IN THE HIGH COURT OF DELHI
Chandra Dhari Singh, J.
United Drilling Tools Ltd. - Appellant
Versus
Oil and Natural Gas Corporation Ltd. - Respondent
O.M.P. (COMM) 574 of 2020
Decided On : 12-12-2022
| Table of Content |
|---|
| 1. factual background of arbitration case. (Para 5 , 14) |
| 2. petitioner's claims for interest are presented. (Para 8 , 9 , 10) |
| 3. respondent's defenses against petitioner's claims. (Para 11 , 12) |
| 4. court's reasoning against interference with the award. (Para 19 , 20 , 21) |
| 5. conclusion of the court's decision. (Para 22 , 23) |
ORDER
Chandra Dhari Singh, J. (Oral)
I.A. 9233/2021 (Delay)
1. This is an application under Section 5 of Limitation Act, 1963 on behalf of the petitioner for condonation of delay in filing the rejoinder to the reply of the respondent.
2. For the reason stated in the application, the delay of 80 days in filing the rejoinder to the reply of the respondent.
3. The application is disposed of.
O.M.P. (COMM) 574/2020
4. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "The Act, 1996") has been filed on behalf of the petitioner seeking the following relief:
"(a). Allow the present Petition and set aside the Award dated 10.08.2020 only in respect of Claim no. 2..."
5. The brief facts of the case are that the Petitioner is a company registered under the Companies Act, 1956, having its office at A-22, Phase-II, District Gautam Budh Nagar, Noida-201305, U.P. and the Respondent is a public sector undertaking having its registered office at Deen Dayal Urja Bhawan, 5, Nelson Mandela Marg, Vasant Kunj, New Delhi-110070. The Respondent floated a tender bearing no. ZNJMC10004 for procurement of Truck mounted heavy-duty dual skid Hydraulic Single Drum Wireline Winch Units. Accordingly, the Petitioner submitted its Bid No. UDT/MKTG/EBID/2010-11/514 dated 31st January, 2011 for supply of 17 Nos. Wireline Winch Units. The bid of the Petitioner was accepted by the Respondent and the Respondent issued NOA dated 28th September, 2011 to the Petitioner and, thereafter, the Respondent issued Purchase Order dated 24th February, 2012 in favour of the Petitioner. Thereafter, the Petitioner supplied 17 nos. of wireline winch units well within time. But, the Respondent illegally, unlawfully, mala fidely and unconstitutionally deducted USD 1,46,400 from the Petitioner's account towards alleged Liquidated Damages, arising disputes and differences between the parties. Accordingly, the Respondent vide letter dated 17th January, 2019 appointed Shri P. K. Jain as sole Arbitrator for adjudication of disputes and differences between the parties.
6. The learned Arbitrator passed the Award dated 10th August, 2020 whereby the claim no. 1 of the Petitioner pertaining to refund of Liquidated damages amounting to USD 1,46,400 was allowed but the claim no. 2 which pertained to award of interest on withheld sum was declined.
7. Being aggrieved by the part of award (claim no. 2), the Petitioner has filed the present objection Petition.
8. Learned counsel appearing on behalf of the Petitioner submitted that as per law if a person is deprived of the money which he is legitimately entitled to, the said person is liable to be compensated in form of interest or damages. Since the learned Arbitrator came to the conclusion that withholding of USD 1,46,400 by the Respondent is illegal and had wrongly imposed Liquidated Damages on the Petitioner, the Petitioner ought to have been granted the interest on the said amount which had been illegally withheld by the Respondent. It is further submitted that the circular dated 17th August, 2020 issued by the Respondent clearly entitles the Petitioner to get interest, being a small-scale industry.
9. It is submitted by learned counsel appearing on behalf of the Petitioner that the Respondent never filed any counter claim against the Petitioner nor could justify the withholding of USD 1,46,400 for nine years. Therefore, the Petitioner is very much entitled to interest on withheld amount. It is further submitted that the learned Arbitrator is empowered to grant Pendente-lite and future interest on the sum awarded in the Award. It is a
The court confirmed that arbitral awards can only be set aside under specific grounds outlined in the Arbitration and Conciliation Act, affirming the validity of the arbitrator's decision regarding l....
The main legal point established in the judgment is the narrow scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and the emphasis on reasonableness, natural justice, and....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
The Court's decision highlights the limited scope of judicial review of arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996. The Court held that it lacked the authority to ....
Limited grounds for setting aside an arbitral award under Section 34 of the Arbitration Act and the Court's reluctance to re-adjudicate disputes on their merits.
The main legal point established in the judgment is the significance of adhering to the prescribed limitation period under the Arbitration Act and the requirement for parties to exercise their rights....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.