2012 Supreme(Guj) 415
GUJARAT HIGH COURT
Hon’ble Mr. Justice Jayant Patel & Hon’ble Mr. Justice C.L. Soni
State of Gujarat & Anr.
Versus
Narendra R. Patel
First Appeal No. 2626 of 2002—Decided on 01/09/2012
Important Points
Whether in the facts and circumstances of the case present suit is maintainable.
Subject
Contract Disputes - CONSTRUCTION CONTRACT DISPUTE
Act Referred
LIMITATION ACT : Art.14, Art.56, Art.56(6), Art.56(7)
Headnote
Held :
The pleadings in the first suit, if not produced on record, plea as to the bar to the second suit cannot be raised. It is also held that subsequent suit must be in respect of same cause of action on which previous suit was based. [Para 16]
In the case on hand, cause for filing the present suit has arisen for the contractor because of filing of appeal by the appellant against the order appointing arbitrator in the suit filed by the contractor. The respondent plaintiff has clearly stated about the events which had taken place in the cause of action itself and has further stated that in order to save the time limit, suit was required to be filed. The cause of action in the present suit therefore cannot be said to be the same cause of action on which the previous suit was based. It appears that the respondent was concerned with the violation or infraction of his right of making claims under the contract and, therefore, necessity had arisen for filing the second suit. Court is therefore of the opinion that the second suit was not barred at all by the provisions of Order 2, Rule 2 especially when the first suit was subsequently permitted to be withdrawn at the appellant stage though unconditionally. [Para 17]
(b) Limitation Act, 1963 (Central Act 36 of 1963) — Articles 14 and 56 — Suit based on building contract — Filed after three years of issuance of notice by contractor — When final bill of the work under contract submitted — Maintainability — Finding of — The present suit is based on a building contract containing Clauses (6) and (7) in the standard form — It is therefore governed by Article 56 and starting point of limitation would be the date when the Engineer-in-charge issues the certificate of competition and when final measurements are made — That apart on application of respondent arbitrator was appointed on 07.01.1989 — Against the order appellant filed first appeal and stay was granted against that order of appointment of arbitrator — The contractor would not have filed the suit if appointment of arbitrator was not challenged by appellant by filing appeal — In the facts cause of action for filing the civil suit actually arose after the appellant preferred appeal before High Court challenging the order of appointment of arbitrator in year 1989 — These facts clearly shows that suit filed by respondents plaintiff on 28.08.1991 can not held time barred — It is within limitation period of three years.
Held :
Where the suit is based on a building contract containing Clauses (6) and (7), in standard form, it is governed by Article 56 and the starting point of limitation would be the date when the Engineer-in-charge issues the certificate of completion and when the final measurements are made.
The contractor would not have filed the suit for civil action if the appointment of arbitrator was not challenged by the appellant by filing the first appeal and, therefore, in fact, cause of action for filing the civil suit had actually arisen after the appellant had preferred appeal before the High Court challenging order of appointment of arbitrator in the year 1989 when the First Appeal No. 841 of 1989 was preferred. These bundle of facts have been clearly stated by the contractor in the suit on hand. We are therefore of the opinion that the time would start running for filing the suit in the civil Court by the contractor from the date of filing of the first appeal by the appellant before the High Court in the year 1989 and if we take the date of order for appointment of arbitrator on 7.1.1989 7.1.1989 (sic) and the date of the suit on hand, 28.8.1991, the suit can be said to have been filed within time limit. Court accordingly hold that the suit of the contractor was filed within the prescribed period of limitation.
[Para 18]
(c) Government Contract — Interest on amount found due — Admissibility — It appears before filing suit contractor had issued notice on 28.08.1987 and there after under Section 80 on 16.11.1989 — But suit came to be filed on 28.08.1991 i.e. almost after a period of one year and two months — There was no reason for not filing the suit immediately after two months of issuance of notice — Contractor can not be allowed to take advantage of delay occurred for his own fault in the circumstances Court allowed interest from 28.08.1987 till 31.01.1990 to respondent on the total amount of Rs. 4,22,973.00 found due.
Held :
It appears that before filing the present suit, contractor had issued notice under Section 80 of the Code on 16.11.1989, still however, present suit came to be filed on 28.8.1991 i.e. almost after a period of one year and two months. There was no reason for not filing the suit immediately after issuance of notice under Section 80 of the Code, meaning thereby, after two months from the date of issuance of the notice under Section 80 of the Code. Contractor cannot be permitted to take advantage of delay occurred for his own fault for not filing the suit immediately after expiry of two months from the date of notice under Section 80 of the Code, which could be 31.1.1990. Therefore, we are of the view that the learned trial Judge was not justified in granting interest from 28.8.1987 to 28.8.1991, the date on which the suit was filed. In our view, the contractor would be entitled to interest from the date of notice 28.8.1987 till 31st January, 1990. [Para 20]
Law Laid Down :
If the pleadings in the first suit not produced on record plea as to bar to the second suit cannot be raised.
