NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
J.M. Malik, P.M, S.M. Kantikar, Member
NATIONAL FLASK INDUSTRIES LTD. - Appellant
Vs.
GUJARAT ELECTRICITY BOARD AND OTHERS - Respondent
Consumer Case No. 71 of 2001.
Decided On : 16-04-2015

Advocates Appeared:
For the Appellant :Subodh Gokhale, Advocate
For the Respondent:Prasenjit Keswani and Ms. Puja Singh, Advocates for Ms. Hemantika Wahi, Advocate.

Headnote:

repudiation - electricity supply - Indian Electricity Rules 1956, Consumer Protection Act, 1986 - The court dismissed the case as the evidence did not prove that the loss was caused due to constant power voltage fluctuation and erratic supply from the electricity board. The court also found that the complainant was negligent in keeping inflammable material near the electricity equipment, in contradiction with the Electricity Rules.

Fact of the Case:

The complainant filed a complaint against the electricity board for constant power voltage fluctuation and erratic supply, alleging that it caused a major fire in the factory premises, resulting in severe damage. The complainant sought compensation for the loss and damage caused to the machinery, stocks, and property.

Finding of the Court:

The court found that the evidence did not prove that the loss was caused due to constant power voltage fluctuation and erratic supply from the electricity board. The court also found that the complainant was negligent in keeping inflammable material near the electricity equipment, in contradiction with the Electricity Rules.

Issues: The main issues were whether the loss was caused due to constant power voltage fluctuation and erratic supply from the electricity board, and whether the complainant was negligent in keeping inflammable material near the electricity equipment.

Ratio Decidendi: The evidence did not prove that the loss was caused due to constant power voltage fluctuation and erratic supply from the electricity board. The complainant was negligent in keeping inflammable material near the electricity equipment, in contradiction with the Electricity Rules.

Final Decision: The court dismissed the case, finding that the evidence did not prove that the loss was caused due to constant power voltage fluctuation and erratic supply from the electricity board. The court also found that the complainant was negligent in keeping inflammable material near the electricity equipment, in contradiction with the Electricity Rules.

ORDER :

J.M. Malik, (P.M) - "Whether, the part repudiation or alleged part settlement of claim with insurance company, gives rise to a fresh cause of action against the third-party, i.e., the Gujarat Electricity Board (in short 'GEB'), now known as 'Dakshin Gujarat Vij Co. Ltd., to bring the case within the period of limitation, otherwise barred by time?". "Whether, the over/low voltage fluctuation can cause short circuit causing big loss under the facts and circumstances to be detailed herein with?". These knotty problems are to be adjudicated herewith.

2. The above said complaint was filed by M/s. National Flask Industries Ltd., the complainant, on 27.02.200,1 against the Dakshin Gujarat Vij Co. Ltd., (Formerly known as Gujarat Electricity Board) Balitha and its functionaries, viz., Executive Engineer and Deputy Engineer, OPs 1 to 3, respectively. The main allegation against the OPs was that there was constant power voltage fluctuation and erratic supply from the Dakshin Gujarat Vij Co. Ltd., (Formerly known as Gujarat Electricity Board). Many letters were also sent in this respect, but those did not ring the bell. M/s.National Flask Industries Limited, the complainant, transacts the business of manufacturing moulded and insulated plastic articles for household use at Plot No. A-2, Shed No. 502 in GIDC Industrial State, Sarigam. They have also taken the adjoining shed being Plot No. A-2, Shed No. 504 belonging to M/s Crown Industries, which is a sister concern of the complainant.

3. In the year 1987, the complainant, M/s.National Flask Industries Limited (originally known as M/s. Maruti Plastics Industries) at the time of commencement of its business) entered into an agreement dated 13.03.1987, with the then Gujarat Electricity Board-OP-1, for the supply of electricity to its premises, wherein OP-1 agreed to reserve for and to supply to the complainant, electrical energy upto a maximum of 300 KVA for Manufacturing Unit of the complainant. Clause 5 of the agreement stipulated that the electricity would be maintained by the supplier of the electrical energy of the above stated voltage and frequency at the said point of delivery. According to clause 14 of the agreement, reasonable precautions to ensure continuity of supply of power to the complainant/consumer were to be taken by the suppliers/OPs, except under certain 'force majeure' conditions. Copy of the said agreement has been placed on record as Annexure P-1.

4. The complainant used to face constant hardships owing to the fluctuating voltage in the electricity supplied by the then Gujarat Electricity Board to its premises. At times, the electricity fluctuation was so severe that the machinery and other electric gadgets installed in the said premises were required to be instantly shut down for extensive damage was caused to it. On each such occasion, the OPs were apprised of these facts. The complainant also made several representations to 'Sarigam Industries Association' (in short, 'SIA'). It also addressed letters dated 04.05.1993 and 07.05.1993 to the SIA, copies of which were produced on the record as Annexures P-2 and P-3, respectively. The OPs were to carry out a checking program but the same was not materialised. Further, another letter dated 02.07.1993 was sent to OP-1, copy of which has been placed on record as Annexure P-4.

5. The complainant received reply from OP-3 dated 07.07.1993 and another letter dated 27.06.1993 sent by OP-2. These letters reveal that necessary instructions were given to the Deputy Engineer, GEB, Sarigam as regards the action to be taken in future with such voltage fluctuation occurred, copies of which have been placed on record as Annexure P-5. However, no action was taken. The Complainant sent another letter dated 12.08.1993, wherein the grievance was again repeated. Copy of said letter has been placed on record as Annexure P-6. Although, one year had elapsed, yet, there was no improvement in the voltage situation. The situation became worse,

Click Here to Read the rest of this document