UTTAR PRADESH STATE CONSUMER DISPUTES
REDRESSAL COMMISSION, LUCKNOW
Hon’ble Mr. Justice K.C. Bhargava, President & Mr. D.D. Bahuguna, Member
GHAZIABAD DEVELOPMENT AUTHORITY—Appellant
versus
V.D. DIMIRI—Respondent
Appeal No. 113/SC of 1998—Decided on 16.9.1999
Counsel for the Parties :
For the Appellant :Mr. Arvind Kumar, Advocate.
For the Respondent:Mr. M.H. Khan, Advocate.
The housing authority is liable to pay interest on the deposited amount at the rate of 18% per annum for the delay in delivery of possession of the house due to its fault.
Headnote:
CONSUMER PROTECTION - HOUSING - ALLOTMENT OF HOUSE - DELAY IN DELIVERY OF POSSESSION - INTEREST ON DEPOSITED AMOUNT - RATE OF INTEREST - INTERPRETATION OF BROCHURE - FAULT OF HOUSING AUTHORITY - LIABILITY TO PAY INTEREST.
Fact of the Case:
The complainant applied for allotment of a house under MIG scheme in Indrapuram on instant payment basis. He deposited the registration amount and the rest of the amount. However, the possession of the house was not delivered. The complainant filed a complaint before the District Forum seeking interest, rebate, and compensation.
Finding of the Court:
The District Forum awarded interest at the rate of 18% per annum from the date of deposit till the date of possession, rebate of Rs. 3,600/-, and Rs. 3,000/- as cost. The possession was to be delivered within two months, failing which interest would be payable at the rate of 21% per annum.
Issues: 1. Whether the interest awarded at the rate of 18% per annum was excessive. 2. Whether the delay in delivery of possession was due to the fault of the housing authority.
Ratio Decidendi: 1. The National Commission had previously held that interest at the rate of 18% per annum could be awarded as compensation for the loss suffered by allottees due to negligence and deficiency in service on the part of the housing authority. 2. The housing authority failed to construct the houses according to the brochure and hand over the possession of the house to the allottees. The complainant was not at fault for the delay in delivery of possession.
Final Decision: The appeal filed by the housing authority was dismissed. The housing authority was directed to pay Rs. 1,000/- as cost to the complainant and deduct the amount of Rs. 98,940/- already paid as interest from the entire amount due against it. The compliance was to be made within two months from the date of the judgment.
Mr. Justice K.C. Bhargava, President— This is an appeal against judgment and order dated 16.12.1998 passed by District Forum, Ghaziabad in the complaint case No. 299/1997.
2. The facts of the case stated in brief are that the complainant applied for allotment of a house under MIG scheme in Indrapuram on instant payment basis. He was told that the approximate price of the house would be Rs. 3,60,000/- out of which he deposited a sum of Rs. 36,000/- as registration amount on 20.6.1996. The rest amount of Rs. 3,24,000/- was deposited on 9.8.1996, but even then the possession of the house has not been delivered as yet. It was prayed by the complainant that till the date of possession he should be awarded interest. He should also be paid rebate of Rs. 3,600/-. He has also claimed a sum Rs. 2,00,000/- as compensation.
3. The opposite party in his written version has admitted the deposit of the amount for taking the house. The learned District Forum, after considering the facts of the case, came to the conclusion that the possession letter has not been issued by the Ghaziabad Development Authority and the complainant is entitled to get interest from 1.9.1996 till the date of possession. The interest awarded was 18% per annum. He was also allowed rebate of Rs. 3,600/-. Further a sum of Rs. 3,000/- was allowed as cost. The possession was to be delivered within a period of two months. It was further mentioned that if the order is not complied with within the time allowed, then interest shall be payable at the rate of 21% per annum.
4. Aggrieved against this order, Ghaziabad Development Authority has come in appeal and has challenged the correctness of the order passed by the learned District Forum.
5. We have heard the learned Counsels for the parties. Learned Counsel for the opposite party has argued that the interest at the rate of 18% could not have been awarded as it is very much on the higher side. In the case of George Thomas & Ors. v. Ghaziabad Development Authority, I (1999) CPJ 18 (NC), it was held by the National Commission as under :
"The Authority had utilised the amount of the complainants all these years whereas the complainants had been wrongly deprived of the use of the amount which was deposited by them with the Authority. If the complainants have to find out a similar premises, they have to pay a very high price, the complainants have to be compensated for the loss suffered by them on account of negligence and deficiency in service on the part of the Authority. The negligence on the part of the Authority is very apparent inasmuch as after collecting the required consideration, it neglected the construction of the flats.
In our opinion it will meet the ends of justice if the complainants are awarded interest at the rate of 18% per annum by way of compensation on the amount which the Authority is required to refund."
6. Thus in view of the above observations of the National Commission the interest which has been awarded at the rate of 18% cannot be said to be excessive.
7. It is further argued by the learned Counsel for the opposite party that the possession could not be delivered on account of the fact that the house in the block was actually not constructed by the appellant and all those allottees were given an opportunity to take flats in another block as per the terms of the brochure. It is further argued that the appellants had informed the Court about the current status of the house and intimated that the possession of the houses may be given in one year, i.e. in September, 1999. Thus the facts on record goes to show that the houses which were intended to be allotted to the complainant were under the construction and instead of that the complainant was offered another house in another block which resulted in delay in delivery of the possession of the house. The complainant cannot be blamed for non- allotment of the house because he was not at fault. The fault lies with Ghaziabad Development Authority who failed to co