Supreme Court of India
S.N. Variava & Arijit Pasayat, JJ.
HARYANA URBAN DEVELOPMENT AUTHORITY—Appellant
versus
REKHA SHARMA—Respondent
Civil Appeal No. 3410 of 2003 from Judgment and Order dated 19.7.2002 of National Consumer Disputes Redressal Commission, New Delhi in R.P. No. 1097 of 2002—Decided on 10.8.2004
For the Appellant :Mr. Satinder Singh Gulati, Mrs. Kamaldeep Gulati and Dr. Kailash Chand, Advocates.
For the Respondent:Mr. M.P. Shorawala, Advocate (N.P.).
Headnote:Consumer Protection Act, 1986 - Sections 14 and 23-Housing-Delay in offering possession-Award of interest-Respondent was allotted a plot in Gurgaon in January 1986-All dues paid-Possession not offered-Consumer complaint-District Forum directed the Development Authority to deliver alternate plot at the same price and to pay interest @ 10% after two years from the date of deposit-Appellant have paid interest only in July, 2004-They have delivered possession of an alternate plot in 2003-District Forum has not awarded compensation for mental agony and harassment-Whether National Commission was justified in increasing the rate of interest of 18% p.a.-(No)-Appellants directed to execute sale deed and to give permission to construct.
In spite of there being no stay, to payment of interest beyond 12% and in spite of clarification given by this Courts order in Ghaziabad Development Authority v. Balbir Singh, (reported in (2004) 5 SCC 65), the amounts were only paid on 28th July, 2004. We feel that for the lapse Appellants must pay interest at the rate of 15% from 17th March, 2004 till 28th July, 2004. Appellants shall also pay costs fixed at Rs. 500/- to the Legal Aid Society of the Supreme Court. The Appellants must recover the amount paid towards costs personally from the officer/s, who were responsible for not paying even after clarification by this Court. A complaint is made that the Appellants are not executing the sale deed and are not giving permission to construct. We, therefore, direct the Appellants to execute the sale deed and to give permission to construct without claiming any amounts whatsoever, except the registration charges, from the Respondent. The same is to be done within one month from today.
S.N. Variava, J.—Before this Court a large number of appeals have been filed by the Haryana Urban Development Authority and/or the Ghaziabad Development Authority challenging Orders of the National Consumer Disputes Redressal Commission, granting to complainants, interest at the rate of 18% per annum irrespective of the fact of each case. This Court has, in the case of Ghaziabad Development Authority v. Balbir Singh reported in II (2004) CPJ 12 (SC)=(2004) 5 SCC 65, deprecated this practice. This Court has held that interest at the rate of 18% cannot be granted in all cases irrespective of the facts of the case. This Court has held that the Consumer Forums could grant damages/compensation for mental agony/harassment where it finds misfeasance in public office. This Court has held that such compensation is a recompense for the loss or injury and it necessarily has to be based on a finding of loss or injury and must co-relate with the amount of loss or injury. This Court has held that the Forum or the Commission thus had to determine that there was deficiency in service and/or misfeasance in public office and that it has resulted in loss or injury. This Court has also laid down certain other guidelines which the Forum or the Commission has to follow in future cases.
2. This Court is now taking up the cases before it for disposal as per principles set out in earlier judgment. On taking the cases we find that the copies of the claim/petitions made by the respondent/complainant and the evidence, if any, led before the District Forum are not in the paper book. This Court has before it the order of the District Forum. The facts are thus taken from that order.
3. In this case the respondent was allotted a plot bearing No. 211, Sector 12A, Gurgaon vide memo dated 23rd January, 1986. The respondent paid all dues but was not offered possession.
4. On these facts, the District Forum directed to deliver an alternate plot at the same price and to pay interest @ 10%, as per HUDA policy, after two years from the date of deposit till the date of delivery of physical possession of alternate plot.
5. The State Forum upheld the order of the District Forum and dismissed the Appeal. The respondent did not go in Revision before the National Commission. The Appellants went in Revision before the National Commission. The National Commission has increased the rate of interest to 18% p.a.
6. For reasons set out in the Judgment in the case of Ghaziabad Development Authority v. Balbir Singh (supra), the order of the National Commission cannot be sustained and is hereby set aside. As stated above, the relevant papers regarding the claim made, the affidavits filed, the evidence submitted before the District Forum are not produced before this Court. In this case, the appellant have paid interest @ 12% only on 28th July, 2004. They have delivered possession of an alternate plot bearing No. 1269, Sector 45, Gurgaon in 2003. The District Forum has not awarded compensation for mental agony and harassment. Where possession is given at old rate, the party has got benefit of escalation in price of land. Thus, normally there should not also be award of interest on the money deposited. However, as the allotment was in 1986 and possession given only in 2003 the respondent has suffered mental agony and harassment and the costs of construction has gone up, the respondent should have been compensated for these. We thus take it that the interest awarded and paid is towards compensation on these counts.
7. In spite of there being no stay, to payment of interest beyond 12% and in spite of clarification given by this Court’s order (reported in (2004) 5 SCC 65), the amounts were only paid on 28th July, 2004. We feel that for the lapse appellants must pay interest at the rate of 15% from 17th March, 2004 till 28th July, 2004. Appellants shall also pay costs fixed at Rs. 500/- to the Legal Aid Society of the Supreme Court. The appellants must recover the amount paid towards c