IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
A.P. THAKER, J.
Uday Builders – Appellant
Versus
Gujarat Industrial Development Corporation – Respondent
First Appeal No. 5266 of 1999
Decided On : 25-01-2021
Code of Civil Procedure, 1908 -Section 96 - Civil Suit whereby the plaintiff-appellant's suit has been partly allowed as well as counter claim put up by the defendant-respondent is also allowed by the learned City Civil Court – Appeal –
Finding of the Court: Oral and documentary evidence that the plaintiff has not carried out the contract in accordance with the Agreement between the parties and, therefore, the defendant was within its right to direct the plaintiff to suspend the work for the specific reason. It also reveals that there is specific admission on the part of the defendant about the change of zone and about the suspension of the work during the heavy rain would not help the plaintiff in as much as the contractual agreement specifially provided for such kind of contingencies and there is a specific bar to demand any amount towards any loss or loss of profit in such circumstances -Court is of the considered opinion that the learned trial Court has properly appreciated the facts and applied the legal aspects thereof and it has not committed any error of facts and law in passing the impugned judgment and decree
Result: Appeal is liable to be dismissed
JUDGMENT :
A.P. THAKER, J.
1. The present Appeal has been filed under the provisions of Section 96 of the Code of Civil Procedure, 1908 against the judgment and decree dated 20.11.1998 passed in Civil Suit No. 106 of 1988 whereby the plaintiff-appellant's suit has been partly allowed as well as counter claim put up by the defendant-respondent is also allowed by the learned City Civil Court No. 18.
2. Being aggrieved and dissatisfied with the impugned judgment and decree, the original plaintiff has filed the present appeal on the ground that the trial Court has not appreciated the oral as well as documentary evidences rendered by both the sides in proper perspective and has committed serious error in exercising the jurisdiction vested in it and has exceeded its jurisdiction. It is also contended that the learned trial Court has wrongly come to the conclusion that the Appellant is guilty of breach of contract. According to him, the learned trial Court ought to have held that the plaintiff-appellant has not left the work unfinished. It is also contended that the contention of the plaintiff regarding non-supply of cement and steel by the defendant-respondent is ought to have been believed by the trial Court and thereby has committed serious error. It is further contention of the appellant that though there was no item-wise programme given by the respondent to the plaintiff, this fact is not considered by the learned trial Court and has wrongly come to the conclusion that due to alleged breach on the part of the appellant, contract could not be completed. It is also the contention that the trial Court has wrongly relied upon the various Clauses of the contract and has wrongly held against the plaintiff that he was not ready and willing to perform his part of the contract. The other contention is that in granting relief to the respondent, in a counter-claim is also not proper. It is further submitted that the impugned judgment and decree passed by the learned trial Court to the extent which is not allowed by the trial Court, be set-aside and at the same time, the counter-claim put up by the respondent be dismissed.
3. Heard Mr. K.G. Sukhwani, learned advocate for the appellant and Mr. Uday Bhatt, learned advocate for the defendant at length through video-conferencing.
4. Mr. K.G. Sukhwani, learned advocate for the appellant has vehemently submitted that the plaintiff has filed suit before the trial Court for damages as there was a breach of contract by the respondent. He has also contended that the defendant has not provided the site as well as not supplied requisite material and other items as per the Clause of the contract and due to the delay on the part of the defendant, the plaintiff could not complete the work of the contract in stipulated period. According to him, the contract was repudiated by the defendant. He has also contended that the plaintiff has put up his case regarding return of security as well as loss of profit and other ancillary benefit. He has further submitted that though there was ample evidence on record to substantiate the claim of the plaintiff, the trial Court has not properly appreciated and has wrongly held against the plaintiff and has wrongly observed that at the instance of the plaintiff, the contract has been breached. He has also contended that the counter-claim put up by the defendant has not basis and it ought to have been rejected by the trial Court instead of granting it. He has submitted that considering the material placed on record, the impugned judgment and order of the trial Court granting the counter-claim of the defendant and rejecting the amount on various heads in favour of the plaintiff, be seta-side and entire suit amount be awarded to the appellant-plaintiff and the counter-claim be rejected. He has also prayed that cost be awarded to the respondent throughout.
5. Per contra, Mr. Uday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.