NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Sudip Ahluwalia, Presiding Member
Adyaraj S. – Complainant
versus
M/s. Patel Engineering Limited
and Anr. – Opp. Party
Consumer Case Nos.1938 and 1939 of 2019
Decided on 27.6.2024
Consumer Protection Act, 1986 – Section 21(1)(a)(i) [Consumer Protection Act, 2019 – Section 58(1)(a)(i)] – Real Estate – Allotment of Flat/Plot – Delayed Possession – It transpires that in the matter at hand, the primary relief sought by the Complainants is possession of the apartment initially promised by the Opposite Parties – However, considering the prolonged delay and failure of the Opposite Parties to meet their contractual obligations, the Complainants have also sought, in the alternative, a refund of the amounts deposited along with interest at the rate of 24% per annum – Upon perusal of the documents on record, it is evident that the Opposite Parties have not furnished any critical documentation to substantiate their claim that the project is complete and ready for possession – Specifically, they have failed to produce either an Occupancy Certificate or a Completion Certificate – The absence of these documents signifies that the project has not met the necessary regulatory and safety standards for habitation – Granting possession without such certifications would be imprudent and potentially hazardous, as it would contravene established legal and safety requirements for residential occupancy, besides, directing possession of the apartment without the requisite certificates would be inappropriate and not in the interest of justice – Therefore, National Commission determines that the Complainants are entitled to a refund of the amounts deposited for the purchase of the apartment – In deciding the appropriate rate of interest on the refund, it would be appropriate to give the rate of interest as in the previously covered matter as mentioned above – In that matter, the Commission determined an interest rate of 10% per annum to be fair and reasonable – Given the parallel nature of the issues in both cases, specifically, the prolonged delay and lack of delivery of the promised apartment, National Commission finds it equitable to apply the same interest rate in the present matter – Opposite Parties are directed to refund the amount deposited by the Complainant.[Paras 14 to 16].
Result: Complaints disposed off.
ORDER
These Consumer Complaints have been filed alleging deficiency in service and unfair trade practice on the part of the Opposite Parties, and seeking refund with ancillary reliefs.
2. The facts and question of law involved in these Complaints are similar in all material particulars except for minor variations in the dates, consideration amount and Flat numbers, therefore these Complaints are being disposed of by this common Order. However, for the sake of convenience, CC/1938/2019 is treated as the lead case and the facts enumerated hereinafter are extracted from this Complaint.
3. The factual background, in brief, is that in the year 2011, the Opposite Party No. 1 represented to the Complainants that they were developing a project named “Townsville” on land located at Sy No. 352, Hulimangala Village, Jigani Hobli, Anekal Taluk, Bengaluru, Karnataka, and claimed to be the exclusive owners of this land. The Complainants submitted an application for the allotment of a residential apartment on 15.03.2012 and was subsequently allotted Unit No. 31A in Block No. 16, with a total area of 3,477 Sq. Ft. and two parking spaces, as per the Allotment Letter dated 24.03.2012. Following the payment of Rs. 5,00,000/- to the Opposite Party No. 1, a Sale Agreement was executed on 26.06.2012, setting the total sale consideration at Rs. 1,76,33,762/-. According to the Agreement, the possession of the flat was assured by December 2013, with an additional grace period extending to June 2014. However, the Opposite Party No. 1, without prior notice to the Complainants, entered into a Development Agreement with Opposite Party No. 2. This agreement entailed constructing, marketing, selling, and realizing the sales proceeds of the unsold units and overseeing the completion and handover of the project. In adherence to the payment schedule, the Complainants made a total payment of Rs. 1,21,47,705/- through various means, including bank loans. Despite this, the construction was incomplete as of December 2013. The Complainants raised the issue with the Opposite Party No. 1 but did not receive an adequate response. It later emerged that Patel Realty (India) Limited, the original party to the Agreement, had undergone a Corporate Insolvency Resolution Process and was amalgamated with Opposite Party No. 1. Due to the continued non-delivery of the flat by 2019, the Complainants issued a Legal Notice dated 12.06.2019 to the Opposite Party No. 1. However there was no proper response. Aggrieved with the deficiency in service on the part of the Opposite Parties, the Complainants have filed the present complaint.
4. In view of the aforesaid facts, the Complainant prayed for the following reliefs -
“(A) Allow the present consumer complaint;
(B) Declare the act of the OPs of non - completion & delay in the project “Townville”, an act of “Deficiency in service” under Section 2 (g) of the Consumer Protection Act, 1986 & the Opposite Party and its Directors are liable to be accordingly punished accordingly;
(C) Direct the Opposite Parties deliver the possession of the subject flat along with interest at the rate @24% per annum till date of realization which at the date of filing of the instant Complaint is Rs. 1,76,33,762/- (Rupees One Crore Seventy Six Lacs and Thirty Three Thousand and Seven Hundred and Sixty Two Only)
(D) Direct the Opposite Parties for reimbursement of interest paid till 30.08.2019 towards Loan Financing of the subject Flat of the Complainant;
(E) Direct the Opposite parties to reimburse towards rentals to stay in alternate accommodation till the possession is finally granted to the Complainant;
(F) Direct the Opposite Parties to furnish Rs. 25,00,000/-( Rupees Twenty Five Lacs Only) towards Mental Agony faced by the Complainant;
(G) Direct the Opposite Party to reimburse amount towards litigation cost incurred by the Complainant to the tune of Rs. 5,00,000/- (Rupees Five Lacs Only);
(H) In the interim, this Hon’ble Commission be
(1) Possession – Directing possession of the apartment without the requisite certificates would be inappropriate and not in the interest of justice.(2) National Commission – National Commission deter....
For failure of delivery of possession of flats within the stipulated, refund of amount directed.
Specified time - Therefore when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable Interes....
(1) Remedies - The remedies under the Consumer Protection Act, 1986 are in addition to the remedies available under special statutes.(2) Refund of Money - Buyer cannot be made to wait indefinitely fo....
Installment – Once the instalments were collected, the buyers are sought to be non-suited on a multitude of grounds, primarily the liability of the Government in not providing infrastructure and to c....
Valid Possession – Mere completion of structure cannot be said that the Apartment is ready for valid possession.
Earnest Money Clause – Earnest Money Clause in the Agreement being wholly one-sided and unjustified constitutes an unfair trade practice and therefore, is not binding upon the Complainant.
(1) Bald assertion – In the absence of any evidence being brought on record, merely a bald assertion that the project was delayed due to in action by the Government or its statutory organisations and....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.