after three years from the refusal to appoint, with delays not justified.
Arbitration requests must be filed within three years of the cause of action; failure to act in time bars subsequent petitions.
The main legal point established in the judgment is that failure to follow the prescribed procedure and a claim being hopelessly barred by time can lead to the dismissal of a petition seeking the con....
The Chief Justice can appoint arbitrators under Section 11 of the Arbitration Act and determine issues of jurisdiction and validity of claims, while disputes over notification receipt are left for re....
The court upheld the right to appoint a Substitute Arbitrator due to the previous Arbitrator's mandate termination, ensuring the unresolved disputes could be adjudicated. This reflects the essential ....
The main legal principle established is that the Court should not reject an application for appointment of an arbitrator at the threshold unless the claim is manifestly, ex-facie and hopelessly time-....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.