IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
The Oriental Insurance Co. Ltd. - Petitioner
Versus
HCL Infosystems Limited - Respondent
O.M.P. (COMM) 436 of 2022 & I.A. 17574 of 2022
Decided On : 01-03-2023
The Court held that the Arbitral Tribunal's decision to award interest at 18% per annum was reasonable and well-reasoned, and did not suffer from any patent illegality or contravene public policy. The Court also held that it lacked the authority to modify the arbitral award, as such power is not granted under Section 34 of the Arbitration and Conciliation Act, 1996.
Fact of the Case:
The petitioner, a public sector general insurance company, entered into a contract with the respondent, a company providing IT solutions, for the procurement, implementation, customization, deployment, maintenance, training, and support of an Enterprise Content Management (ECM) solution. A dispute arose between the parties regarding the deduction of liquidated damages by the petitioner for alleged delays in the completion of certain milestones. The respondent invoked arbitration, and the Arbitral Tribunal awarded the respondent a sum of Rs. 2,24,18,595/- along with 18% interest per annum from the date of deduction of liquidated damages till the filing of the claim, as well as 8% interest on the awarded sum as pendente lite and post-award future interest.
Finding of the Court:
The Court found that the Arbitral Tribunal had adequately reasoned its decision to award interest at 18% per annum, considering the facts and circumstances of the case, including the admission by the respondent that there were delays in the completion of certain milestones. The Court also held that the rate of interest awarded was not contrary to any provision of the contract between the parties.
Issues: 1. Whether the Arbitral Tribunal's decision to award interest at 18% per annum was reasonable and well-reasoned, or whether it suffered from any patent illegality or contravened public policy. 2. Whether the Court had the authority to modify the arbitral award.
Ratio Decidendi: 1. The Court held that the Arbitral Tribunal's decision to award interest at 18% per annum was reasonable and well-reasoned, as it was based on a consideration of the facts and circumstances of the case, including the admission by the respondent that there were delays in the completion of certain milestones. The Court also found that the rate of interest awarded was not contrary to any provision of the contract between the parties. 2. The Court held that it lacked the authority to modify the arbitral award, as such power is not granted under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision: The Court dismissed the petition filed by the petitioner, upholding the Arbitral Tribunal's award.
JUDGMENT :
CHANDRA DHARI SINGH, J.
1. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter “The Act, 1996”) has been filed on behalf of the petitioner seeking the following reliefs: -
FACTUAL MATRIX
2. The petitioner is a public sector, general insurance company of India, having its head quarters at A-25/27, Asaf Ali Road, New Delhi-110002 (hereinafter referred to as “Insurance Company”). The Respondent is a company incorporated under the laws of India, and is involved in the business of providing Information Technology (“IT”) solutions, hardware, software, as well as ancillary solutions across the country, having its registered office at 806 Siddharth, 96, Nehru Place, New Delhi-110019 (hereinafter referred to as “HCL”).
3. The petitioner floated a 'Request for Proposal' (hereinafter referred as "RFP") on 5th August, 2016 for the procurement, implementation, customization, deployment, maintenance, training and support qua an Enterprise Content Management (EMC) solution. The Respondent was declared a successful bidder and the Notification of Award (“NOA”) dated 10th February, 2017 for a total project value of Rs. 15,98,57,533/- was issued to the Respondent. The project value included Annual Maintenance (“AMC”) for a period of five years after the implementation of the work. Consequently, an agreement dated 23rd February, 2017 was executed between the parties.
4. The Clause 7.13 of the RFP provides for Liquidated Damages in case the Respondent fails to meet the Milestone No. 3 specified in Clause 3.8 of RFP. As per the Clause 3.8, the Respondent was obliged to ensure (i) Delivery of Application, Database Licenses; and (ii) Delivery, Installation and Acceptance of DC-DR Hardware and Scanners at respective locations within twelve weeks from the date of issuance of the Purchase Order, which was originally by 5th May, 2017. Clause 10.8 of the RFP provides the list of offices of the petitioner where the deliveries under the aforesaid Clause 3.8 were to be made and the work was to be completed.
5. Some portion of work was not completed within the stipulated period. The petitioner, while holding that the Respondent was solely responsible for the entire delay, imposed penalty and deducted Liquidated Damages at the rate of 10% of the entire project value i.e. Rs. 1,59,85,753/-. The Respondent objected to the said deduction of Liquidated Damages. According to the Respondent, any imposition of Liquidated Damages by the Respondent was not only against the terms of the contract but also, against the law. Both the parties tried to settle the dispute amicably, however, they could not arrive at an amicable settlement and the matter remains unresolved.
6. The Respondent has given the notice under Section 21 of the Act, 1996 on 4th June, 2020 to the petitioner for invocation of the arbitration clause and for appointment of an Arbitrator to adjudicate the arbitral disputes between the parties. In reply to the said notice, the petitioner justified the deduction of Liquidated Damages on the ground that the same was made in terms of the RFP. It is also contended in the said reply that since the Respondent exceeded more than twenty weeks to complete the Milestone 3, therefore, Liquidated Damages upto maximum deduction of 10% were levied. Thereafter, the dispute was referred to the Arbitration Tribunal.
7. On 6th January, 2021, the Respondent filed its Statement of Claim (“SOC”) before the learned Arbitral Tribunal. On 5th February, 2021, the Petitioner fi
Arosan Enterprises Ltd. v. Union of India
Central Inland Water Transport Corporation Ltd. vs. Brojo Nath Ganguly
Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.
Hyder Consulting (UK) Ltd. vs. Governor
Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd.
McDermott International Inc. v. Burn Standard Co. Ltd.
Northern Railway v. Sarvesh Chopra
The Court's decision highlights the limited scope of judicial review of arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996. The Court held that it lacked the authority to ....
The main legal point established in the judgment is the narrow scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and the emphasis on reasonableness, natural justice, and....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
An arbitrator must adhere to the contractual terms regarding interest, and if parties explicitly waive interest claims, such claim cannot be awarded under Section 34 of the Arbitration and Conciliati....
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.