NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI
Ram Surat Ram Maurya, Presiding Member and Dr. Inder Jit Singh, Member
Anil Rana – Complainant
versus
M/s. ATS Estates Pvt. Ltd. and Anr. – Opp. Parties
Consumer Case No.234 of 2018
Decided on 5.1.2023
Consumer Protection Act, 1986 – S.21(1)(a)(i)[Consumer Protection Act, 2019 – S.58(1)(a)(i)] – Services – Real Estate – Allotment of Flat / Plot – Delayed Possession – Complaint Rank defaulter – cannot allege deficiency in service against the opposite party - The opposite party issued demand/ reminders dated 05.06.2014, 05.09.2014 and 05.12.2014 but the complainant did not respond. The complainant was a rank defaulter in payment of instalment from very beginning and failed to perform his obligation under the agreement - When the complainant was defaulter, he cannot allege deficiency in service against the opposite party. Clause 11(a) of the agreement was subject to timely payment of the instalment. Now the complainant demands for return of his money as such earnest money, which is 10% of Basic Sale Price would be liable to be forfeited under clause-5 of the agreement – Therefore, when interest is awarded as compensation then awarding additional compensation was not justified – Also, 9% interest, in case of refund, is just compensation – On facts, complaint is dismissed. [Paras 4 to 6].
Result: Compliant dismissed.
ORDER
Heard Mr. Aditya Parolia, Advocate, for the complainant and Mr. Sandeep Thukral, Advocate, for the opposite parties.
2. Anil Rana has filed above complaint, for directing the opposite party to (i) refund Rs.5768544/- with interest @18% per annum from the date of respective deposit till the date of actual payment, (ii) pay Rs.500000/-, as compensation for mental agony and harassment, (iii) pay Rs.100000/-, as litigation cost; and (iv) any other relief which is deemed fit and proper in the facts and circumstances of the case.
3. The complainant stated that M/s. ATS Estates Private Limited and M/s. ATS Infrastructure Ltd. (the opposite parties) were companies, registered under the Companies Act, 1956 and engaged in the business of development and construction of group housing project and selling its unit to the prospective buyers. M/s. ATS Infrastructure Ltd., who was owner of the project land, entered into development agreement dated 20.07.2007, with M/s. ATS Estates Private Limited, by which, the works of development and construction of the project and selling its unit were assigned to M/s. ATS Estates Private Limited (the opposite party). The opposite party launched a group housing project, in the name of “ATS Golf Meadows” at villages Sadhemajra and Madhopur, tehsil Dera Bassi, district S.A.S. Nagar, Mohali, in the year 2012 and made wide publicity of its facilities and amenities. The complainant booked a villa on 09.02.2012 and deposited booking amount of Rs.1900000/-. The opposite party allotted Villa no.-226, “ATS Golf Meadows-1”, area 500 sq. yard, total sale price of Rs.188/- lacs and executed Buyer’s Agreement in his favour on 09.03.2012. Under Payment Plan entire consideration was payable in 5 instalments. Last instalment was payable on offer of possession on 08.02.2013. The complainant deposited total amount of Rs.5768544/-. Clause-11(a) of the agreement provides that the opposite party will offer possession within 36 months from the date of allotment subject to timely payment of the instalments and force majeure reasons. Clause 11(c) provides a grace period of 120 days. Although due date of possession expired in September, 2015 but the opposite party did not offer possession. The construction was moving at very slow pace and was not likely to be completed till 2020. Therefore, the complainant, vide email dated 04.05.2016, requested to cancel his allotment of villa No.226 and transfer his money for allotment of Plot No.115-116, “ATS Golf Meadows-1” but the opposite party did not respond. Then this complaint was filed on 23.01.2018, alleging deficiency in service.
4. The opposite party filed its written reply on 26.04.2018 and contested the matter. The opposite party did not dispute, booking of the villa, allotment of the villa No.226, execution of Buyer’s Agreement dated 09.03.2012 and deposits made by the complainant. The opposite stated that allotment letter was issued on 21.07.2012 and received by the complainant on 23.07.2012 and the complainant has deliberately made false allegation in this respect. Annexure-1 of the agreement contained “Time Linked Payment Plan” under which Rs.6667750/- was required to be deposited till 14.05.2012. The complainant deposited Rs.19/- lacs, on 09.03.2012, Rs.1940052/-, on 01.08.2012 and Rs.1928492/-, on 31.07.2013 (total Rs.5768544/-) although till November, 2012, Rs.16067750/- was payable. The opposite party raised construction by expending Rs.58/- lacs. The complainant stopped payment of instalment as such the construction was not proceeded further. EDC was statutory charge. Delayed payment of EDC attracts 10% interest and 3% delayed penalty. The opposite party issued demand/reminders dated 05.06.2014, 05.09.2014 and 05.12.2014 but the complainant did not respond. The complainant was a rank defaulter in payment of instalment and failed to perform his obligation under the agreement. Clause 11(a) of the agreement was subject to timely payment of the instalment. The complainan
Possession timelines must be adhered to per contract and statutory obligations, with reasonable terms for earnest money forfeiture.
Real Estate – SC in cases of delay in offer of possession has ordered refund with 9% S.I. per annum which appears to be reasonable.
Housewife - Complainant is a housewife and there is nothing on record to show that she is engaged in any visible commercial activity.
Non-delivery of plot possession despite 75% payment, no agreement, and unilateral size reduction after 13 years constitutes deficiency in service and unfair trade practice; entitles refund with 9% in....
Residential buyers are consumers; builders liable for delayed possession sans force majeure proof; refund with interest from deposit dates.
Commercial purpose - At subsequent stage if the complainants offered the opposite party to buy back the flat or gave an advertisement for selling their flat as they found for themselves it difficult ....
Builders are liable for delay compensation until possession is offered, despite claims of force majeure.
Opposite parties cannot forfeit earnest money when they violate statutory provisions of advance acceptance under Real Estate Regulation and Development Act.
(1) Possession – Directing possession of the apartment without the requisite certificates would be inappropriate and not in the interest of justice.(2) National Commission – National Commission deter....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.