IN THE HIGH COURT OF DELHI
Sanjeev Narula, J.
Grand Reality Pvt. Ltd. - Appellant
Versus
Nanak Mehta - Respondent
O.M.P. (COMM) 92 of 2021
Decided On : 31-03-2022
| Table of Content |
|---|
| 1. dispute arises from a development agreement. (Para 1 , 2 , 3) |
| 2. parties’ arguments on breach and interest. (Para 4) |
| 3. court’s observations on breach and interest claimed. (Para 5 , 6 , 7 , 8) |
| 4. clarification on entitlement to interest. (Para 9) |
| 5. the petition is dismissed. (Para 10) |
JUDGMENT
Sanjeev Narula, J. (Oral)--The present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter, the `Act'] impugning the Award dated 19th March 2020 passed by a Sole Arbitrator appointed for adjudicating disputes arising out of an Agreement for Development dated 01st July, 2015 [hereinafter, `Agreement'] executed between the Respondent - M/s Grand Reality Pvt. Ltd. (Claimant in arbitration) and the Petitioner herein - Shri Nanak Mehta (Respondent in arbitration) for construction of Country Homes/Villas on agricultural land (admeasuring 15 Bighas and 4 Biswas) bearing Khasra Nos. 113/23/2 (5-12), 24 (4-16), 25/1 (2.08), 25/2 (2-08) situated in Village Bijwasan, Tehsil Vasant Vihar, New Delhi [hereinafter, "Demised Land"].
2. At the outset, it must be noted that vide Judgment dated 23rd December 2021 in O.M.P (COMM) 33/2021, a challenge to the impugned Award, at the instance of the Respondent herein, has been rejected.
3. The facts of the case have been recounted in the aforenoted judgment and the same shall be deemed to be part of the present order. For the sake of brevity, in a nutshell, the dispute between the parties was as follows:
3.1. A Development Agreement dated 01st July, 2015 was executed between the parties for development of Demised Land owned by the Respondent. In terms of the Agreement, a sum of Rs.2,04,85,000/- was paid to the Respondent (including payment of Rs.84,50,000/- paid directly to the Bank at the behest of the Petitioner). The Respondent failed to comply with the condition precedent of handing over the vacant physical possession of the property to the Petitioner after getting the title cleared, on or before 07th April, 2016.
3.2. The Respondent sent a legal notice allegedly terminating the Development Agreement. In any event, the Petitioner also terminated the Development Agreement in terms of Clause 8 of the Development Agreement vide legal notice dated 03rd April, 2018. In such circumstances, Petitioner contended that Respondent became liable to refund the amount received, along with interest @ 24 % p.a.
Proceedings under Section 9 of the Act:
3.3. Petitioner Company preferred a petition under Section 9 of the Act, 1 , to preserve the sub-stratum of the Development Agreement. The Court vide order dated 01st August, 2018, restrained the Respondent from creating any third-party interest or parting with the possession of the Demised Land, till the Respondent deposits a sum of Rs.2.05 crores with the Registry of this Court in the form of Fixed Deposit Receipt (FDR). The said sum was deposited by the Respondent, as recorded in order dated 06th September, 2018.
Award:
3.4. On 06th September, 2018, this Court appointed Mr. S.M Chopra, Retired Additional District Judge, as the Sole Arbitrator. The proceedings culminated in an Award on 19th March, 2020, holding the following:
(i) The Petitioner herein shall pay to the Respondent herein Rs.2,04,85,000/- from the proceeds of FDR No. 12452596 dated 14th August, 2018, deposited with ICICI Bank, Gurugram, with lien marked by Registrar General of the Court.
(ii) Petitioner shall pay to the Respondent interest to the extent of the difference between Rs.2,04,85,000/- and the principal amount of the FDR of Rs.2,05,00,000/- and the interest accrued on the said FDR till realization by the Respondent herein towards the satisfaction of the Award.
(iii) In view of the lien marked in favour of the Registrar General of this Court on the aforesaid FDR, the Respondent to take appropriate steps before this Court towards the satisfaction of the Award.
4. Mr. Akshay Makhija, Senior Counsel for the Petitioner, states that c
Arbitrators have discretion in awarding interest, and findings of breach by both parties can justify lower interest than contractually stipulated rates.
The main legal point established in the judgment is the court's interpretation and application of the arbitration and Conciliation act, 1996, particularly in relation to the impugning of the award an....
The court upheld the arbitral award, ruling that grounds for intervention under Section 34 of the Arbitration Act were not met, affirming the tribunal's discretion and findings based on evidence subm....
The court upheld the trial court's dismissal of the appeal against the arbitration award, confirming that there was no patent illegality or grounds for interference under the Arbitration and Concilia....
Arbitrator cannot award interest where contract expressly bars it, even as compensation; limited judicial interference under Sections 34/37.
The court emphasized the importance of arbitration in resolving disputes arising from the agreement between the parties.
The court affirmed that arbitral awards can only be set aside under Section 34 if grounds of patent illegality are established, emphasizing the sanctity and finality of arbitration decisions.
When parties agree on an amount of damages in case of breach of contract, the claimant is not required to prove the damages in a general sense, as the agreement itself serves as evidence of the quant....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.