IN THE HIGH COURT OF DELHI
Sanjeev Sachdeva, J.
Sandeep Kumar - Appellant
Versus
South Delhi Municipal Corporation - Respondent
W.P.(C) 8411 of 2021 & CM. Appl. 25989 of 2021 and W.P.(C) 10295 of 2021
Decided On : 27-01-2022
| Table of Content |
|---|
| 1. unauthorized construction concerns (Para 3 , 4 , 6 , 7 , 8) |
| 2. challenging legality of demolition orders (Para 9) |
| 3. orders regarding proceedings and protections (Para 10 , 11 , 12 , 13 , 14) |
| 4. disposal of petitions with reserved rights (Para 15) |
JUDGMENT
Sanjeev Sachdeva, J. The hearing was conducted through video conferencing.
2. Learned counsel for respondent/SDMC in W.P. (C) 10295/2021 has shared status report over the e-mail of the Court Master. The same is taken on record.
3. Petitioner in W.P. (C) 8411/2021 seeks a Mandamus to respondent No.1/South Delhi Municipal Corporation to demolish the alleged illegal unauthorized construction raised by respondent No.4 on the third floor of property number 6/33A, opposite Kargil Park, Jangpura B, New Delhi.
4. W.P. (C) 10295/2021 is a petition filed by respondent No.4 in W.P. (C) 8411/2021 seeking a Mandamus to be issued to respondent No.1/South Delhi Municipal Corporation to take action alleged illegal unauthorized construction raised on the first and second floor of the subject property by the petitioner in W.P. (C) 8411/2021.
5. Respective status reports have been filed by the Corporation in both the petitions.
6. In W.P. (C) 8411/2021, status report records that the ground, first and second floor of the subject property was found to be old constructed and residentially occupied. However, fresh unauthorized construction of a room having tin shed at third floor was found and action has been initiated and a demolition order qua the same has been passed on 27.08.2021.
7. The first status report filed on 27.09.2021 in W.P. (C) 10295/2021 states that the ground, first and second floor are old and occupied. However, as excess coverage/deviation was found at the ground, first and second floor, action has been initiated and show cause notice has been issued on 22.09.2021 to the owners/occupants of ground, first and second floor.
8. A second status report has been filed in W.P. (C) 10295/2021, stating that the deviations on the first and second floor were found to be protected under the National Capital Territory of Delhi Laws (Special Provisions) Second (Amendment) Act, 2020. However, a demolition order qua the ground floor of the subject property has been passed.
9. Learned counsel appearing for (Mr. Raman Rahani) petitioner in W.P. (C) 10295/2021, who is the owner/occupier of ground floor and third floor of the subject property, submits that the orders passed by the Corporation are illegal and motivated. He reserves the right to challenge the same in accordance with law.
10. Since the respondent/Corporation has filed status reports with respect to the respective properties and stated that they shall be taking action in accordance with law, these petitions are disposed of, directing the respondent/Corporation to take action in accordance with the status reports filed before the Court and in accordance with law.
11. It is, however, clarified that this would be without prejudice to the right of the owners/occupiers to defend proceedings in accordance with law by initiating appropriate proceedings before the Appellate Tribunal, MCD.
12. It is directed that in case any proceedings are initiated by the owners/occupiers, the same would be dealt with by the Appellate Tribunal, MCD without being influenced by anything stated in this order.
13. It is further directed that for a period of two weeks from today, no coercive action shall be taken so that the owners/occupiers can avail of the remedy of appeal.
14. It is clarified that the protection shall lapse on the expiry of the period of two weeks or listing of the appeals whichever is earlier and continuance of interim protection thereafter would be subject to orders to be passed by the Appellate Tribunal.
15. Petitions are accordingly disposed of in the above terms. All rights and contentions of the parties are reserved.
16. Copy of the order be uploaded on the High Court website and be also forwa
Municipal authorities must operate within legal frameworks when enforcing demolition orders, respecting property owners' rights to appeal.
The need for the Corporation to take action in accordance with law and the rights of owners/occupiers to defend proceedings before the appellate Tribunal, MCD.
The court emphasized that unauthorized construction enforcement must respect legal processes and pending appeals, leaving petitioner's standing open for further consideration.
In a contempt petition for non-compliance, where the authority demonstrates sufficient action taken to satisfy the court's previous order, the petitioner's grievances regarding the adequacy of such a....
The court's decision was based on the respondent's assurance of further action in accordance with the law and the pending appeal before the Appellate Tribunal, MCD.
The High Court holds that once demolition and sealing orders are passed by municipal authorities under the Delhi Municipal Corporation Act, the authorities are duty-bound to execute them within a spe....
The court upheld the MCD's authority to issue demolition notices for illegal constructions, emphasizing compliance with statutory procedures.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.