IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
DLF Ltd. - Appellant
Versus
IL&FS Engineering and Construction Company - Respondent
Arb.P. 1166 of 2021
Decided On : 21-12-2022
| Table of Content |
|---|
| 1. factual background related to project delays and disputes. (Para 1 , 2 , 3 , 4) |
| 2. details on disputes and legal notices related to claims. (Para 5 , 6 , 8 , 9) |
| 3. petitioner's arguments regarding arbitration and claims. (Para 10 , 11 , 12 , 13 , 14) |
| 4. discussion on legal implications of claims before and post moratorium. (Para 18 , 19 , 21) |
| 5. court's refusal to dismiss case and maintained order regarding claims. (Para 54 , 55 , 64) |
| 6. final ruling on the petition dismissal. (Para 73 , 74) |
JUDGMENT
V. Kameswar Rao, J.
1. The present petition has been filed under Section 11 of the Arbitration and Conciliation Act, 1996 ("Act of 1996", hereinafter) seeking appointment of a sole arbitrator for the resolution of disputes between the parties under a Contract dated June 21, 2012.
2. At the outset, I may briefly narrate the facts which have lead to the filing of the present petition. The petitioner entered into a cost sharing agreement with Haryana Urban Development Authority ("HUDA", hereinafter), for external development works for improvement of certain road networks in Gurgaon, Haryana. The respondent presented itself as a prominent infrastructure development company to the petitioner and based on its representation, the petitioner awarded development works to be carried out in the project to the respondent.
3. Subsequently, the petitioner entered into a separate contract agreement dated June 21, 2012 ("contract", hereinafter) with the respondent. The term of the contract period was for 24 months and total price of the contract was Rs.394,30,00,000/-. However, the said project was not completed because of various defaults on the part of the respondent, and the project timelines were extended till June 30, 2017. A major portion of the works were de-scoped, vide agreement dated May 11, 2018 as the respondent was unable to complete the work on time and further did not carry out the maintenance works; which in terms of the contract, the respondent was liable to do for five years. The maintenance work of the project is still ongoing and is being carried out through some other agencies at the risk and cost of the petitioner. Due to the delay caused by the respondent, and the subsequent de-scoping, the petitioner incurred additional expenses. The respondent also failed to adhere by the quality and safety norms set out in the agreement and the petitioner even imposed a fine on the respondent for its failure to adopt the safety measures in terms of the contract.
4. In November 2018, disputes arose between the petitioner and the respondent in relation to certain works to be completed/rectified by the respondent with respect to the construction of a culvert near AIT Chowk and Belmonte of HUDA sector road. There were several issues raised by the petitioner regarding the safety of the said culvert highlighting that it had become an accident prone area. Several correspondences were exchanged between the petitioner and the respondent wherein the petitioner time and again called upon the respondent to cure the defects in the area but the respondent has repeatedly failed to comply with the requests made by the petitioner.
5. Meanwhile, the Union of India filed a petition under Sections 241 and 242 of the Companies Act, 2013 before the National Company Law Tribunal ("NCLT"), Mumbai, inter alia praying for stay of institution of suits and arbitral proceedings against Infrastructure Leasing and Financial Services Limited ("IL&FS"), i.e., the parent company of the respondent, and its 348 Group Companies. However, the NCLT, Mumbai declined the said relief. Thereafter, the Union of India filed an appeal before the National Company Law Appellate Tribunal ("NCLAT") challenging the order passed by the NCLT, Mumbai. The NCLAT on October 15, 2018 passed an interim order staying the institution of suits and other proceedings against IL&FS and its 348 Group Companies.
6. Subsequently, the respondent issued a demand notice dated Jul
The initiation of arbitration is impermissible due to an existing moratorium that restrains all legal proceedings, including arbitration, until the related insolvency matters are resolved.
The Court by default would refer the matter when contentions relating to non-arbitrability are plainly arguable.
Point of law: The Court by default would refer the matter when contentions relating to non-arbitrability are plainly arguable.
Disputes concerning alleged payments are referable to arbitration despite claims of prior resolution efforts, where the existence of disputes was upheld.
The mere filing of the proceedings under Section 7 of the IBC did not preclude the Court from exercising its jurisdiction under Section 11 of the aCa, as the proceedings under Section 7 of the IBC we....
IBC is a time bound process – Plea of not being aware of newspaper pronouncements is not one which should be available to a commercial party.
Once a resolution plan is approved under the IBC, all claims not part of the plan are extinguished, and the tribunal lacks jurisdiction to adjudicate on such claims.
Judicial immunity under the Judges (Protection) Act, 1985 is upheld, but the court emphasizes the need for accountability and the exhaustion of alternative remedies before seeking writ relief.
The court held that the validity of claims and the arbitrability of related disputes must be referred to arbitration, rejecting the respondent's claims of non-compliance with contractual protocols li....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.