Appearance :
Ms. Moxa Thakkar, AGP for the Appellants No. 1 - 2.
Mr. B.S. Patel, for the Defendant No. 1.
C.L. Soni, J.—This appeal under Section 96 of the Code of Civil Procedure, 1908 [“the Code” for short] is directed against the judgment and decree dated 30.10.2001 passed by the learned Civil Judge (S.D.) Bharuch in Special Civil Suit No. 150 of 1991 whereby the respondent is held entitled to recover Rs. 16,88,812.00 from the appellants.
2. The facts which are noticed from the record of the case are stated as under:
The respondent was awarded public contract for work of Minor and Sub Minor of Narwadi Distributory from Ch. 0 to 4050 Mtrs. of Choadway Irrigation Scheme. As per the agreement, the work was to commence from 10.4.1986and to be completed within eight months i.e. on or before 9.12.1986. The tender was accepted for Rs. 6,46,082.82. It appears that since the dispute had arisen between the parties, the respondent had issued notice for appointment of arbitrator to the appellants under clause 30 of the Agreement and subsequently filed suit under Section 20 of the Arbitration Act, 1940 for appointment of arbitrator. The suit was allowed and the order for appointment of arbitrator was passed which was challenged by the respondent by filing appeal before this Court. The respondent therefore filed the above referred Special Civil Suit in the Court of the learned Civil Judge (S.D.) Bharuch for recovery of Rs. 28,89,000.00 with interest at the rate of 18 per cent per annum from the appellants. The suit was filed by the respondent mainly on the ground that the appellant did not make available the line out for work, that the canal line was passing through various ground level; that the canal land was not acquired by the department and was also not acquired at the time of acceptance of tender. That the appellant had failed to provide drawings and designs of the work contract to the respondent. That the respondent was not handed over possession of the land for carrying out the work.
3. In the suit, the respondents claimed following amounts:
Claim No. 1 : Rs. 2,22,683.00 Amount remained outstanding
towards the final bill.
Claim No. 2 : Rs. 8,74,614.00 Amount claimed for revised rate.
Claim No. 3 : Rs. 1,45,184.00 Amount of extra work in item No. 6.
Claim No. 4 : Rs. 27,123.00 Amount claimed for work executed
in item No. 10.
Claim No. 5 : Rs. 96,840.00 Amount on account of idle labour
charges.
Claim No. 6 : Rs. 42,134.40 Amount on account of extra rate for
loading and unloading for item No. 10.
Claim No. 7 : Rs. 34,657.00 Amount on account of item No. 12
Claim No. 8 : Rs. 3,24,000.00 Amount on account of spreading of
hard murram.
Claim No. 9 : Rs. 2366.00 Amount on account of loss for not
taking measurement.
Claim No. 10 : Rs. 1,00,000.00 Amount on account of loss suffered
on tender quantity.
Claim No. 11 : Rs. 70,000.00 Amount on account of over head
and over stay.
Claim No. 12 : Rs. 13,210.00 Amount on account of payment
made in hard murram.
Claim No. 13 : Rs. 1400.00 Amount on account of time limit
deposit.
Claim No. 14 : Rs. 11097.00 Amount on account of security
deposit.
4. Above amounts come to Rs. 19,65,308.40 paisa. Respondent has further claimed interest on the above said amounts at the rate of 12 per cent per annum from 28.8.1987 i.e. date of notice till the date of filing the suit i.e. 28.8.1991. The amount come to Rs. 28,89,000.00, as claimed in the suit.
5. The suit was resisted by the original defendants appellants herein by filing written statement at Exh. 61.
6. Following issues were framed at Exh. 24 and answered as under:
Issues:—
(1) Whether the plaintiff proves that the defendant No. 2 had invited tenders publicly on behalf of the State of Gujarat for the work of Minor and Sub Minor of Narwadi Distributory from CH-O to 4050 Mts. of Chopadway Irrigation Scheme and the plaintiff filed up the tender and his tender was being accepted by the defendants as alleged?
(2) Whether the plaintiff proves that after his acceptance of tender agreement No. B-1 of 1986- 87 was entered into between the plaintiff and defendant and he ha