2017 Supreme(Guj) 535

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
M.R. Shah and B.N. Karia, JJ.
Hindustan Dorr Oliver Limited – Appellant
Vs.
Gujarat State Fertilizers and Chemicals Limited – Respondent
First Appeal No. 891 of 2017 and Civil Application No. 3082 of 2017 in First Appeal No. 891 of 2017
Decided On : 09-03-2017

Subject

Banking and Finance Law - BANK GUARANTEE

Act Referred

ARBITRATION AND CONCILIATION ACT : S.17, S.9
CONTRACT ACT : S.55

Headnote

Arbitration & Conciliation Act, 1996 Section 9, 17 -learned Judge, Commercial Court, Vadodara in Commercial Civil Miscellaneous Application No. 112 of 2016, by which, learned Commercial Court has rejected the said Application submitted by the original applicant under Section 9 of the Arbitration & Conciliation Act, 1996 and has refused to grant interim injunction restraining the respondent herein [original opponent] from en-cashing the respective bank guarantees, the original applicant has preferred the present Appeal. Facts leading to the present Appeal in nutshell are as under: opponent herein, a public sector undertaking, was in need of Engineering Procurement and Construction [EPC] contractors for establishing production facilities for 2000 MTPY Water Soluble Fertilizer, NPX 19-19-19 Grade and Micronutrient Mixture with required bagging along with additional bagging facilities for 10000 MTPY other grades of WSFs lump sum turnkey [LSTK] basis. That thereafter, pursuant to the tender process, the respondent expressed their intention of awarding the contract to the applicant and issued a Letter of. The original applicant [hereinafter referred to as, "the Contractor"] accepted the said Letter of Intent vide communication. That, the said Letter of Intent came to be amended by the original respondent vide letter learned Commercial Court initially granted ex parte injunction restraining the original opponent from invoking/encashing the bank guarantees. That thereafter, while deciding Application Exh. 9, the learned Commercial Court passed an order disposing of the said application and thereby continued ex parte ad interim injunction till the applicant approaches the learned Arbitral Tribunal and obtains appropriate order Act. Feeling aggrieved and dissatisfied with the order passed by the learned Commercial Court, Vadodara disposing of the said Application without deciding the same on merits and continuing earlier ad interim injunction till the applicant approaches the learned Arbitral Tribunal, the original respondent preferred First Appeal before this Court and this Court quashed and set-aside the order passed by the learned Commercial Court disposing of Section 9 application and directed the learned Commercial Court to decide and dispose of the Application preferred under Section 9 on merits. That thereafter, by the impugned order, the learned Commercial Court has rejected Section 9 Application submitted by the original applicant and has refused to continue injunction restraining the respondent from encashing the respective bank guarantees. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the learned Commercial Court, Contractor has preferred the present First Appeal -Held Now so far as submission made on behalf of the Contractor that time is not the essence of the contract since it was extended from time to time, and therefore, time cannot be said to be the essence of the contract, and therefore, the Owner is not entitled to any loss or damages and that the submissions made on behalf of the Owner that despite the above, considering Section 55 of the Contract Act, the Owner shall be entitled to compensation is concerned; as observed hereinabove, at this stage, the aforesaid dispute is not required to be considered. Even other submissions made by the learned counsel appearing on behalf of the respective parties with respect to the amount due and/or retained by the owner and/or whether there was delay on the part of the Contractor and/or Owner are not required to be considered at this stage. While considering the Application and while considering whether by way of interim measure under Section 9 of the Arbitration Act, there shall be injunction against invocation of the bank guarantee or not.In view of the above and for the reasons stated above, the present First Appeal deserves to be dismissed and is accordingly dismissed to costs -Appeal is Dismissed.

Advocates Appeared:
For the Appellant :R.S. Sanjanwala, Sr. Advocate and Pranav M. Trivedi, Advocate for Singhi & Co., Advocates
For the Respondent:K.S. Nanavati, Sr. Advocate for Nanavati Associates

JUDGMENT :

M.R. Shah, J.

1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 16th February 2017 passed by the learned Judge, Commercial Court, Vadodara in Commercial Civil Miscellaneous Application No. 112 of 2016, by which, the learned Commercial Court has rejected the said Application submitted by the original applicant under Section 9 of the Arbitration & Conciliation Act, 1996 and has refused to grant interim injunction restraining the respondent herein [original opponent] from en-cashing the respective bank guarantees, the original applicant has preferred the present Appeal.

2. Facts leading to the present Appeal in nutshell are as under:

2.1 The opponent herein, a public sector undertaking, was in need of Engineering Procurement and Construction [EPC] contractors for establishing production facilities for 2000 MTPY Water Soluble Fertilizer, NPX 19-19-19 Grade and Micronutrient Mixture with required bagging along with additional bagging facilities for 10000 MTPY other grades of WSF's lump sum turnkey [LSTK] basis. That thereafter, pursuant to the tender process, the respondent expressed their intention of awarding the contract to the applicant and issued a Letter of Intent dated 3rd November 2012. The original applicant [hereinafter referred to as, "the Contractor"] accepted the said Letter of Intent vide communication dated 5th November 2012. That, the said Letter of Intent came to be amended by the original respondent vide letter dated 27th December 2012 and pursuant thereto, the Contractor entered into a contract on 25th April 2013 for the said facilities on LSTK basis. As per the terms of the contract, the contract was to be executed and completed within a period of fifteen months ie., on or before 30th July 2014. That, the contract was awarded for a total amount of Rs. 38,29,00,000/-. As per the terms of the contract, the Contractor was required to furnish advance Bank Guarantee and a Performance Bank Guarantee in favour of the original respondent for the sum of Rs. 5,17,17,726/- and Rs. 3,82,90,000/- respectively. It is an admitted position that as per the terms and conditions of the contract, the Contractor was paid in advance a sum of Rs. 3,82,90,000/-. Accordingly, the Contractor furnished two Bank Guarantees viz., [i] an Advance Bank Guarantee, bearing No. 002812GFIN0058 and [ii] Performance Bank Guarantee, bearing No. 0119JFJBG120078 through its Bankers on 20th December 2012. That thereafter, it appears that disputes arose between the parties as the contractor failed to execute/complete the contract within the stipulated time and according to the original respondent because of delay in completion of the project, the original respondent had suffered huge loss. However, it is the case on behalf of the contractor that during the course of execution of the contract, because of irregularities in release of the payments in time by the respondent, it was facing financial crunch, and therefore, the project could not be completed within the time limited. That thereafter, at the request of the Contractor, the time was extended from time to time. However, thereafter, the respondent terminated the contract and also claimed damages/loss caused because of delay in completion of the project. As per the terms of the contract, the parties initiated arbitration proceedings, however, till the contractor approached the learned Commercial Court by way of preferring an Application under Section 9 of the Arbitration & Conciliation Act, the Arbitral Tribunal was not constituted. In the meantime, as the original respondent was to encash the aforesaid respective bank guarantees, and therefore, the Contractor submitted aforesaid Commercial Civil Misc. Application before the learned Commercial Court at Vadodara under Section 9 of the Arbitration & Conciliation Act for interim measures and prayed for the following reliefs:

"[A] The Hon'ble Court be pleased to grant interim measures of protection restraining the resp